RESOLUTION R-02-1942
A RESOLUTION AUTHORIZING THE APPROVAL OF CHANGE ORDER 3 TO THE
CONSTRUCTION CONTRACT FOR THE COLLEYVILLE JUSTICE CENTER WITH
CMPA, INC.
WHEREAS, the construction contract with CMPA, Inc., was approved by Council on
December19,2000;and
WHEREAS, construction started in mid-April of 2001; and
WHEREAS, Colleyville City Council approved Change Order 1 and 2 on August 8,
2001; and
WHEREAS, additional modifications to the building are required.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
COLLEYVILLE, TEXAS:
Sec. 1.
THAT $52,719.96 for the construction contract Change Order 3 with
CMPA, Inc., for the Colleyville Justice Center, is hereby approved.
AND IT IS SO RESOLVED.
PASSED BY A VOTE OF S AYES, 0 NAYS, AND 0 ABSTENTIONS ON
THIS THE /ItM DAY OF a~ 2002.