HomeMy WebLinkAboutCity Council-Agenda Packets-9/16/2013City of Colleyville Page 1
City of Colleyville
City Council Worksession
Agenda
City Hall
100 Main Street
Colleyville, Texas 76034
817. 503.1000
www.colleyville.com
Monday, September 16, 2013
6:00 p.m.
Executive Conference Room
Third Floor, City Hall
5:30 P.M. - BOARD, COMMISSION, AND COMMITTEE APPLICANT INTERVIEWS
1. CALL TO ORDER
2. PRESENTATION AND DISCUSSION
2a Presentation on the status of the SH26/Colleyville Boulevard reconstruction
project and discussion of options to accelerate completion of the project
3. EXECUTIVE SESSION - In accordance with Texas Government Code
Chapter 551, Subchapter D
Section 551.087 – Economic Development - Discuss or deliberate regarding
commercial or financial information that the City has received from business
prospects that the City seeks to have locate, stay, or expand in the City and with
which the City is conducting economic development negotiations; deliberate the
offer of a financial or other incentive to a business prospect
4. ADJOURNMENT
I hereby certify this agenda was posted on City Hall bulletin boards Friday, September 13,
2013 by 5:00 p.m.
Amy Shelley, TRMC
City Secretary
Any matter on this agenda may, at the discretion of the governing body, be opened for
public comment and discussion.
If you plan to attend this public meeting and have a disability that requires special
accommodations, please advise the City Secretary at least 48 hours in advance at
817.503.1133, and reasonable accommodations will be made to assist you.
City of Colleyville Page 1
City of Colleyville
Colleyville City Council
Worksession
Agenda Briefing
City Hall
100 Main Street
Colleyville, Texas 76034
www.colleyville.com
Agenda Number 2a Agenda Date 09/16/2013 Number
Type Presentation
Department Public Works
Title
Presentation on the status of the SH26/Colleyville Boulevard reconstruction project and
discussion of options to accelerate completion of the project
Explanation
Reconstruction of SH26 (Colleyville Boulevard) in Colleyville, began with the award of a
construction contract by the Texas Department of Transportation (TxDOT) to AUI, Inc.,
in August of 2011. The initial contract is for reconstruction of SH26 from Pool
Road/Brumlow Road to approximately 1,000 feet south of John McCain Road, and is
expected to be complete in 2014.
The next phase of reconstruction, from 1,000 feet south of John McCain Road to Hall-
Johnson Road, is scheduled to be bid by TxDOT in September of 2014. Plans for this
section of the project are complete, and utility relocations are underway and scheduled
to be competed by January 2014. Funding for this phase is in place.
The remainder of the project is unfunded and cannot move forward until funding is
secured. The purpose of this worksession is to discuss possible options to fully fund
the remainder of the project, and will include presentations by City staff and Michael
Morris, the Director of Transportation for the North Central Texas Council of
Governments (NCTCOG).
Attachments
1.SH26/Colleyville Boulevard Reconstruction Project Presentation
SH26/Colleyville Boulevard
Reconstruction Project
City Council Worksession
September 16, 2013
Overview of Presentation
•Project Update
•Funding Status
•Presentation by NCTCOG
•Discussion of options to complete
construction
•Phase I Road Construction (Pool
Road/ Brumlow Road to John McCain
Road)
–Contract awarded by TxDOT in August 2011
–Construction started July 2012
•394 “working days”
–Six lane divided roadway
–Estimated completion date Spring 2014
•Phase II Road Construction (John
McCain Road to Hall-Johnson Road )
–Six lane divided roadway
–Utility relocations underway
–Estimated bid date – September 2014
–Funding in place for FY2014
•Phase III (Hall-Johnson Road to
Brown Trail)
–Six lane divided roadway
–Utility relocations underway
–No funding identified
•Phase IV (Brown Trail to Cheek-
Sparger Road
–Six lane divided roadway
–Utility relocations not started
–No funding identified
•Water and Sewer Utility Relocations
–Phase I (north city limits to south of John McCain Road
•Completed in late 2011
•$ 213,150.39
•2,200 linear feet of new water line
–Phase II (John McCain Road to Centerpark Drive)
•Started on June 3, 2013
•Contract awarded: $3,560,188.50
•18,500 linear feet of water line and 3,000 linear feet of sewer line
–Phase III (Centerpark Drive to Cheek-Sparger Road)
•Pending Road Construction
•Estimated cost $1,692,000
•4,700 linear feet of new water line and 3,400 linear feet of sewer line
•Phase II SH26 Water and Sewer Utility
Relocation Project
–John McCain Road to Centerpark Drive
•Currently under construction
•Contract Cost of $3,560,188.50
•Project includes 18,500 linear feet of water
line and 3,000 linear feet of sewer line
•Estimated completion – June 2014
•Currently installed 9,000 linear feet of
waterline
•Enhancements for Phase I SH26
reconstruction
–Green Ribbon Funding
•La terra Studio landscape plans for median and
parkway have been approved by TxDOT and
change order for construction has been executed
–Signal Poles
•Working with Tx DOT to finalize a change order
–LED Backlit Signage
•Working with TxDOT to finalize a change order
–Hardscape (pavers, crosswalks, etc.)
•Working with TxDOT to finalize a change order
SH26 Traffic Counts*
•2008 – 33,000 vpd
•2009 – 25,000 vpd
•2010 – 23,000 vpd
•2011 – 22,000 vpd
*Vehicles Per Day (vpd) from TxDOT
Status of Project Funding
•Phase I (Pool Road/Brumlow Road to John
McCain Road) funded and under construction
•Phase II (John McCain Road to Hall-Johnson
Road) funded and scheduled for letting in
September 2014
•Phases III (Hall-Johnson Road to Brown Trail)
and IV (Brown Trail to Cheek-Sparger Road)
not funded
CURRENTLY FUNDED/UNDER
CONSTRUCTION
11730/CSJ 0363-01-111
From SH 114 to Brumlow/Pool
ROW Completed – 10/2008
Design Complete – 05/2010
Utilities Complete – 09/2011
Under Construction – Let 07/2010
Est. Comp. Date – 07/2013
Scope: Widen 4 lane with continuous
turn lane to 6 lane divided
Funding:
$11,572,675 TxDOT PE & ROW
$11,897,197 Federal (ARRA)
$479,799 Local
$23,949,671 Total
SH 114/
121
DRAFT
Source: North Central Texas Council of Governments, September 2013
CURRENTLY FUNDED/UNDER CONSTRUCTION
11153.1/0363-01-136
SH 26 from Brumlow/Pool to John McCain
ROW Completed – 10/2012
Design Complete – 06/2011
Utilities Complete – 06/2012
Under Construction – Let 08/2011
Est. Comp. Date – 08/2014
Scope: 4 to 6 lanes urban, replace bridges, & upgrade
signal system, incl. trail crossing over Big Bear Creek
Costs:
$3,654,000 PE/ROW
$196,000 Utilities
$11,414,000 Const
$15,264,000 Total
Funding:
$3,654,000 TxDOT PE/ROW
$4,000,000 Tarrant County
$5,100,000 City of Colleyville
$2,008,000 Federal (STP-MM)
$502,000 State Match to STP-MM
$15,264,000 Total
OPTION 1: CURRENTLY FUNDED
11153/0363-01-114
From John McCain to Hall-Johnson
ROW Completed – 08/2012
Design Complete – Est. 06/2011
Utilities Complete – Est. 09/2013
Est. Let Date – 08/2014
Scope: Widen from 4 to 6 lanes urban,
replace bridges, & upgrade signal system
Costs:
$1,701,152 PE
$8,042,848 ROW
$3,625,000 Utilities
$11,152,728 Const
$24,521,728 Total
Funding:
$9,744,000 TxDOT PE/ROW Funds
$3,625,000 Local (for utilities)
$10,926,115 Federal (STP-MM)
$2,731,528 State Match to STP-MM
$27,026,643 Total
UNDER CONSIDERATION
11153.2/0363-01-139
From Hall-Johnson to Brown
Trail
ROW Completed – 10/2012
Design – 06/2011
Utilities Complete – Est. 09/2014
Est. Construction – Unknown
Scope: 4 to 4 lanes urban,
intersections, replace bridges, &
upgrade signal system
Costs:
$3,451,000 ROW
$886,608 Utilities
$13,652,711 Const
$17,990,319 Total
Estimated ROW and utility costs
from Hall-Johnson to Brown
Trail are prorated with 11153.3.
Funding:
$3,451,000 TxDOT ROW Funds
UNDER CONSIDERATION
11153.3/0363-01-139
From Brown Trail to Cheek-
Sparger
ROW Completed – 10/2012
Design – 06/2011
Utilities Complete – Est.
09/2014
Est. Construction – Unknown
Scope: 4 to 4 lanes urban,
intersections, replace bridges, &
upgrade signal system
Costs:
$3,451,000 ROW
$805,392 Utilities
$5,000,000 Const (est.)
$9,256,392 Total
Estimated ROW and utility costs
from Brown Trail to Cheek-
Sparger are prorated with
11153.2.
Funding:
$3,451,000 TxDOT ROW Funds
Creek
+$1M Commitment
from Commissioner
Fickes and
+$1.59M in
Transportation
Enhancement Funds
Grapevine section first discussed in 1994, funding added in 2006
Colleyville project selected and funded in 1999
–TxDOT design began in approximately 2002
•Design plan has undergone several changes since that time
•In 2010, section from Brumlow/Pool to John McCain split out
–TxDOT completed environmental clearance in 2005
–Right-of-Way Acquisition – Complete
–Utilities – Underway
Insufficient funding for remaining sections (from Hall-Johnson to Cheek-Sparger)
Decisions needed regarding use of remaining funds
MAP-21 (current transportation funding bill) authorizes
funding through September 30, 2014
–TxDOT estimates revenues into the future, but federal authorization
not yet available past FY 2014
Regional Transportation Council (RTC) has programmed all
STP-MM funds (SH26 funding source) through FY 2017
New projects added in last year or so have largely been
legacy projects with strong tolling or leveraging components
TxDOT proposing to turn back roads (including SH26 to
local agencies)
Legislature approved voter referendum for November 2014
(If approved by voters, 1/3 of funds would likely go to DFW,
but not until 2015 or later and only under certain conditions.)
Costs are adjusted for “total project cost” and “year of expenditure” consistent with SAFETEA-
LU planning requirements. “Actual Dollars” reflects the effect of inflation over time.
Major Expenditure Type
Mobility 2035 -
2013 Update
(Financially-
Constrained)
Regional
Needs
Operations & Maintenance
Operations, Maintenance, Rehabilitation, Safety, Facility
Reconstruction, Transit Operations
$28.9
$119.2
(13,000 lane miles
to be
rehabilitated)
Non-Capacity Improvements
Congestion Management Process, Air Quality &
Environment, Bicycle & Pedestrian, Sustainable
Development, Transportation Enhancements
$8.7 $9.6
Capacity Improvements
Freeway, Tollway, HOV, Managed System, Rail Capital,
Bus, Paratransit, Regional Arterial System, Other Arterials,
Goods Movement
$61.1 $266.5
(22,500 additional
lane miles needed)
Total $98.7 $395.3
$8.3 Billion Dollars in 2013-2016 TIP
–57% from highly leveraged projects (tolls,
managed lanes) and public-private partnerships
–26% from regional toll revenues
–17% from traditional federal, State, and local
sources
Thus, 83% of revenue is from non-traditional sources
Expectations that traditional funding options are or will be available must be adjusted
Funding currently available in FY 2014
–TxDOT’s FY is September 1, 2013 through August 31, 2014
–If project cannot let by August 2014, it will have to be pushed
back
If changes are desired to project scope, decisions should be made
in mid to late October 2013
–Engineering plans would need to be revised (six month
duration)
–TIP listing would need to be updated (six month duration)
–Deadline to submit next round of TIP modifications is
October 25, 2013
Option 1 – Maintain Status Quo
–Section from John McCain to Hall-Johnson remains funded (4 to 6 lanes)
–No funding for additional sections
Option 2 – Shift Funding to the Southwest
–Remove funds from John McCain to Hall-Johnson section
–Move funds to section from Hall-Johnson to Brown Trail (4 to 4 lanes with build out at intersections)
Option 3 – Utilize Pass-through Finance Agreement with TxDOT
–Build section from Hall-Johnson to Brown Trail first using local funds
–Leave federal funds to build additional sections
–Use funds repaid by TxDOT to build additional sections
■Glade Road
■Centerpark Drive
■Brumlow Avenue/Pool Road
■Hall-Johnson Road
■John McCain Road
■Brown Trail
■Cheek-Sparger Road
■Tinker Road
Intersection
Development
Score
Bike and
Pedestrian
Score
Land Use
Score
Combined
Score
Cumulative
Rank*
Brumlow/ Pool 1 3 3.94 7.94 3
John McCain 1 3 2.47 6.47 5
Tinker 1 0 2.50 3.50 8
Hall-Johnson 3 0 3.74 6.74 4
Glade 4 3 3.93 10.93 1
Center Park 3 2 3.26 8.26 2
Brown Trail 2 1 2.48 5.48 6
Cheek-Sparger 2 0 2.91 4.91 7
*Each intersection is given a ranking of 1-8, with 1 representing the greatest
need/benefit.
Intersection
Location
Traffic Measures
Total
Volume 1
SH 26
Left
Turns2
SH 26
Right
Turns2
Minor
Arterials
Left Turns2
Minor
Right
Turns2
Speed
on
SH 263
TOTAL
(Weighted
Ranks)
Brumlow/ Pool 1 1 1 1 1 3 1
John McCain 6 7 5 5 6 6 7
Tinker 8 8 8 8 8 8 8
Hall-Johnson 4 6 3 4 5 4 4
Glade 2 2 2 2 2 2 2
Centerpark 3 5 7 7 7 1 3
Brown Trail 5 4 6 6 4 5 5
Cheek-Sparger 7 3 4 3 3 8 6
Notes:
1 Daily intersection volumes
2 Hourly volumes
3 Average of AM & PM Peak Periods
4 Each intersection is given a ranking
of 1-8, with 1 representing the
greatest need/benefit
Intersection
Location
Ranking*
Total Status Traffic
Measures
Land Use
Measures
Brumlow/Pool 1 3 4 Under Construction
John McCain 7 5 12 Under Construction
Tinker 8 8 16 Later Priority?
Hall-Johnson 4 4 8 Proposed New Section?
Glade 2 1 3 Proposed New Section?
Centerpark 3 2 5 Proposed New Section?
Brown Trail 5 6 11 Proposed New Section?
Cheek-Sparger 6 7 13 Later Priority?
*Each intersection is given an ranking of 1-8, with 1 representing the
greatest need/benefit.
Source: City of Pantego
and Stad.com
Funding
Availability
•Volumes
•Turning
Movements
•Speeds
Transportation
Need
Economic
Development
•Development
Type
Land Use and
Placemaking
•Bike and
Pedestrian
Connections
•Land Uses
Leveraging
Ability
Enhancement Funding ($1.59M total
approved in May 2013)
Commissioner Fickes $1 Million (Tarrant
County)
Move funding to most needed section
(leverage for development)
Potential Pass-Through Finance Agreement
Christie Gotti
NCTCOG
Senior Program Manager
817/608-2338
cgotti@nctcog.org
Questions and
Discussion
City of Colleyville Page 1
City of Colleyville
Colleyville City Council
Worksession
Agenda Briefing
City Hall
100 Main Street
Colleyville, Texas 76034
www.colleyville.com
Agenda Number 3 Agenda Date 09/16/2013
Type Executive Session
Department City Manager
Title
Section 551.087 – Economic Development - Discuss or deliberate regarding
commercial or financial information that the City has received from business prospects
that the City seeks to have locate, stay, or expand in the City and with which the City
is conducting economic development negotiations; deliberate the offer of a financial or
other incentive to a business prospect
Attachments