HomeMy WebLinkAboutCity Council-Agenda Packets-1/16/2024City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL AGENDA
100 Main Street, Colleyville, Texas, 76034
TUESDAY, JANUARY 16, 2024
RIBBON CUTTING AND OPEN HOUSE
COLLEYVILLE SENIOR CENTER
2512 Glade Road – 4:30 – 6:00 p.m.
WORKSESSION
5:30 PM
EXECUTIVE CONFERENCE ROOM
THIRD FLOOR
CALL TO ORDER
WS-1 Review and discuss the market study for the Northern Gateway property
WS-2 Discussion of the January 16, 2024, City Council regular agenda items
1.EXECUTIVE SESSION - In accordance with Texas Government Code,
Chapter 551, Subchapter D
Section 551.071 - Legal - Consultation with the City Attorney regarding
items on the agenda or for matters in which the duty of the attorney to the
governmental body under the Texas Disciplinary Rules of Professional
Conduct of the State Bar of Texas clearly conflicts with Chapter 551 of the
Texas Code
Section 551.072 - Real Estate - Deliberate the purchase, exchange, lease, or
value of real property for City facilities
Section 551.087 – Economic Development - Discuss or deliberate regarding
commercial or financial information the City has received from business
prospects the City seeks to have locate, stay, or expand in the City and with
which the City is conducting economic development negotiations; deliberate
the offer of a financial or other incentive to a business prospect
REGULAR MEETING
7:00 P.M.
CITY COUNCIL CHAMBERS
INVOCATION: Pastor Lanre Sobo, Glory House
PLEDGE OF ALLEGIANCE: City Attorney Whitt Wyatt
City Council Agenda January 16, 2024
City of Colleyville Page 2
2. EXECUTIVE SESSION READING AND PUBLIC HEARING: CONSIDER
AND TAKE ANY ACTION(S) NECESSARY RELATIVE TO ITEMS
DISCUSSED IN EXECUTIVE SESSION - RESOLUTION R-24-4906
3. ANNOUNCEMENTS, PROCLAMATIONS, AND PRESENTATIONS
Proclamation in recognition of Colleyville Library Director Mary Rodne –
Mayor Bobby Lindamood
4. CONSENT: READING AND PUBLIC HEARING - RESOLUTION R-24-4907
4a Approval of the minutes of the regular City Council meeting of
December 19, 2023
4b Approval of a contract with McDonald Municipal & Industrial, in an
amount not to exceed $216,469, and a contingency amount not to
exceed $30,000, and authorizing the City Manager to execute the
contract
4c Approval of an amendment to the Professional Services Agreement
with Freese and Nichols, Inc., amending the design parameters for the
Roberts Road Project Phase 2 in an amount not to exceed $99,730,
and authorizing the City Manager to execute the amendment
4d Approval of an amendment to the Professional Services Agreement
with Freese and Nichols, Inc., amending the design parameters for the
Roberts Road Project in an amount not to exceed $8,400, and
authorizing the City Manager to execute the amendment
4e Approval to purchase a replacement Vactor 2100i Sewer Cleaner truck
from Kinlock Equipment & Supply, Inc., through the HGAC Purchasing
Program in an amount not to exceed $514,214, and authorizing the
City Manager to execute the contract
4f Approval of the Second Amended Regional Municipal Court Judge
Agreement
5. ITEMS NOT FOR CITY COUNCIL ACTION
5a Monthly Financial Report - December 2023
6. RESOLUTION(S): READING AND PUBLIC HEARING
6a Resolution R-24-4908
Approval of a resolution calling a General Election for the purpose of
electing City Councilmembers to Place 5 and Place 6, and adding a
Referendum Question to the ballot to determine whether voters desire
to place a proposition on a future election ballot asking the City's
City Council Agenda January 16, 2024
City of Colleyville Page 3
voters to authorize issuance of ad valorem tax bonds for expansion of
the Colleyville Recreation Center, and authorizing a joint election
agreement and contract for election services for the General Election
and the Referendum Question with Tarrant County Elections
Administration
7. TABLED RESOLUTION(S): READING AND PUBLIC HEARING
7a Resolution R-23-4883
Consideration of a variance to lot size, lot coverage, and side yard
setbacks for lot 27, Community Home Addition, located at 1611 Cherry
Lane, Case VC23-004 - WITHDRAWN BY APPLICANT
8. CITIZEN COMMENTS
9. REPORTS
Planning and Zoning Commission Minutes - December 11, 2023
10. ACTION/RESOLUTION: DISCUSSION AND CONSIDERATION OF A
RESOLUTION RATIFYING COUNCIL AGENDA ACTION FOR TUESDAY,
JANUARY 16, 2024 - READING AND PUBLIC HEARING - RESOLUTION
R-24-4909
11. ADJOURNMENT
I hereby certify this agenda was posted on City Hall bulletin boards Friday, January 12,
2024 by 5:00 p.m.
Christine Loven, TRMC
City Secretary
A quorum of any Colleyville board, commission, or committee may be present at this
meeting. Any matter on this agenda may, at the discretion of the governing body, be
opened for public comment and discussion.
If you plan to attend this public meeting and have a disability requiring special
accommodations, please advise the City Secretary at least 48 hours in advance at
817.503.1133, and reasonable accommodations will be made to assist you.
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number WS-1 Agenda Date 1/16/2024
Type Worksession
Department City Manager
Title
Review and discuss the market study for the Northern Gateway property
Explanation
This item will provide for staff to review the Northern Gateway Market Study conducted
by Harvest MXD.
Attachments
1. Colleyville Market Study
Chris HardenPresident & CEOMobile: +1 972 746 0725chris@harvestmxd.com
Daniel MitlyngVice PresidentMobile: +1 214 499 3762daniel@harvestmxd.com
SWC John McCain & Hwy 26
Colleyville, Texas
STRATEGIC PLANNING & PROJECT UNDERWRITING
NOVEMBER 2023
PREPARED FOR:
CITY OF COLLEYVILLE
2 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Executive Summary
Harvest MXD has been retained by the City of Colleyville (“Colleyville”) to perform a
detailed market study for a city owned tract of land located at the southwest
corner of John McCain Road and Colleyville Boulevard / Highway 26 (the
“Property”), a ±37 acre, suburban in-fill property located in one of the highest
income submarkets in the DFW Metroplex, one of the nations fastest growing
MSA’s. The property is located at the northern gateway to the City of Colleyville,
with excellent visibility and access to over 34,000 vehicles per day along Hwy 26.
This market study analyzes the current market conditions and contemplates a
proposed development plan to maximize the benefits Colleyville would receive and
quantifies the development potential of the Property.
It is our opinion that the Property is marketable for commercial development over
the next 12 months for a variety of commercial uses. Our opinion is that the
highest and best use of the property, other than residential development, is
predominately destination restaurant with outdoor recreational amenities that
appeal to the surrounding high-income neighborhoods.
3 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Valuation
Rationale:
It is our opinion that the property is suitable for a variety of commercial uses, however city incentives
will most likely be required to attract a resort hotel and/or anchor destination
entertainment/restaurant user. Once these “loss leader” users are committed, the rest of the
development should fill in rather quickly due to the attractiveness of the surrounding demographics,
visibility and traffic counts along Highway 26.
Estimated Value Range 37.42 Acres
$15,485,144 $9.50 $413,820
$13,855,129 $8.50 $370,260
$12,225,114 $7.50 $326,700
$10,595,099 $6.50 $283,140
$8,965,084 $5.50 $239,580
General Notes:
* Valuation is based upon the net developable area excluding 14.32 acres of Flood Zone.
Purchase Price Price PSF
Land
* Valuation does not take into consideration extraordinary site development costs such as tree removal and
extensive retaining walls.
Price Per Acre
Land
Stretch Buyer TARGET MARKET
Majority of Market
Land Area AC Land SF Potential Product Mix
Flood Zone 14.32 623,779 Open Green Space
Hwy 26 Frontage 10.30 448,668 55k SF Restaurants, Entertainment, Service Retail
West of Flood Zone 12.80 557,568 70K SF Medical Office or Resort Hotel
37.42 1,630,015
Use NRSF Cost PSF Est. AV
Est. City AV
Revenue Est. Sales PSF Est. Annual City
Sales Tax Revenue
Restaurants, Entertainment, Service Retail 55,000 $350 $19,250,000 $50,241 $400 $440,000
Medical Office 70,000 $400 $28,000,000 $73,077
Total 125,000 $378 $47,250,000 $123,318 $440,000
General Notes:
*Sales Tax Revenue based on 2.00% to the City of Colleyville
* AV Tax Revenue based on City of Colleyville millage rate of 0.260991 per $100 of AV
4 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Goals & Objectives – Evaluation Criteria
Key Goals & Objectives:
•Create a place for the citizens of Colleyville to enjoy an engaging environment with a mixture of commercial uses.
•Help establish the gateway for the City of Colleyville with a well curated commercial development with high quality architecture and landscaping.
•A development that incorporates and takes advantage of the natural amenities of the Property.
•Diversify the tax base for the City of Colleyville and its citizens.
Submission Evaluation Criteria:
Financial Factors
•Financial strength and experience of the master developer.
•Proposed quality of tenancy and overall project.
Place-Making, Quality of Life Factors
•Gateways and walkability through pedestrian and bicycle connections to
the broader city.
•High quality architecture of buildings and outdoor space.
•Imaginative development theming with mix of uses.
Project Development Parameters:
•Should be entirely commercial uses including hospitality,
entertainment, restaurant, retail, office, medical office,
and senior living (all categories).
•Should be programmed to be activated year-round and
an engaging place, focal point, for the overall
development.
•Incorporate the highest quality building and landscaping
materials, and signage consistent with other first-class
developments in Colleyville.
•The City is open to creative parking solutions that
maximize open space and overall quality of the
development.
5 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Marketing Strategy
SELLING THEMES
“Highly Affluent Submarket” – Demographics surrounding the property are some of the strongest in the Dallas-Fort Worth metroplex at a
median income of over $206,000 within the 1-mile radius and over $166,000 within the 3-mile radius.
“High Barrier To Entry Infill Location” – The Property is located in Colleyville TX, a largely built-out community boasting a strong
demographic profile. With over 200 companies having announced relocations to DFW since 2010, and many others recently announcing
relocations, in-fill locations will continue to be highly desired.
“Outstanding Accessibility and Connectivity” – The Property is located with immediate access to Colleyville Blvd providing access to some of
north Texas’ most traveled regional thoroughfares, Highway 114 to the north, Highway 121 to the east, and Highway 183 to the south.
Connectivity is further improved by DFW International Airport, providing international connectivity within a 15-minute drive from the
property.
“Proximate to Major Employment” - The Property is nearly equidistant from the major employment nodes of Downtown Dallas and
Downtown Fort Worth. Other employment nodes include DFW International airport which supports over 228,000 employees.
TIMELINE
STRATEGIC
PLANNING AND UNDERWRITING
CREATE & APPROVE
MARKETING
MATERIALS
SOLICITATION OF
INITIAL PROPOSALS
INITIAL PROPOSAL
ANALYSIS & PHASE 2 SOLICITATION OF
FORMAL PROPOSALS
FORMAL PROPOSAL
EVALUATION &
MASTER DEVELOPER /
BUYER SELECTION
CONTRACT
NEGOTIATION & EXECUTION
±30 DAYS ±30 DAYS ±30-45 DAYS ±30-45 DAYS ±15-30DAYS ±30 DAYS
Harvest MXD will develop a Needs Assessment / Decision Matrix that will guide the RFP and subsequent selection process, preparation of due diligence materials, expected financing structure(s), and marketing strategy.
Harvest MXD will develop a detailed Request for Proposal (RFP) document to solicit the initial and formal proposals and finalize the RFP based on feedback from City.
Harvest MXD will send an introductory offering memorandum to qualified developers/investors. Harvest MXD will directly contact each prospective developer and/or investor and promote the offering.
Harvest MXD will review and analyze all initial proposals submitted, make a comprehensive presentation summarizing all bids received, and make recommendations for formal proposal invitees.
Harvest MXD will create a
comprehensive presentation for
City, analyzing and evaluating
all formal proposals received,
coordinate developer/buyer
interviews and upon request,
will make a recommendation
for the selection of the
preferred developer/buyer.
Harvest MXD and City will
determine the appropriate
transaction structure and
Harvest MXD will negotiate on
City’s behalf a Memorandum of
Understanding. Harvest MXD
will assist City to finalize and
execute definitive agreements.
6 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Location Map
Dallas
±35 MinFort Worth
±30 Min
DFW Airport
±15 Min
AT&T Stadium
±25 Min
GrandScape/
Legacy West
±30 Min
Grapevine
±15 Min
Trophy Club
±20 Min
Love Field
±30 Min
Addison
±35 Min
Keller
±20 Min
7 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Retailer Voids
Desserts Pets Pizza
Brew Pubs – “Eatertainment ”
Burgers
Steak / BBQ OtherBreakfast
Mexican
8 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Retail Hubs
1.0 MILE
2.0 MILES
3.0 MILES
Grapevine Lake
DFW
International
Airport
Retail Properties >1.5K NRSF within 3miles
403 Buildings with ±7.5 million NRSF
Average year built: 2001
Occupancy Rate: ±96.8%
12-Month Absorption: 128,300 NRSF
Market Rent: $27.89 PSF
Rent Growth: 2.6%
9 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
1.0 MILE
2.0 MILES
3.0 MILES
DFW
International
Airport
Ranked in the 89th Percentile Statewide
TTM Visits: ±2 million from 344,400 individuals
Average Time Spent at Center: 60 minutes
Visitor Median Household Income: $96,400
3-Year Growth Rate: 6.0%
Last Year Growth Rate: -1.2%
Market Street ranks in the 44th percentile statewide
Ranked in the 67th Percentile Statewide
TTM Visits: 1.2 million from 229,100 individuals
Average Time Spent at Center: 57 minutes
Visitor Median Household Income: $92,900
3-Year Growth Rate: 24.1%
Last Year Growth Rate: -3.9%
Whole Foods ranks in the 3rd percentile statewide
Colleyville Downs
Glade Point Shopping Center
Ranked in the 25th Percentile Statewide
TTM Visits: 656,400 from 159,400 individuals
Average Time Spent at Center: 38 minutes
Visitor Median Household Income: $79,300
3-Year Growth Rate: -6.3%
Last Year Growth Rate: -2.2%
Albertson’s ranks in the 37th percentile statewide
Ranked in the 95th Percentile Statewide
TTM Visits: ±7.3 million from 1.7 million individuals
Average Time Spent at Center: 1 hour 40 minutes
Visitor Median Household Income: $97,700
3-Year Growth Rate: 32.4%
Last Year Growth Rate: 0.7%
Cheesecake Factory ranks #1 statewide
TTM Visits: 1.9 million from 949,000 individuals
Average Time Spent at Center: 1 hour 28 minutes
Visitor Median Household Income: $88,600
3-Year Growth Rate: 39.4%
Last Year Growth Rate: 2.1%
Historic Downtown Grapevine
10 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Employment Hubs
1.0 MILE
2.0 MILES
3.0 MILES
Grapevine Lake
DFW International Airport
±228,000 employees
Highway 26 & Hwy 114 Industrial Park
±2.3 million NRSF
±94% leased at $9.80 PSF
±8.8% Annual Rent Growth
Office Properties >15K NRSF within 3miles
75 Buildings with ±2.65 million NRSF
Average year built: 2008
Occupancy Rate: ±79%
12-Month Absorption: -29,500 NRSF
Market Rent: $31.86 PSF
Rent Growth: 2.1%
±139,800 annual visits
Avg Dwell Time: 3.5 hours
Visits YoY: -16.7%
±1.5 million annual visits
Avg Dwell Time: 2.5 hours
Visits YoY: 10.4%
Birdville High School
±2,000 students
Athletics Complex
Stadium
Timberline Elementary School
±630 students
Cross Timbers Middle School
±830 students
Grapevine High School
±1,900 students
Colleyville Middle School
±615 students
Colleyville Elementary School
±495 students
City of Colleyville
±200 employees
11 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Hotels
1.0 MILE
2.0 MILES
3.0 MILES
Grapevine Lake
DFW International
Airport
The area is bordered by hotels within 3 to 5
miles of the property along the major
highways of Hwy 114 to the north, Hwy 121
to the east, and Hwy 183 to the south that
serve the surrounding area.
Inventory: 775 rooms
12-month occupancy rate: 72.7%
12-month ADR: $194
12-month REVPAR: $141
Hotels within 3 to 5 miles of the Property
12 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Residential Neighborhoods
Timarron Country Club
John McCain Rd
Oak Alley
Homes from $1 million to
$5 Million +
Timarron Cascades
Homes from $1 million+
Shalimar
Homes from $1 million+
Sapphire Enclave
Homes from $900K+
Monterra
Homes from $800K to $1 million+
Longwood Estates
Homes from $800K to $1 million+
East Point Terrace
Homes from $900K to $2 million+
Glenhope
Elementary School
Colleyville
Elementary School
1.0 MILE
Remington Park
Homes from $850K to $2 million+
Timber Lake
Homes from $950K to $2 million +
The Overlook
Homes from $1 million to
$2 Million+
Montclair Parc
Homes from $700K to $3 million+
13 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Land Sale Comps
1
2
3
4
5 6
No. Address City Acres SF Net SF Zoning Sale Date Price Price PSF Net
1 1300 Rufe Snow Road Keller 10.94 476,546 476,546 Retail 7/19/2022 $2,382,732 $5.00
2 1963 West Southlake Blvd.Southlake 14.1341 615,681 615,681 C2 Retail 6/14/2022 7,810,000$ $12.69
3 205 North Industrial Blvd.Bedford 18.77 817,404 817,404 L/H Commercial 12/17/2021 9,500,000$ $11.62
4 7201 Precinct Line Road Fort Worth 9.24 402,494 402,494 C-1 8/20/2021 1,250,000$ $3.11
5 2000 Whitley Road Keller 5.5 239,580 239,580 C 12/30/2020 900,000$ $3.75
6 3105 William D Tate Avenue Grapevine 5.2 226,519 226,519 CC 2/24/2020 4,530,240$ $20.00
14 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Potential Developers
WIRE Properties
15 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Texas Fast Facts
16 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Economic Strength –DFW and Texas
17 //
SWC John McCain & Hwy 26
Colleyville, Texas
Strategic Planning & Project Underwriting
Economic Strength –Colleyville
Chris HardenPresident & CEOMobile: +1 972 746 0725chris@harvestmxd.com
Daniel MitlyngVice PresidentMobile: +1 214 499 3762daniel@harvestmxd.com
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number WS-2 Agenda Date 1/16/2024
Type Worksession
Department City Secretary
Title
Discussion of the January 16, 2024, City Council regular agenda items
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number 1 Agenda Date 1/16/2024
Type Executive Session
Department City Secretary
Title
Section 551.071 - Legal - Consultation with the City Attorney regarding items on the
agenda or for matters in which the duty of the attorney to the governmental body under
the Texas Disciplinary Rules of Professional Conduct of the State Bar of Texas clearly
conflicts with Chapter 551 of the Texas Code
Section 551.072 - Real Estate - Deliberate the purchase, exchange, lease, or value of
real property for City facilities
Section 551.087 – Economic Development - Discuss or deliberate regarding commercial
or financial information the City has received from business prospects the City seeks to
have locate, stay, or expand in the City and with which the City is conducting economic
development negotiations; deliberate the offer of a financial or other incentive to a
business prospect
RESOLUTION R-24-4906
A RESOLUTION APPROVING COUNCIL ACTION REGARDING
EXECUTIVE SESSION ITEMS AT THE REGULAR CITY COUNCIL
MEETING OF JANUARY 16, 2024
WHEREAS, following discussion in Executive Session, and in full
accordance with the requirements of the Open Meetings Act,
the City Council determines that the following action is in the
best interests of the health, safety, and welfare of the public.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF COLLEYVILLE, TEXAS:
Sec. 1. THAT
AND IT IS SO RESOLVED.
APPROVED BY A VOTE OF _ AYES, _ NAYS ON THIS THE 16TH DAY OF
JANUARY 2024.
Mayor Bobby Lindamood Aye Mayor Pro Tem Callie Rigney Aye
Brandi Elder, Place 1 Aye George Bond, Place 2 Aye
Scotty Richardson, Place 3 Aye Ben Graves, Place 4 Aye
Chuck Kelley, Place 5 Aye
ATTEST: CITY OF COLLEYVILLE
Christine Loven, TRMC Bobby Lindamood
City Secretary Mayor
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number Agenda Date 1/16/2024 Number 3
Type Announcements, Proclamations, and Presentations
Department City Secretary
Title
Proclamation in recognition of Colleyville Library Director Mary Rodne – Mayor Bobby
Lindamood
RESOLUTION R-24-4907
APPROVING CITY COUNCIL ACTION UNDER CONSENT ITEMS AT
THE REGULAR CITY COUNCIL MEETING OF JANUARY 16, 2024
WHEREAS,City Council has taken action on certain items on the agenda
under Consent Items.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF COLLEYVILLE, TEXAS:
Sec. 1. THAT the agenda decisions approved by City Council action
under Consent Items as follows are hereby adopted:
a. Approval of the minutes of the regular City Council meeting of
December 19, 2023
b. Approval of a contract with McDonald Municipal &
Industrial, in an amount not to exceed $216,469, and a
contingency amount not to exceed $30,000, and authorizing
the City Manager to execute the contract
c. Approval of an amendment to the Professional Services
Agreement with Freese and Nichols, Inc., amending the design
parameters for the Roberts Road Project Phase 2 in an amount
not to exceed $99,730, and authorizing the City Manager to
execute the amendment
d. Approval of an amendment to the Professional Services
Agreement with Freese and Nichols, Inc., amending the design
parameters for the Roberts Road Project in an amount not
to exceed $8,400, and authorizing the City Manager to
execute the amendment
e. Approval to purchase a replacement Vactor 2100i Sewer
Cleaner truck from Kinlock Equipment & Supply, Inc., through
the HGAC Purchasing Program in an amount not to exceed
$514,214.00, and authorizing the City Manager to execute the
contract
f. Approval of the Second Amended Regional Municipal Court
Judge Agreement
AND IT IS SO RESOLVED.
Resolution R-24-4907
Page 2 of 2
APPROVED BY A VOTE OF AYES, NAYS ON THIS THE 16TH DAY OF JANUARY
2024.
Mayor Bobby Lindamood Aye Mayor Pro Tem Callie Rigney Aye
Brandi Elder, Place 1 Aye George Bond, Place 2 Aye
Scotty Richardson, Place 3 Aye Ben Graves, Place 4 Aye
Chuck Kelley, Place 5 Aye
ATTEST: CITY OF COLLEYVILLE
Christine Loven, TRMC Bobby Lindamood
City Secretary Mayor
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL MINUTES
100 Main Street, Colleyville, Texas, 76034
TUESDAY, DECEMBER 19, 2023
Mayor Bobby Lindamood called the Colleyville City Council Worksession to order on
Tuesday, December 19, 2023, at 5:34 p.m.
ROLL CALL: Mayor Bobby Lindamood, Mayor Pro Tem Callie Rigney, and
Councilmembers Brandi Elder, George Bond, Scotty Richardson, Ben Graves, and
Chuck Kelley.
ALSO PRESENT: City Manager Jerry Ducay, Assistant City Manager Mark Wood,
Assistant City Manager Adrienne Lothery, Community Development Director Ben
Bryner, Public Works Director Amber Beard, City Engineer Larry Wright, City
Attorney Nicole Corr, and City Secretary Christine Loven.
WS-1 Discussion regarding a referendum question to be added to the May 4,
2024 General Election ballot
Assistant City Manager Mark Wood reviewed completed projects and timing for
remaining projects in Phase 1 of the Recreation Center which was funded with
$1.5 million in existing bond funding. He then reviewed the feedback regarding
amenities at the Recreation Center which was received from residents, the Parks
and Recreation Advisory Board, and City Council. Manager Wood noted any
additional amenities above Phase 1 would have to be budgeted for over a period of
years or potentially be financed through bonds.
Manager Wood provided potential ballot language for a referendum question which
could be added to the May 4, 2024 General Election ballot. The referendum
question would pose a yes or no answer to the question, “Should the City of
Colleyville place a proposition on a future election ballot asking the City’s voters to
authorize the issuance of ad valorem tax bonds for expansion of the Colleyville
Recreation Center, which may include a fitness center, locker room, indoor track,
and multi-use field?”
Following discussion, the City Council directed staff to place the question on the
May ballot and noted this would allow another opportunity for residents to voice
their opinions regarding the amenities at the Recreation Center.
WS-2 Discussion of corner lot fence regulations
Community Development Director Ben Bryner stated in late November, City
Council had directed staff to prepare possible text changes to the Land
City Council Minutes December 19, 2023
City of Colleyville Page 2
Development Code (LDC) with regard to regulations for fences on corner lots.
Specifically, the Council wanted to review options for non-opaque fences, and
whether they should be allowed to encroach into the street side yard setback. He
reviewed current LDC language, and suggested language to address the corner
side yard setbacks.
City Council directed staff to proceed with taking the proposed changes to the
Planning and Zoning Council for review and comment.
WS-3 Discussion of Old Grove pond
City Engineer Larry Wright provided a review of the current condition of the
detention pond in Old Grove Subdivision and the previous anticipated cost to
rehabilitate the pond. Engineer Wright noted the Engineering Department had
performed a topographic survey to identify slope and erosion issues, and a grading
plan design to make the slopes accessible to residents and reduce erosion. By
doing so, staff devised a rehabilitation and beautification plan for the pond which
would be cost effective, and the work will be performed by the Public Works
Department.
The City Council thanked Engineer Wright and the Public Works Department for
their commitment to efficiency and cost savings.
WS-4 Discussion of the December 19, 2023, City Council regular agenda items
There was no discussion of this item.
Mayor Lindamood adjourned the Worksession at 6:04 p.m. and called the
Executive Session to order.
1. EXECUTIVE SESSION - In accordance with Texas Government Code,
Chapter 551, Subchapter D
Section 551.071 - Legal - Consultation with the City Attorney regarding
items on the agenda or for matters in which the duty of the attorney to the
governmental body under the Texas Disciplinary Rules of Professional
Conduct of the State Bar of Texas clearly conflicts with Chapter 551 of the
Texas Code
Section 551.071 - Legal - Hall-Johnson Road Water Tank
Section 551.072 - Real Estate - Deliberate the purchase, exchange, lease, or
value of real property for City facilities
Section 551.087 – Economic Development - Discuss or deliberate regarding
City Council Minutes December 19, 2023
City of Colleyville Page 3
commercial or financial information the City has received from business
prospects the City seeks to have locate, stay, or expand in the City and with
which the City is conducting economic development negotiations; deliberate
the offer of a financial or other incentive to a business prospect
There was no action taken and Mayor Lindamood adjourned Executive Session at
6:52 p.m.
Mayor Lindamood called the regular meeting of the City Council to order at 7:08
p.m. and called the roll.
ROLL CALL: Mayor Bobby Lindamood, Mayor Pro Tem Callie Rigney, and
Councilmembers Brandi Elder, George Bond, Scotty Richardson, Ben Graves, and
Chuck Kelley.
INVOCATION: Pastor Lee Johnson, Bear Valley Church
PLEDGE OF ALLEGIANCE: City Attorney Nicole Corr
2. EXECUTIVE SESSION READING AND PUBLIC HEARING: CONSIDER
AND TAKE ANY ACTION(S) NECESSARY RELATIVE TO ITEMS
DISCUSSED IN EXECUTIVE SESSION - RESOLUTION R-23-4903
This resolution was not needed.
3. ANNOUNCEMENTS, PROCLAMATIONS, AND PRESENTATIONS
Mayor Lindamood and the City Council made announcements regarding City and
community events.
Proclamation to Natalie Poveda, Miss Colleyville's Teen, Miss Texas'
Teen - Mayor Bobby Lindamood
Mayor Lindamood presented a proclamation declaring Natalie Poveda Day in
Colleyville to Miss Natalie Poveda, Miss Colleyville's Teen and Miss Texas' Teen.
Mayor Lindamood thanked Miss Poveda for representing Colleyville and GCISD and
noted she will be going on to compete for the title of Miss America's Teen 2024, in
Orlando, Florida.
4. CONSENT: READING AND PUBLIC HEARING - RESOLUTION R-23-4904
4a Approval of the minutes of the regular City Council meeting of
December 5, 2023
City Council Minutes December 19, 2023
City of Colleyville Page 4
4b Approval of a First Amendment to the Lease Agreement with Tarrant
County 9-1-1 for facility space at the Colleyville Justice Center
4c Approval of a construction contract with Legacy Signs of Texas for the
Wayfinding Signage Project, in an amount not to exceed $94,027.00
and a contingency amount not to exceed $10,000.00, and authorizing
the City Manager to execute the contract
4d Approval of an Interlocal Agreement with Tarrant County for the
funding of the Bedford Road Roundabout at Cheek-Sparger
Improvements project, and authorizing the City Manager to execute
the agreement
4e Approval of an Interlocal Agreement with Tarrant County for the
funding of the Heritage Avenue Bridge Replacement and Turn Lane
Extensions at Cheek-Sparger Improvements Project, and authorizing
the City Manager to execute the agreement
4f Approval of an Interlocal Agreement with Tarrant County for the
funding of the John McCain Road Bridge Widening and Curvature
Improvements Project, and authorizing the City Manager to execute
the agreement
4g Approval of a contract with The Lawn Firm for the Tree Trimming
Contract, in an amount not to exceed $75,000, and authorizing the
City Manager to execute the contract
4h Approval to purchase six custom bronze statues of U.S.A. Military
Servicemen from the Randolph Rose Collection for the future Heroes
Park in an amount not to exceed $272,800, and authorizing the City
Manager to execute related purchasing documents
Mayor Lindamood read Resolution R-23-4904 in its entirety.
Assistant City Manager Adrienne Lothery presented items 4b and 4h and answered
questions of the City Council.
Elijah Dorminy, Capital Projects Program Manager, presented item 4c, and Public
Works Director Amber Beard presented items 4d through 4f and answered
questions of the City Council.
Mayor Lindamood opened the public hearing.
Harold Ledbetter, 6700 Pleasant Run Road, commented on 4h, the statues for
Heroes Park.
City Council Minutes December 19, 2023
City of Colleyville Page 5
There were no others wishing to speak and Mayor Lindamood closed the public
hearing.
Mayor Pro Tem Rigney made a motion to approve Resolution R-23-4904,
seconded by Councilmember Graves.
The motion was approved by the following vote:
Ayes: 7 – Mayor Bobby Lindamood, Mayor Pro Tem Callie Rigney, and
Councilmembers Brandi Elder, George Bond, Scotty Richardson, Ben
Graves, and Chuck Kelley.
5. ITEMS NOT FOR CITY COUNCIL ACTION
5a Monthly Financial Report - November 2023
Assistant City Manager Mark Wood presented the November financial report noting
this is the second month of the fiscal year. He noted November is the first month
of sales tax collection for FY24, and total collections were down 4.95% from the
same month last year. Manager Wood stated the collection did include an audit
adjustment of $27,630, and when accounting for the audit, the percentage
improves to being down 1.3%. He said sales tax for purchases made in October
jumped 19.52% from 2021 to 2022, followed by another increase of 1.3% last
year, which may be an indicator of sales tax reaching a leveling point going
forward. Manager Wood provided a recap of activity in the remaining budgets.
6. ORDINANCE(S): SECOND READING AND PUBLIC HEARING
6a Ordinance O-23-2272
Consideration of a rezoning from AG Agricultural to R-40 Single Family
Residential for Lot 1, Block 1, Fred C. Rice Addition, located at 6103
Hunter Lane, Case ZC23-032
Mayor Lindamood read the caption of Ordinance O-23-2272.
Community Development Director Ben Bryner presented this request to rezone to
allow for a piece of land to be platted from 6103 Hunter Lane to 6113 Hunter
Lane.
There was no discussion and Mayor Lindamood opened and closed the public
hearing without anyone wishing to speak.
Councilmember Elder made a motion to approve Ordinance O-23-2272,
seconded by Councilmember Richardson.
City Council Minutes December 19, 2023
City of Colleyville Page 6
The motion was approved by the following vote:
Ayes: 7 – Mayor Bobby Lindamood, Mayor Pro Tem Callie Rigney, and
Councilmembers Brandi Elder, George Bond, Scotty Richardson, Ben
Graves, and Chuck Kelley.
6b Ordinance O-23-2273
Consideration of a rezoning from AG Agricultural and RE Single Family
‘Estate’ Residential to R-40 Single Family Residential for Tracts 1B1,
1C1, 1B2, and 1B3, Abstract 294, Robert Chowning Survey and Lot 1,
Block 1, Cero Addition, located at 2417 Wilkes Drive and 6900 Pool
Road, Case ZC23-033
Mayor Lindamood read the caption of Ordinance O-23-2273.
Community Development Director Ben Bryner presented this item, recapping the
presentation from the previous meeting. Director Bryner said at City Council’s
request, the applicant reexamined and adjusted the large tree preservation
easements and has submitted a revised zoning exhibit and urban forestry plan
showing expanded easements, which encompasses approximately 40% of the
overall land.
There were questions and discussion between staff and City Council regarding tree
cutting, AG zoning regulations, and easements. The City Attorney explained the
Preemption Bill.
Mayor Lindamood opened the public hearing.
Those signing a speaker card to register opposition, but not speak: Stephen
Muzyka, 2902 Roaring Springs Drive, Grapevine, Cindy Kay Campbell, 2410
Wilkes, Jason Aguirie, 2402 Wilkes, Michael Shur, 7300 Jo West, Desiree Hershon,
7300 Jo Will Street, John and Judi Schaefer, 6803 Atlanta Drive, Richard
Limbacher, 6602 Charleston Drive, Robert and Rita Zebian, 6708 India Court,
Anne Dyson, 909 Dogwood Court, Andrew and Stephanie Gaska, 6801 India Court,
Allen and Bonnie Weikel, 1829 Fountain Pass, Tim Lavas, 2405 Wilkes Drive, Carol
Wollin, 4600 Dartmoore Lane, Paddy Meehan, 2512 Independence Road, Dorthea
Theus, 4104 Oxford Court, Steve Wasson, 2413 Wilkes Drive.
Those speaking in support: Jeff Cosand, 2604 Twelve Oaks, David Dudziak, 2301
Wilkes Court, and Stacey Taylor, 4501 Shadycreek Lane.
Those speaking in opposition: Sam Hearn, 2409 Wilkes Drive, Sue Reed, 2512
Independence Road, Bob Egan, 2410 Twelve Oaks Lane, Vicki Heminger, 6804
Rockbrook Court, Charlie Anderson, 2414 Wilkes Drive, Mike Farrell, 2504 Twelve
City Council Minutes December 19, 2023
City of Colleyville Page 7
Oaks Lane, Harold Ledbetter, 6700 Pleasant Run Road, and Tim Waterworth, 6808
Rockbrook Court.
There were no others wishing to speak and Mayor Lindamood closed the public
hearing.
The City Council convened in Executive Session at 9:22 p.m. and reconvened at
10:01 p.m.
Applicant Curtis Young stated they have listened, made major changes, and tried
to be adaptive. Mr. Young stated they will dedicate a pedestrian trail to the City if
it is desired. He also noted working with the Land Trust is not an option, and
reviewed the plan details.
The City Council expressed appreciation to the applicant for their continued work
with the City Council and their concern for the opposition and their thoughts for
the property.
Councilmember Kelley made a motion to deny without prejudice
Ordinance O-23-2273, seconded by Councilmember Graves.
The motion to deny without prejudice was approved by the following vote:
Ayes: 4 – Councilmembers Brandi Elder, Scotty Richardson, Ben Graves,
and Chuck Kelley.
Nays: 3 – Mayor Bobby Lindamood, Mayor Pro Tem Callie Rigney, and
Councilmember Bond
6c Ordinance O-23-2274
An ordinance amending Sections 3A and 3B of the Water and Sewer
Policy and Procedure manual as contained in the Code of Ordinances of
the City of Colleyville, Texas, adjusting water and wastewater
volumetric rates to pass through changes from the Trinity River
Authority
Mayor Lindamood read the caption of Ordinance O-23-2274.
Assistant City Manager Mark Wood presented this item which is a pass-through
rate increase for water and wastewater rates assessed by the Trinity River
Authority.
Mayor Lindamood opened the public hearing.
Harold Ledbetter, 6700 Pleasant Run Road, questioned the TRA capital debt.
City Council Minutes December 19, 2023
City of Colleyville Page 8
There were no others wishing to speak and Mayor Lindamood closed the public
hearing.
Mayor Lindamood made a motion to approve Ordinance O-23-2274,
seconded by Councilmember Bond.
The motion was approved by the following vote:
Ayes: 7 – Mayor Bobby Lindamood, Mayor Pro Tem Callie Rigney, and
Councilmembers Brandi Elder, George Bond, Scotty Richardson, Ben
Graves, and Chuck Kelley.
7. CITIZEN COMMENTS
There were seven speakers who spoke regarding the Israeli–Palestinian conflict,
asking City Council to issue a cease fire resolution. The City Secretary is listing
those who completed a speaker card: Salah Elshanshon, 3572 Versalles, Noor
Hasan, 5220 Center Hill Drive, Fort Worth, Faryall Tayyas, 5304 Center Hill Drive,
Fort Worth, Sama Rhiman, 602 Hays Drive, Keller. Following these speakers,
Mayor Lindamood offered information on the Colleyville community and the
Ministerial Alliance.
Sayeda Syed, 6705 Sapphire Circle North, spoke regarding school break, parking,
and the December gift card.
Harold Ledbetter, 6700 Pleasant Run Road, spoke regarding wars throughout the
world.
8. REPORTS
Colleyville Library Board Minutes - October 9, 2023
Sign Board of Appeals Minutes - October 10, 2023
Planning and Zoning Commission Minutes - November 13, 2023
Planning and Zoning Commission Worksession Minutes - November 27, 2023
There was no action taken.
9. ACTION/RESOLUTION: DISCUSSION AND CONSIDERATION OF A
RESOLUTION RATIFYING COUNCIL AGENDA ACTION FOR TUESDAY,
DECEMBER 19, 2023 - READING AND PUBLIC HEARING -
RESOLUTION R-23-4905
This resolution was not needed.
City Council Minutes December 19, 2023
City of Colleyville Page 9
10. ADJOURNMENT
There being no further business before the City Council, Mayor Lindamood
adjourned the meeting without objection by the City Council at 11:20 p.m.
APPROVED BY A VOTE OF AYES, NAYS, ON THIS THE 16TH DAY OF JANUARY
2024.
Minutes taken and prepared by:
Christine Loven, TRMC
City Secretary
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number 4b Agenda Date 1/16/2024 Number Resolution R-24-4907
Type Resolution
Department Engineering
Title
Approval of a contract with McDonald Municipal & Industrial, in an amount not to exceed
$216,469, and a contingency amount not to exceed $30,000, and authorizing the City
Manager to execute the contract
Explanation
Reading and Public Hearing
On September 19, 2023, City Council, through Resolution R-23-4876, adopted the
Capital Improvement Program (CIP) Fiscal Year 2020-2024. The CIP includes $470,000
for the rehabilitation of the Reserve Lift Station.
The project includes the replacement of two existing submersible pumps and variable
frequency drives, with the addition of one spare, and two check valves. The installation
of a back-up generator and automatic transfer switch, electrical improvements, the
addition of a containment for degreaser storage and dosing equipment, including
permanent routing of degreaser lines to the wet well.
Public notification of the invitation for bids was advertised in the Fort Worth Star-
Telegram on November 19, 26, December 3, 10 and 17, 2023. The notice to bidders
and bid packet were posted on CivCast for free downloading and distributed to the
Dodge Lead Center, BlueBook Building and Construction Network, and Construct
Connect, which includes ISqFt, CMD, CDC, and Bid Clerk. Additionally, staff directly
notified a list of local contractors who may be interested in the bid opportunity. The
project had 93 plan holders, of which there was 1 architect, 4 engineers, 13 general
contractors, 6 manufacturers, 27 sub-contractors, 28 suppliers, 2 not specified, 4 plan
rooms, and 8 others.
The City received four sealed bids, which were opened and publicly read aloud on
December 19, 2023.
Financial Impact
The funding source for the project is the Capital Utility Fund
Form 1295 - Acknowledged by City
Recommendation
Approve
City of Colleyville Page 2
City Council Agenda Briefing 4b
Attachments
1. Bid Tabulation
2. Construction Services Agreement
Unit Total Unit Total Unit Total Unit Total
1 Mobilization for the
lump sum of:
LS 1.00 $20,000.00 $20,000.00 $16,500.00 $16,500.00 $29,200.00 $29,200.00 $31,000.00 $31,000.00
2 All Work as defined
in the Contract
Documents except
those items listed
separately below, for
the lump sum of:
LS 1.00 $1,000.00 $1,000.00 $5,000.00 $5,000.00 $15,000.00 $15,000.00 $30,000.00 $30,000.00
3 Demolition of
exisiting pumps for
the lump sum of:
LS 1.00 $1,000.00 $1,000.00 $6,000.00 $6,000.00 $44,000.00 $44,000.00 $10,000.00 $10,000.00
4 Demolition of
exisiting electrical
equipment for the
lump sum of:
LS 1.00 $2,500.00 $2,500.00 $6,000.00 $6,000.00 $9,400.00 $9,400.00 $20,000.00 $20,000.00
5 Installation of the
generator concrete
pad for the unit price
of:
CY 2.00 $1,000.00 $2,000.00 $5,000.00 $10,000.00 $4,500.00 $9,000.00 $5,000.00 $10,000.00
6 Purchase and
installation of the air
compressor pad for
the lump sum of:
EA 1.00 $1,000.00 $1,000.00 $2,000.00 $2,000.00 $3,000.00 $3,000.00 $500.00 $500.00
7 Purchase and
installation of the
generator for the
lump sum of:
EA 1.00 $30,000.00 $30,000.00 $96,277.00 $96,277.00 $113,000.00 $113,000.00 $120,000.00 $120,000.00
8 Installation of the
required electrical
improvements for the
lump sum of:
LS 1.00 $96,469.00 $96,469.00 $55,000.00 $55,000.00 $205,000.00 $205,000.00 $200,000.00 $200,000.00
9 Purchase and
installation of the
automatic transfer
switch for the lump
sum of:
EA 1.00 $10,000.00 $10,000.00 $20,000.00 $20,000.00 $10,800.00 $10,800.00 $10,000.00 $10,000.00
10 Purchase and
installation of the
motor starters for the
lump sum of:
EA 3.00 $3,000.00 $9,000.00 $5,000.00 $15,000.00 $5,500.00 $16,500.00 $5,000.00 $15,000.00
11 Installation of the
degreaser tubing, air
tubing, containment
tubing, and sleeve
penetration for the
lump sum of:
LS 1.00 $2,000.00 $2,000.00 $3,000.00 $3,000.00 $11,000.00 $11,000.00 $10,000.00 $10,000.00
12 Installation of the
Owner-furnished
check valves for the
lump sum of:
EA 2.00 $1,500.00 $3,000.00 $1,500.00 $3,000.00 $3,500.00 $7,000.00 $15,000.00 $30,000.00
13 Purchase and
installation of the new
submersible pumps
for the lump sum of:
EA 3.00 $12,000.00 $36,000.00 $20,000.00 $60,000.00 $33,250.00 $99,750.00 $35,000.00 $105,000.00
14 Purchase and
installation of the spill
containment deck
with drain line ball
valve for the lump
sum of:
LS 1.00 $2,500.00 $2,500.00 $3,000.00 $3,000.00 $13,000.00 $13,000.00 $1,500.00 $1,500.00
$216,469.00 $300,777.00 $585,650.00 $593,000.00
15 Owner's Contigency
Allowance for Work
Change Directives for
the lump sum of:
LS 1.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00
$246,469.00 $330,777.00 $615,650.00 $623,000.00
City of Colleyville Reserve Lift Station Improvements
ID: ENG-2024-002
Bid Tabulation December 19, 2023
Grand Total
SubTotal Base Bid
McDonald Municipal &
Industrial
Taknek Rey-Mar Construction Urban InfraConstruction,
LLC.
Item
Description
Unit
QTY
_______________________________________________________________________________
1
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
CONSTRUCTION SERVICES AGREEMENT
RESERVE LIFT STATION IMPROVEMENTS
(Bid #ENG-2024-002)
This CONSTRUCTION SERVICES AGREEMENT (“Agreement”) is made as of the Effective
Date by and between McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.,
a Texas Corporation, hereinafter called "Contractor", and the City of Colleyville, Texas, hereinafter
called "City".
RECITALS
WHEREAS, City desires Contractor to perform certain work and services set forth in Section 1,
below; and
WHEREAS, Contractor has expressed a willingness to perform said work and services, hereinafter
referred to only as "services", specified in the Contract Documents and Section 1 of this Agreement.
NOW, THEREFORE, for and in consideration of the covenants and promises made one to the
other herein, City and Contractor agree as follows:
Section 1. Scope of Services
Upon issuance of a written notice to proceed by City, Contractor agrees to provide to City the
necessary services, labor, materials, equipment, and supplies to perform the Reserve Lift Station
Improvements (the “Project”), such services being more fully described herein and pursuant to the plans
and specifications identified in the Contract Documents (defined below).
Section 2. Term of Agreement
The term of this Agreement shall begin on the last date of execution hereof (the “Effective Date”)
and shall continue until Contractor completes the services required herein to the satisfaction of City and
has been paid in full by City, unless sooner terminated in conformance with this Agreement.
Section 3. Contract Documents
(a) This Agreement is a part of the “Contract Documents”, which include:
(1) This Agreement, including all exhibits and addenda hereto;
(2) City’s plans, specifications, and all other contract documents for the Project
contained in City’s Bid #ENG-2024-002;
(3) City’s written notice(s) to proceed to the Contractor;
(4) Properly authorized change orders;
(5) Contractor’s Bid Proposal (“Proposal” and/or “Response”); and
(6) Any other materials distributed by the City that relate to the Project.
In the event there exists a conflict between any term, provision, and/or interpretation of the Contract
Documents, the documents shall take precedent and control in the order listed above in this section (which
shall supersede any conflicting provision concerning priority of contract documents contained in the Bid
Packet). If discrepancies are found that may impact Contractor’s performance of the services for the
Project, it shall be the Contractor’s obligation to seek clarification as to which requirements or provisions
control before undertaking any work on that component of the Project. Should the Contractor fail or refuse
to seek a clarification of such conflicting or inconsistent requirements or provisions prior to any work on
_______________________________________________________________________________
2
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
that component of the Project, the Contractor shall be solely responsible for the costs and expenses -
including additional time - necessary to cure, repair and/or correct that component of the Project.
Section 4. Contractor Obligations
(a) Performance of Services. To the extent reasonably necessary for Contractor to perform the
services under this Agreement, Contractor shall be authorized to engage the services of any agents,
assistants, persons, or corporations that Contractor may deem proper to aid or assist in the performance of
the services under this Agreement with the prior written approval of City. The cost of such personnel and
assistance shall be a reimbursable expense to Contractor only if authorized in writing in advance by City.
Unless otherwise agreed, Contractor shall provide and pay for all materials, supplies, machinery,
equipment, tools, superintendence, labor, insurance, and all water, light, power, fuel, transportation and all
other facilities necessary for the execution and completion of the Project.
(b) Quality Materials. Contractor shall be responsible for the professional quality, technical
accuracy, and the coordination of all materials, construction, installation and other services furnished by
Contractor under this Agreement. Unless otherwise specified in writing by City, all materials shall be new
and both workmanship and materials shall be of a good quality. Contractor shall, if required, furnish
satisfactory evidence as to the kind and quality of materials. Materials or work described in the Contract
Documents that, so applied, have well known, technical or trade meaning shall be held to refer to such
recognized standards. Contractor shall, without additional compensation, correct or revise any errors or
deficiencies in the installation and construction of the Project components to conform as shown in the
Project drawings and specifications.
(c) Additional Services. All minor details of the work not specifically mentioned in the
Contract Documents but obviously necessary for the proper completion of the work, such as the proper
connection of new work to old, shall be considered as incidental to and a part of the work for which the
prices are set forth in this Agreement. Contractor will not be entitled to any additional compensation
therefor unless specifically stated otherwise. Should City require additional services not included under
this Agreement, Contractor shall make reasonable effort to provide such additional services at mutually
agreed charges or rates, and within the time schedule prescribed by City, and without decreasing the
effectiveness of the performance of services required under this Agreement. The terms "extra work" and
“additional services” as used in this Agreement shall be understood to mean and include all work that may
be required by City to be done by Contractor to accomplish any alteration or addition to the work as shown
on the Project plans and drawings. It is agreed that Contractor shall perform all extra work under the
direction of the City's representative when presented with a written work/change order signed by the City’s
representative, subject, however, to the right of Contractor to require written confirmation of such extra
work order by City. No claims for extra services, additional s ervices or changes in the services whatsoever,
including any change in pricing or time for performance related to the services will be made by Contractor
without first obtaining the City’s written agreement and approval of a work/change order reflecting the
same.
(d) Independent Contractor. It is understood and agreed by and between the parties that
Contractor, while performing under this Agreement, is acting independently, and that City assumes no
responsibility or liabilities to any third party in connection with Contractor’s acts or omissions. All services
to be performed by Contractor pursuant to this Agreement shall be in the capacity of an independent
contractor, and not as an agent or employee of City. Contractor shall supervise the performance of its
services and shall be entitled to control the manner and means by which its services are to be performed,
subject to the terms of this Agreement. There is no intended third-party beneficiary to this Agreement.
(e) Inspection of Records. Contractor grants City and its designees the right to audit, examine,
or inspect, at City’s election, all of Contractor's Records relating to the performance of services under this
Agreement, during the term of the Agreement and any retention period herein. City’s audit, examination,
_______________________________________________________________________________
3
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
or inspection of Contractor’s Records may be performed by a City designee, which may include its internal
auditors or an outside representative engaged by City. Contractor agrees to retain Contractor’s Records for
a minimum of four (4) years following termination of the Agreement, unless there is an ongoing dispute
under the contract; then, such retention period shall extend until final resolution of the dispute.
"Contractor's Records" shall include any and all information, materials and data of every kind and character
generated as a result of the services under this Agreement. City agrees that it will exercise its right to audit,
examine or inspect Contractor’s Records only during regular business hours unless City has provided
advance written notice of an alternate time. Contractor agrees to allow City and its designees access to all
of Contractor's Records, Contractor's facilities and the current or former employees of Contractor, deemed
necessary by City or its designee(s), to perform such audit, inspection, or examination.
(f) Certification of No Conflicts. Contractor hereby warrants to the City that Contractor has
made full disclosure in writing of any existing or potential conflicts of interest related to Contractor's
services under this Agreement. In the event that any conflicts of interest arise after the Effective Date of
this Agreement, Contractor hereby agrees immediately to make full disclosure to the City in writing.
(g) No Waiver of City’s Rights. Neither City’s review, approval or acceptance of, nor payment
for any of the materials or services required under this Agreement, shall be construed to operate as a waiver
of any rights under this Agreement or of any cause of action arising out of the performance of this
Agreement, and Contractor shall be and remain liable to City in accordance with applicable law for all
damages to City caused by Contractor’s negligent performance of any of the services furnished under this
Agreement.
(h) Rights-of-Access. City will endeavor to provide such rights of access on any project site
as may be reasonably necessary for Contractor to perform any required preliminary site studies, surveys,
tests, or other necessary investigations prior to mobilization for the Project. Contractor will take all
necessary and reasonable precautions to minimize damage to all personal and real property in the
performance of such surveys, tests, studies and investigations.
(i) Storm Water Management. When performing or delivering services at or upon any property
owned, leased, or managed by the City, or in performance of any services or other acts on behalf of, or at
the direction of the City (regardless of location), Contractor shall at all times comply with (i) the City’s
Storm Water Management and Discharge Control provisions codified in Chapter 42 of the Colleyville
Municipal Code, as amended, (ii) all applicable Minimum Best Management Practice requirements, as
defined by the Texas Commission on Environmental Quality, and (iii) any Storm Water Pollution
Prevention Plan (SWPPP) applicable to the worksite. Regardless of the applicability of the foregoing
regulations, CONTRACTOR SHALL AT ALL TIMES BE RESPONSIBLE FOR IMPLEMENTING
SUCH CONTROLS AS MAY BE REASONABLY NECESSARY TO MINIMIZE ANY NEGATIVE
IMPACT TO THE STORM WATER COLLECTION SYSTEM OR ENVIRONMENT AND SHALL
FOLLOW ALL STATE AND LOCAL ILLICIT DISCHARGE REPORTING PROCEDURES IN THE
EVENT OF AN OCCURRENCE OR DISCHARGE.
(j) Compliance with Laws. Contractor shall comply with all laws, ordinances, rules, policies,
orders, directives, and other regulations governing Contractor’s performance of this Agreement.
Section 5. Payment
(a) Compensation. City agrees to pay Contractor for all services authorized in writing and
properly performed by Contractor in a total amount not to exceed TWO HUNDRED AND FOURTY-SIX
THOUSAND, FOUR HUNDRED AND SIXTY-NINE DOLLARS ($246,469.00) (“Contract Price”),
subject to additions or deletions for change orders and/or extra work agreed upon in writing.
_______________________________________________________________________________
4
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
(b) Method of Payment. Unless otherwise agreed by the parties in writing, payment to
Contractor shall be monthly based on a monthly progress report and detailed monthly itemized statement
for services submitted by Contractor that shows the names of the Contractor’s employees, agents, or
subcontactors performing the services, the time worked, the actual services performed, and the rates
charged for such services, in a form acceptable to City. City shall pay such monthly statements within
thirty (30) days after receipt of a completed submission and City’s verification of the services performed.
(c) Schedule of Values and Application for Payment. City may deduct from any amounts
due or to become due to Contractor any sum or sums owing by Contractor to City. In the event of any
breach by Contractor of any provision or obligation of this Agreement, or in the event of the assertion by
any third-party of a claim or lien against City, or the City’s premises, arising out of Contractor’s
performance under this Agreement, City shall have the right to retain out of any payments due or to
become due to Contractor an amount sufficient to completely protect the City from any and all loss,
damage or expense therefrom, until the breach, claim, or lien has been satisfactorily remedied by
Contractor. Additionally, City may, on account of subsequently discovered evidence, withhold the whole
or part of any payment to such extent as may be necessary to protect itself from loss on account of:
(1) defective work not remedied;
(2) claims filed or reasonable evidence indicating possible filing of claims;
(3) failure of Contractor to make payments promptly to subcontractors or for material or
labor which City may pay as an agent for the Contractor; or
(4) damages to another contractor or subcontractor.
When the above grounds are removed, or Contractor provides a letter of credit, or similar guaranty
satisfactory to City (to be determined in City’s sole discretion) which will protect City in the amount
withheld because of said grounds, City will release the amounts withheld.
Section 6. Performance Schedule
(a) Time for Performance. Contractor shall perform all services as provided for under this
Agreement in a proper, efficient, timely, and professional manner in accordance with City’s requirements.
The time for performance under this Agreement is two hundred seventy-three (273) calendar days.
Accordingly, Contractor shall complete all work related to the Project on or before two hundred seventy-
three (273) calendar days following the date of City’s written notice to proceed to Contractor.
(b) Extensions; Written Request Required. No allowance of any extension of time, for any
cause whatever (including an event of Force Majeure), shall be claimed by or granted to Contractor, unless
(i) Contractor shall have made written request to City for such extension within forty-eight (48) hours after
the cause for such extension occurred, and (ii) City and Contractor have agreed in writing that such
additional time shall be granted. As used in this section, the term “Force Majeure” shall mean that
Contractor’s performance of the services under this Agreement is prevented or delayed, in whole or in part,
to such an extent that Contractor would not be able to complete the services (or any partial component
thereof) within the time for performance set forth herein by reason of or through work strikes, stoppage of
labor, riot, fire, flood, acts of war, insurrection, court judgment, act of God, pandemic, or other specific
cause reasonably beyond Contractor’s control and not attributable to its malfeasance, neglect or
nonfeasance. Should Contractor timely request an extension of time due to an event of force majeure under
this section, City and Contractor may agree in writing to suspended Contractor’s performance until such
disability to perform (other than a payment obligation) is removed; provided, that Contractor shall use
commercially reasonable efforts to remove any such causes and resume performance of the services under
this Agreement as soon as reasonably practicable.
_______________________________________________________________________________
5
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
(c) Costs of Delay. Contractor understands and agrees that time is of the essence of this
contract, and that for each day of delay beyond the number of calendar days agreed upon for the completion
of the work herein specified and contracted for (after due allowance for such extension of time as may
otherwise be provided for extension of time herein), the Owner may withhold permanently from the
Contract Price an amount equal to $1,500.00 per day, which the parties agree represents a reasonable
estimation of the actual costs that would be incurred by the City in the event of such delay. In the event
Contractor's performance under this Agreement is delayed or interfered with, regardless of reason,
Contractor shall not be entitled to any increase in fee or price, or to damages or additional compensation as
a consequence of such delays.
Section 7. Ownership of Project; Bill of Sale; No Liens
(a) Title of Ownership. Contractor warrants that title to all services, including all equipment
and materials incorporated into the Project, will pass to City no later than the time of final payment.
Contractor further warrants that upon payment by City, all services for which payments have been received
from City shall be free and clear of liens, claims, security interests or other encumbrances in favor of
Contractor or any other person or entity whatsoever.
(b) Assignment; Bill of Sale. Contractor agrees, no later than the time of completion of the
Project, to assign to City all manufacturer’s warranties relating to equipment, materials and labor used in
the Project and further agrees it will at all times perform the services in a manner that will, to the greatest
extent possible, preserve all manufacturer’s warranties. If necessary as a matter of law, Contractor may
retain the right to enforce directly any such manufacturers’ warranties during the one year period following
the date of acceptance of the Project by City; provided, that City’s rights related to the same shall not be
subordinate to Contractor’s enforcement rights.
CONTRACTOR AGREES TO INDEMNIFY, DEFEND, AND SAVE CITY HARMLESS FROM ALL
CLAIMS RELATED TO ANY DEMANDS OF SUBCONTRACTORS, LABORERS, WORKMEN,
MECHANICS, MATERIALMEN, AND SUPPLIERS OF MACHINERY AND PARTS THEREOF,
EQUIPMENT, POWER TOOLS, ALL SUPPLIES ARISING OUT OF THE PERFORMANCE OF THIS
AGREEMENT. CONTRACTOR SHALL FURNISH SATISFACTORY EVIDENCE THAT ALL
OBLIGATIONS DESCRIBED HEREIN HAVE BEEN PAID, DISCHARGED OR WAIVED UPON
CITY’S WRITTEN REQUEST.
Section 8. Default; Termination; Abandonment
(a) Default; Notice to Cure. A party shall be deemed in default under this Agreement if the
party is in breach of a material provision of this Agreement and said breach is not cured within ten (10)
days written notice of default by the other party. In the event the breaching party has notified the other
party in writing that it is diligently working to cure the breach and has provided reasonable evidence in
support of the same, the breaching party shall not be deemed in default until the thirtieth (30th) day following
the non-breaching party’s notice of default.
(b) Default by Contractor. In addition to default under Section 7(a) above, Should Contractor
fail to comply with any term or condition this Agreement applicable to Contractor, or become disabled and
unable to comply with any provisions of this Agreement related to the quality or character of the services
or time of performance, Contractor shall be deemed in default of this Agreement. If such default is not
corrected within ten (10) days after written notice by City to Contractor, City may, at its sole discretion and
without prejudice to any other right or remedy:
(1) terminate this Agreement and be relieved of any further payment or consideration to
Contractor except for all services determined by City to be satisfactorily completed prior
to such termination. Payment for work satisfactorily completed shall be for actual costs
_______________________________________________________________________________
6
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
incurred and non-refundable, including reasonable salaries and travel expenses of
Contractor to and from meetings called by City at which Contractor is required to attend,
but shall not include any loss of profit of Contractor. City may further proceed to complete
the services in any manner deemed proper by City, either by the use of its own forces or
by resubletting to others; or
(2) City may, without terminating this Agreement or taking over the services, furnish the
necessary materials, equipment, supplies and/or help necessary to remedy the situation, at
Contractor’s sole expense.
(b) Suspension or Termination by City. City may suspend or terminate this Agreement for
cause or without cause at any time by giving written notice to Contractor. In the event suspension or
termination is without cause, payment to Contractor, in accordance with the terms of this Agreement, will
be made based on services reasonably determined by City to be satisfactorily performed as of the date of
suspension or termination. Such payment will become payable upon delivery of all instruments of service
to City and City’s acceptance of the same. If City requires a modification of the services under this
Agreement, and in the event City and Contractor fail to agree upon such modification(s), City shall have
the option of terminating this Agreement and Contractor's services hereunder at no additional cost other
than the payment to Contractor in accordance with the terms of this Agreement for the services reasonably
determined by City to be properly performed prior to such termination date.
(c) Abandonment. If Contractor should abandon and fail or refuse to resume work within ten
(10) days after written notification from the City, or if Contractor fails to timely comply with the orders of
the City, when such orders are consistent with the Contract Documents, then, and in that case, where a
performance bond(s) exists, the surety on the bond(s) may be notified in writing by City and directed to
complete the work (at City’s sole discretion), and a copy of said notice shall be delivered to Contractor.
After receiving said notice of abandonment, Contractor shall not remove from the work any machinery,
equipment, tools, materials or supplies then on the job, but the same, together with any materials and
equipment under contract for the work, may be held for use on the work by the City or the surety on the
performance bond, or another Contractor in completion of the work; and Contractor shall not receive any
rental or credit therefor, having hereby acknowledged that the use of such equipment and materials will
ultimately reduce the cost to complete the work and be reflected in the final settlement. In the event a surety
fails to comply with City’s written notice provided for herein, then the City may provide for completion of
the work in either of the following elective manners:
(1) the City may employ such labor and use such machinery, equipment, tools, materials and
supplies as said City may deem necessary to complete the work and charge the expense of
such labor, machinery, equipment, tools, materials and supplies to Contractor, which shall
be deducted and paid by City out of such amounts as may be due, or that may thereafter at
any time become due to the Contractor under this Agreement. In case such expense is less
than the sum which would have been payable under this Agreement if the same had been
completed by the Contractor, then Contractor shall receive the difference. In case such
expense is greater than the sum which would have been payable under this Agreement if
the same had been completed by said Contractor, then the Contractor and/or its surety (ies)
shall pay the amount of such excess to the City; or
(2) the City may (under sealed bids when and in the manner required by law) let the contract
to another Contractor for the completion of the work under substantially the same terms
and conditions which are provided in this Agreement. In the case of any increase in cost
to the City under the new contract as compared to what would have been the cost under
this Agreement, such increase shall be charged to the Contractor and its surety (ies) shall
be and remain bound therefor. However, should the cost to complete any such new contract
_______________________________________________________________________________
7
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
prove to be less than what would have been the cost to complete under this Agreement, the
Contractor and/or its surety (ies) shall be credited therewith.
(d) Remedies Cumulative. The remedies in this section are cumulative and nothing herein shall
be deemed a waiver of any other remedy available to the City under this Agreement, including its remedies
upon default provided herein above.
Section 9. Insurance
Contractor shall during the term hereof maintain in full force and effect all policies of insurance
reasonably required by City and in compliance with the Contract Documents. Contractor’s obligation to
provide acceptable certificates of insurance is a material condition of this Agreement, and services under
this Agreement shall not commence until certificates of insurance have been received, reviewed, and
accepted by City. The minimum coverages and limits of liability for the policies of insurance required
under this Agreement are maintained by and accessible through the City’s purchasing department.
Section 10. Indemnification
(a) Release of liability. CITY SHALL NOT BE LIABLE FOR ANY LOSS, DAMAGE, OR
INJURY OF ANY KIND OR CHARACTER TO ANY PERSON OR PROPERTY ARISING FROM THE
SERVICES OF CONTRACTOR PURSUANT TO THIS AGREEMENT. CONTRACTOR HEREBY
WAIVES ALL CLAIMS AGAINST CITY, ITS OFFICIALS, OFFICERS, EMPLOYEES, OR AGENTS
(COLLECTIVELY REFERRED TO IN THIS SECTION AS “CITY”) FOR DAMAGE TO ANY
PROPERTY OR INJURY TO, OR DEATH OF, ANY PERSON ARISING AT ANY TIME AND FROM
ANY CAUSE (OTHER THAN THE GROSS NEGLIGENCE OF CITY, IN WHICH CASE
CONTRACTOR SHALL WAIVE ALL CLAIMS TO THE EXTENT OR PROPORTION OF
NEGLIGENCE ATTRIBUTED TO CONTRACTOR AND/OR ITS OFFICERS, DIRECTORS,
SERVANTS, EMPLOYEES, REPRESENTATIVES, CONSULTANTS, LICENSEES, SUCCESSORS
OR PERMITTED ASSIGNS AS DETERMINED BY A COURT OR OTHER FORUM OF COMPETENT
JURISDICTION).
(b) Contractor’s Indemnity Obligation. CONTRACTOR AGREES TO INDEMNIFY AND
SAVE HARMLESS CITY FROM AND AGAINST ANY AND ALL LIABILITIES, DAMAGES,
CLAIMS, SUITS, COSTS (INCLUDING COURT COSTS, REASONABLE ATTORNEYS’ FEES AND
COSTS OF INVESTIGATION) AND ACTIONS OF ANY KIND BY REASON OF INJURY TO OR
DEATH OF ANY PERSON OR DAMAGE TO OR LOSS OF PROPERTY TO THE EXTENT CAUSED
BY CONTRACTOR’S PERFORMANCE OF SERVICES UNDER THIS AGREEMENT OR BY
REASON OF ANY NEGLIGENT ACT OR OMISSION ON THE PART OF CONTRACTOR, ITS
OFFICERS, DIRECTORS, SERVANTS, EMPLOYEES, REPRESENTATIVES, CONSULTANTS,
LICENSEES, SUCCESSORS OR PERMITTED ASSIGNS (EXCEPT WHEN SUCH LIABILITY,
CLAIMS, SUITS, COSTS, INJURIES, DEATHS OR DAMAGES ARISE, IN WHOLE OR IN PART,
FROM OR ARE ATTRIBUTED TO THE GROSS NEGLIGENCE OF CITY, IN WHICH CASE
CONTRACTOR SHALL INDEMNIFY CITY ONLY TO THE EXTENT OR PROPORTION OF
NEGLIGENCE ATTRIBUTED TO CONTRACTOR AND/OR ITS OFFICERS, DIRECTORS,
SERVANTS, EMPLOYEES, REPRESENTATIVES, CONSULTANTS, LICENSEES, SUCCESSORS
OR PERMITTED ASSIGNS AS DETERMINED BY A COURT OR OTHER FORUM OF COMPETENT
JURISDICTION).
(c) Notice of Claim(s). Contractor shall promptly advise City in writing of any claim or
demand against the City, related to or arising out of Contractor’s acts or omissions under this Agreement
and shall see to the investigation and defense of such claims or demand at Contractor’s sole cost and
expense; provided, that City, at its option and at its own expense, may participate in such defense without
relieving Contractor of any of its obligations hereunder.
_______________________________________________________________________________
8
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
CONTRACTOR’S OBLIGATIONS UNDER THIS SECTION SHALL NOT BE LIMITED TO THE
LIMITS OF COVERAGE OF INSURANCE MAINTAINED OR REQUIRED TO BE MAINTAINED BY
CONTRACTOR UNDER THIS AGREEMENT. THE PROVISIONS OF THIS SECTION 10 SHALL
SURVIVE TERMINATION OF THIS AGREEMENT.
Section 11. Notice
All notices required by this Agreement shall be in writing and addressed to the parties at the
addresses set forth on the signature page(s) of this Agreement (or to such other address that may be
designated by the receiving party from time to time in accordance with this section). All notices shall be
delivered by (a) personal delivery, (b) certified or registered mail (in each case, return receipt requested,
postage prepaid), (c) nationally recognized overnight courier (with all fees pre-paid), or (d) email of a pdf
document containing the required notice. Such notice or document shall be deemed to be delivered or given,
whether actually received or not, (i) when received if delivered or given in person, (ii) if sent by United
States mail, three (3) business days after being deposited in the United States mail as set forth above, (iii)
on the next business day after the day the notice or document is provided to a nationally recognized carrier
to be delivered as set forth above, or (iv) if sent by email, the next business day. A confirmation of delivery
report which reflects the time that the email was delivered to the recipient’s last notified email address is
prima facie evidence of its receipt by the recipient, unless the sender receives a delivery failure notification,
indicating that the email has not been delivered to the recipient.
Section 12. Sales and Use Taxes
Contractor understands and acknowledges that City is a governmental entity and exempt from the
payment of sales and use taxes for certain materials and equipment conveyed to City as part of this Project
or otherwise incorporated into the Project. City agrees to provide Contractor such documentation as may
otherwise be required by state law to allow Contractor to avoid payment of sales and uses taxes for materials
and equipment with respect to the Project to the extent allowed by law.
Section 13. Texas Government Code Verifications
Contractor’s execution of this Agreement shall serve as its acknowledgement and written
verification that: (i) the requirements of Subchapter J, Chapter 552, Government Code, apply to this
Agreement and Contractor agrees that the Agreement can be terminated if Contractor knowingly or
intentionally fails to comply with a requirement of that subchapter; (ii) pursuant to Texas Government Code
Chapter 2270, that Contractor’s organization does not presently boycott Israel and will not boycott Israel
during the term of this Agreement; and (iii) pursuant to Texas Government Code Chapter 2251, that
Contractor’s organization does not current discriminate against firearm and ammunition industries and will
not for the term of the contract. Discriminating means refusing to deal with, terminating business activities
with, or otherwise taking any action that is intended to penalize, inflict economic harm on, or limit
commercial relations specifically with the firearm or ammunition industry or with a person or entity doing
business in the firearm or ammunition industry, but does not include an action made for ordinary business
purposes.
Section 14. Miscellaneous
(a) Contractor shall not assign or sublet this Agreement, in whole or in part, without the prior
written consent of City. (b) Contractor shall comply with all federal, state, county and municipal laws,
ordinances, resolutions, regulations, rules, policies, orders, and directives applicable to the services under
this Agreement. (c) The laws of the State of Texas shall govern this Agreement; and venue for any action
concerning this Agreement shall be in the state district courts of Tarrant County, Texas. The parties agree
to submit to the personal and subject matter jurisdiction of said courts. (d) This Agreement contains the
_______________________________________________________________________________
9
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
entire understanding of the parties with respect to the subject matter hereof and there are no oral
understandings, statements or stipulations bearing upon the meaning or effect of this Agreement which
have not been incorporated herein. (e) The exhibits attached hereto, if any, are incorporated herein and
made a part hereof for all purposes. (f) Unless expressly provided otherwise herein, this Agreement may
only be modified, amended, supplemented or waived by a mutual written agreement of the parties. (g) In
the event any one or more of the provisions contained in this Agreement shall for any reason be held to be
invalid, illegal, or unenforceable in any respect, such invalidity, illegality or unenforceability shall not affect
any other provisions, and the Agreement shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained in it. (h) Any of the representations and obligations of the parties, as
well as any rights and benefits of the parties pertaining to a period of time following the termination of this
Agreement shall survive termination. (i) This Agreement may be executed by the parties in separate
counterparts, each of which when so executed and delivered shall be an original, but all such counterparts
shall together constitute one and the same instrument. Each counterpart may consist of any number of
copies hereof each signed by less than all, but together signed by all of the parties. (j) Each party represents
that it has full capacity and authority to grant all rights and assume all obligations granted and assumed
under this Agreement. (k) Subject to the provisions regarding assignment, this Agreement shall be binding
on and inure to the benefit of the parties to it and their respective heirs, executors, administrators, legal
representatives, successors and assigns.
[REMAINDER OF PAGE LEFT BLANK INTENTIONALLY –
SIGNATURES ON FOLLOWING PAGE(S)]
_______________________________________________________________________________
10
Construction Services Agreement with McDonald Municipal & Industrial- A Division of C.F. McDonald Electric, Inc.
(Bid#ENG-2024-002)
IN WITNESS WHEREOF, the parties have executed and delivered this Agreement as of
the Effective Date.
For City:
CITY OF COLLEYVILLE, TEXAS
By:
Jerry Ducay
City Manager
Date:
For Contractor:
MCDONALD MUNICIPAL &
INDUSTRIAL- A DIVISION OF C.F.
MCDONALD ELECTRIC, INC.
By:
Wayne Berkenmeier
Vice President Special Projects
Date:
Notice Address:
City of Colleyville
Attn: City Manager
100 Main Street, 3rd Floor
City of Colleyville, Texas 76034
E: jducay@colleyville.com
ATTEST:
By:
Christine Loven
City Secretary
Date:
Notice Address:
McDonald Municipal & Industrial- A Division
of C.F. McDonald Electric, Inc.
Attn: Wayne Berkenmeier, Vice President
Special Projects
5044 Timber Creek Dr
Houston, Texas 77017
E: wayneb@mcdonaldinc.com
GovDox Colleyville Contract ID:
CSA_ED_January 3, 2024_Rev20230112
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number 4c Agenda Date 1/16/2024 Number Resolution R-24-4907
Type Resolution
Department Engineering
Title
Approval of an amendment to the Professional Services Agreement with Freese and
Nichols, Inc., amending the design parameters for the Roberts Road Project Phase 2 in
an amount not to exceed $99,730, and authorizing the City Manager to execute the
amendment
Explanation
Reading and Public Hearing
This item is for the consideration and approval of an amendment to increase the
existing Professional Services Agreement with Freese and Nichols, Inc., by $99,730, for
the purpose of designing Phase 2 of the Roberts Road Project.
In October 2023, Council authorized the separation of the project into two phases.
Phase 1 includes the westbound right turn lane on Glade Road, the turn lane and
reconstructed pavement, water, and sewer on Roberts between Glade and the northern
Pleasant Glade Baptist Church driveway, and the driveway and parking lot church
improvements. Phase 1 is currently out for bid.
Phase 2 will include design of the roadway, traffic signalization (pending a signalization
study), drainage, and utility improvements from 300’ north of Glade Road to the City
limits near Birch Avenue. The scope of the improvements include the widening of
Roberts Road to 31’ where possible, and 25’ where constrained by right-of-way;
realigning the roadway utilizing the recently-purchased City property to increase the
curve radius, adding a traffic signal, (pending study) and curb ramps at the
Roberts/Glade Road intersection. Bid plans and specifications and construction phase
services are included in this authorization.
Financial Impact
The TIF is the designated funding source for this project. Prior to this amendment, the
cost for the design of the Roberts Road Project was $418,569.09. If approved, this
would increase the design contract by $99,730.00, for a total not to exceed design cost
of $518,299.09.
Recommendation
Approve
Attachments 1. Contract Amendment 4
Fourth Amendment to Professional Services Agreement 1
FOURTH AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
This Fourth Amendment to Professional Services Agreement (“Fourth Amendment”) is
entered by and between the City of Colleyville, Texas (“City”) and Freese and Nichols Inc.,
(“Professional”) as of the Effective Date.
WHEREAS, the parties desire to further amend that certain Professional Services
Agreement for improvements to Roberts Road, effective February 5, 2019 (“the Agreement”), as
amended on September 9, 2019, (“First Amendment”), and April 29, 2020, (“Second
Amendment”), and October 31, 2023 (“Third Amendment”); and
WHEREAS, City and Professional now desire to amend the terms of the Agreement in the
manner provided herein.
NOW THEREFORE, for and in consideration of the mutual covenants made herein and
other good and valuable consideration, the receipt and sufficiency of which is hereby
acknowledged, City and Professional agree as follows:
1.Exhibit A of the Agreement (Scope of Services) is hereby amended to incorporate the
revisions to the Project scope contained in Contract Amendment #4 attached hereto and
incorporated herein as Exhibit A to this Fourth Amendment.
2.The total compensation amount stated in Section 4(C) of the Agreement (entitled
“Payment”) is hereby amended to provide for a total not to exceed amount of
$518,299.09.
3.Except as provided in Paragraphs 1 and 2 above, the provisions of the Agreement, as
previously amended, remain in full force and effect.
4.This Fourth Amendment shall be deemed effective on the date it has been signed by the
authorized representatives of City and Professional (“the Effective Date”).
[REMAINDER OF PAGE INTENTIONALLY LEFT BLANK –
SIGNATURE PAGE FOLLOWS]
Fourth Amendment to Professional Services Agreement 2
The parties have executed and delivered this Fourth Amendment as of the Effective Date.
For City:
CITY OF COLLEYVILLE, TEXAS
r1|Signature]
By:
Jerry Ducay
City Manager
Date:
For Professional:
FREESE AND NICHOLS, INC.
[sig|req|signer2|Signature]
By:
Name:
Title:
[date|req|signer2|Date of Signing]
Date:
Fourth Amendment to Professional Services Agreement 3
EXHIBIT A
Contract Amendment #4
Revised Scope of Services
(attached)
Exhibit “A”
Page 1 of 7
EXHIBIT “A”
PROFESSIONAL ENGINEERING SERVICES
Contract Amendment #4
Roadway, Traffic Signal, Drainage, and Utility Improvements for Roberts Road Phase 2, from 300’ North of
Glade Road to City Limits near Birch Avenue in Colleyville, Texas
The scope set forth herein defines the work to be performed by Freese and Nichols, Inc. (FNI) and the City of
Colleyville, Texas (CITY) in completing the project. Both the CITY and FNI have attempted to clearly define the
work to be performed and address the needs of the project.
The proposed improvements will include roadway, drainage, traffic signal, and utility improvements for
Roberts Road (minor arterial), from 300’ North of Glade Road to City Limits near Birch Avenue (approximately
2,100 feet in total length). Improvements are anticipated to include:
-Design roadway and drainage improvements for Roberts Road similar to the previously proposed
Roberts Road improvements with the following revisions:
o Widen Roberts Road to 31’ BOC-BOC where possible and 25’ BOC-BOC where constrained by
ROW
o Realign Roberts Road utilizing recently-purchased City property to increase curve radius
o Add traffic signal and curb ramps at the Roberts Rd/Glade Rd intersection
o Proposed improvements will stop at City limits boundary and will not include previously-
proposed improvements at the Birch intersection or water interconnect meter vault
-Previous design will be reviewed and updated as needed but with a similar overall scope.
-Additional bid phase and construction phase services will be added for Phase 2.
The project construction will be completed using CITY funding sources; therefore, the project will be designed
in compliance with CITY standards and processes. TxDOT standards and processes will be utilized for subjects
not covered by CITY standards and processes.
Basic Services
Task 1 Project Management
Task 2 30% Design
Task 3 90% Design
Task 4 100% Design
Task 5 Bid Phase Services
Task 6 Construction Phase Services
Special Services
Task 7 Franchise Utility Coordination
Task 8 TDLR/TAS Plan Review and Inspection
Exhibit “A”
Page 2 of 7
FNI will render the following professional engineering services in connection with the development of the
project:
BASIC SERVICES
Task 1 - Project Management
FNI will manage the work outlined in this scope to ensure efficient and effective use of FNI’s and CITY’s time
and resources. FNI will manage change, communicate effectively, coordinate internally and externally as
needed, and proactively address issues with the CITY’s Project Manager and others as necessary to make
progress on the work. FNI will:
A.Attend Phase 2 project kickoff meeting with CITY.
B.Prepare and submit a project schedule to the CITY.
C.Conduct and document up to two (2) project update or review meetings with CITY Project Manager
(not including post submittal meetings).
D.Conduct miscellaneous internal design team coordination meetings.
E.Prepare and submit monthly invoices with project status reports and project schedule updates, as
necessary (up to 9).
F.FNI will make up to two (2) site visits to become familiar with site and observe existing conditions.
Deliverables:
i.Meeting summary notes focusing on decisions and action items.
ii.Design schedule (including baseline and necessary updates).
iii.Monthly invoices and project status reports.
Task 2 – 30% Design
A.FNI will collect relevant project data (such as contour data, aerial imagery, and record drawings) from
CITY and other available sources.
B.FNI will provide 30% Design services to the CITY with the following design plans. All information listed
will be provided on the design plans:
GENERAL
o COVER SHEET
o INDEX OF SHEETS
o PROJECT LAYOUT AND SURVEY CONTROL DATA
o HORIZONTAL ALIGNMENT DATA
o TYPICAL SECTIONS
o GENERAL NOTES
o SUMMARY SHEETS
o CONSTRUCTION PHASING TYPICAL SECTIONS
o CONSTRUCTION PHASING PLANS
o DETOUR PLANS
o REMOVAL PLANS
ROADWAY
o ROADWAY PLAN AND PROFILE
Exhibit “A”
Page 3 of 7
o INTERSECTION LAYOUTS
DRAINAGE
o DRAINAGE CALCULATIONS
o OVERALL DRAINAGE AREA MAP
o STORM DRAIN PLAN AND PROFILE
TRAFFIC SIGNAL
o EXISTING INTERSECTION LAYOUT
o PROPOSED SIGNAL LAYOUT
PAVEMENT MARKING AND SIGNAGE
o PAVEMENT MARKING AND SIGNAGE PLAN
EROSION CONTROL
o EROSION CONTROL PLAN
WATER LINE
o WATER LINE PLAN AND PROFILE
SANITARY SEWER LINE
o SANITARY SEWER PLAN AND PROFILE
CROSS SECTIONS
o CROSS SECTIONS
C.FNI will develop an opinion of probable construction cost (OPCC) based on 30% Design. Sources of data
used in the preparation of the OPCC include construction data aggregation services, similar past project
performed by FNI, bid results from previous CITY projects of similar type, and FNI experience and
engineering judgement.
D.FNI will conduct QC/QA of the 30% Design deliverables.
E.FNI will attend one (1) post-submittal meeting for the 30% Design with CITY.
F.For 30% Design, FNI will provide CITY with of three (3) copies of half size (11”x17”) drawings, three (3)
copies of the opinion of probable construction cost, and PDF copy of the above items.
Deliverables:
i.30% Design Plans
ii.Opinion of Probable Construction Costs (OPCC)
iii.QC/QA Documentation
Exhibit “A”
Page 4 of 7
Task 3 – 90% Design
A.After review and approval of the 30% Design by the CITY and TxDOT, FNI will provide 90% Design
services.
B.FNI will provide 90% Design services by progressing, updating, or revising the plans listed in the 30%
Design submittal and the additional design plans:
GENERAL
o CITY/TXDOT STANDARDS
ROADWAY
o ROADWAY SPECIAL DETAILS
o CITY/TXDOT STANDARDS
DRAINAGE
o CITY/TXDOT STANDARDS
TRAFFIC SIGNAL
o TRAFFIC SIGNAL INTERSECTION QUADRANT DETAILS
o TRAFFIC SIGNAL SUMMARY
o CHANNLE ASSIGNMENT DIAGRAM
o CITY/TXDOT STANDARDS
PAVEMENT MARKING AND SIGNAGE
o CITY/TXDOT STANDARDS
EROSION CONTROL
o CITY/TXDOT STANDARDS
WATER LINE
o CITY/TXDOT STANDARDS
SANITARY SEWER LINE
o CITY/TXDOT STANDARDS
CROSS SECTIONS
C.FNI will develop an opinion of probable construction cost (OPCC) based on 90% Design plans. Sources
of data used in the preparation of the OPCC include construction data aggregation services, similar past
project performed by FNI, bid results from previous CITY projects of similar type, and FNI experience
and engineering judgement.
D.FNI will prepare construction specifications documents utilizing CITY and TxDOT standard documents
for the 90% Design.
E.FNI will conduct QC/QA and constructability review of the 90% Design deliverables.
F.FNI will attend one (1) post-submittal meeting for the 90% Design with CITY.
G.For the 90% Design, FNI will provide CITY with of three (3) copies of half size (11”x17”) drawings, one
(1)copy of the project construction specifications, three (3) copies of the opinion of probable
construction cost, and PDF copy of the above items.
Deliverables:
i.90% Design Plans
ii.Opinion of Probable Construction Costs (OPCC)
Exhibit “A”
Page 5 of 7
iii.Construction Specifications
iv.QC/QA Documentation
Task 4 – 100% Design
A.After review and approval of the 90% Design by the CITY and TxDOT, FNI will provide 100% Design
services.
B.FNI will provide 100% Design services by progressing, updating, or revising the plans listed in the 90%
Design submittal.
C.FNI will develop an opinion of probable construction cost (OPCC) based on 100% Design plans. Sources
of data used in the preparation of the OPCC include construction data aggregation services, similar
past project performed by FNI, bid results from previous CITY projects of similar type, and FNI
experience and engineering judgement.
D.FNI will prepare construction specifications documents utilizing CITY and TxDOT standard documents
for the 100% Design.
E.For the 100% Design, FNI will provide CITY with of three (3) copies of half size (11”x17”) drawings, one
(1) copy of the project construction specifications, three (3) copies of the opinion of probable
construction cost, and PDF copy of the above items.
Deliverables:
i.100% Design Plans
ii.Opinion of Probable Construction Costs (OPCC)
iii.Construction Specifications
iv.QC/QA Documentation
Task 5 - Bid Phase Services
Upon completion of the design services and approval of “Final” drawings and specifications by CITY, FNI will
proceed with the performance of services in this phase as follows:
A.Assist the CITY by attending a pre-bid conference for the construction projects and coordinating
responses with CITY. Response to the pre-bid conference will be in the form of addenda issued after
the conference.
B.Assist CITY by responding to questions and interpreting bid documents. Prepare addenda to the bid
documents if necessary.
C.At CITY request, FNI will assist in the opening, tabulating, and analyzing the bids received. Review the
qualification information provided by the apparent low bidder to determine if, based on the
information available, they appear to be qualified to construct the project. Recommend award of
contracts or other actions as appropriate.
Task 6 - Construction Phase Services
Upon completion of the bid or negotiation phase services, FNI will proceed with the performance of
construction phase services as described below. FNI will endeavor to protect City in providing these services
however, it is understood that FNI does not guarantee the Contractor’s performance, nor is FNI responsible
Exhibit “A”
Page 6 of 7
for supervision of the Contractor’s operation and employees. FNI shall not be responsible for the means,
methods, techniques, sequences or procedures of construction selected by the
Contractor, or any safety precautions and programs relating in any way to the condition of the premises, the
work of the Contractor or any Subcontractor. FNI shall not be responsible for the acts or omissions of any
person (except its own employees or agents) at the Project site or otherwise performing any of the work of
the Project.
These services are based on the use of FNI’s standard General Conditions for construction projects.
Modifications to these services required by use of other general conditions or contract administration
procedures are an additional service. If general conditions other than FNI standards are used, the City agrees
to include provisions in the construction contract documents that will require the construction contractor to
include FNI and their subconsultants on this project to be listed as an additional insured on contractor’s
insurance policies.
A.The construction of this Project is assumed to last approximately 9 months and to be City let and
administered.
B.Assist City and by attending a pre-construction conference(s) with the Contractor(s), review
construction schedules prepared by the Contractor(s) pursuant to the requirements of the construction
contract and prepare a proposed estimate of monthly cash requirements of the Project from
information provided by the Construction Contractor.
C.Attend up to nine (9) monthly construction progress meetings. Includes up to four (4) site visits to
address questions that need to be addressed on site. Visits to the site in excess of the specified number
are an additional service.
D.Notify City of contractor’s non-conforming work observed on site visits. Review quality related
documents provided by the contractor such as test reports or other documentation required by the
Construction contract documents.
E.Interpret the drawings and specifications for City and Contractor(s). Investigations, analyses, and
studies requested by the Contractor(s) and approved by City, for substitutions of equipment and/or
materials or deviations from the drawings and specifications is an additional service.
F.If requested, assist City in negotiations with the contractor on behalf of the City to determine the cost
and time impacts of these changes. Review change order documentation for approved changes for
execution by the City. Documentation of field orders, where cost to City is not impacted, will also be
prepared. Investigations, analyses, studies or design for substitutions of equipment or materials,
corrections of defective or deficient work of the contractor or other deviations from the construction
contract documents requested by the contractor and approved by the City are an additional service.
Substitutions of materials or equipment or design modifications requested by the City are an additional
service.
G.Receive and evaluate notices of contractor claims and make recommendations to the City on the merit
and value of the claim on the basis of information submitted by the contractor or available in project
documentation. Endeavor to negotiate a settlement value with the Contractor on behalf of the City if
Exhibit “A”
Page 7 of 7
appropriate. Providing these services to review or evaluate construction contractor(s) claim(s),
supported by causes not within the control of FNI are an additional service.
H. Conduct, in company with City’s representative, a final review of the Project for conformance with the
design concept of the Project and general compliance with the Construction Contract Documents.
Prepare a list of deficiencies to be corrected by the contractor before recommendation of final
payment. Assist the City in obtaining legal releases, permits, warranties, spare parts, and keys from
the contractor. Review and comment on the certificate of completion and the recommendation for
final payment to the Contractor(s). Visiting the site to review completed work in excess of two trips are
an additional service.
I. Revise the construction drawings in accordance with the information furnished by construction
Contractor(s) reflecting changes in the Project made during construction. One (1) PDF of “Record
Drawings” shall be provided by FNI to City.
SPECIAL SERVICES
Task 7 - Franchise Utility Coordination
A. FNI will coordinate with franchise utilities within the project limits to determine if any facilities have
changed since the project began in 2019.
B. FNI will conduct up to three (3) franchise utility coordination meetings.
Task 8 - TDLR/TAS Plan Review and Inspection
A. FNI will provide permitting support for the CITY and will prepare plan layouts for Americans with
Disabilities Act (ADA) and TDLR compliant sidewalks, curb ramps, pedestrian push buttons, and
crosswalks.
B. FNI will retain the services of a TDLR Registered Accessibility Specialist (RAS) Inspector approved by the
CITY.
C. FNI will be responsible for completing and submitting the inspection forms, paperwork, and RAS plan
review during the design phase as required by the TDLR.
D. During the construction phase, the CITY will coordinate one (1) RAS inspection with FNI and RAS
Inspector no later than thirty (30) calendar days after construction substantial completion.
E. FNI will be compensated for the RAS Inspector costs by the CITY as a reimbursable expense.
Basic Services (Not-to-Exceed)Original Authorization Amendment #1 Amendment #2 Amendment #3 Amendment #4
Project Administration 11,199.00$ -$ -$ 5,870.00$ 10,721.00$
Roadway Design - Colleyville 116,625.00$ -$ 15,182.00$ 32,718.00$ 67,638.00$
Roadway Design - Grapevine -$ 10,595.00$ -$ -$ -$
Water and Sewer Design - Colleyville -$ -$ 109,153.00$ -$ -$
Bid Phase 5,934.00$ -$ -$ -$ 6,429.00$
Construction Phase 13,702.00$ -$ -$ -$ 11,710.00$
Basic Services (Not-to-Exceed) Subtotal 147,460.00$ 10,595.00$ 124,335.00$ 38,588.00$ 96,498.00$
Special Services (Not-to-Exceed)Original Authorization Amendment #1 Amendment #2 Amendment #3 Amendment #4
Public Meeting 4,440.00$ (4,440.00)$ -$ -$ -$
Environmental 7,604.00$ -$ -$ (4,064.91)$ -$
Topographic Survey - Colleyville 17,969.00$ -$ -$ -$ -$
Topographic Survey - Grapevine -$ 3,393.00$ -$ -$ -$
ROW Documents 2,760.00$ -$ -$ -$ -$
TDLR Registration, Review, and Inspection 1,035.00$ -$ -$ -$ 1,226.00$
Water Design - Grapevine (50%)-$ 32,693.50$ -$ -$ -$
Water Design - Colleyville (50%)-32,693.50$ -$ -$ -$
Franchise Utility Coordination -$ -$ -$ -$ 2,006.00$
Glade Road - Right Turn Lane -$ 3,508.00$ -$ -$ -$
Special Services (Not-to-Exceed) Subtotal 33,808.00$ 67,848.00$ -$ (4,064.91)$ 3,232.00$
Authorization Total 181,268.00$ 78,443.00$ 124,335.00$ 34,523.09$ 99,730.00$
Project Total Fee 181,268.00$ 259,711.00$ 384,046.00$ 418,569.09$ 518,299.09$
City of Colleyville - Roberts Road
Amendment No. 4 - Fee Summary
ID Task Name Duration Start Finish Predecessors
0 Roberts Road - Phase 2 481 days 2/5/2024 12/8/2025
1 Design and Construction Phase 481 days 2/5/2024 12/8/2025
2 Notice to Proceed 0 days 2/5/2024 2/5/2024
3 Project Setup 5 days 2/5/2024 2/9/2024 2
4 Task 1 - Project Management 189 days 2/5/2024 10/24/2024
5 Project Review Meetings and Invoicing 189 days 2/5/2024 10/24/2024 2
6 Task 2 - 30% Design 70 days 2/12/2024 5/17/2024
7 Prepare 30% Design 45 days 2/12/2024 4/12/2024 3
8 Internal 30% Design QC 10 days 4/15/2024 4/26/2024 7
9 External 30% Design Submittal 0 days 4/26/2024 4/26/2024 8
10 City Review of 30% Design 15 days 4/29/2024 5/17/2024 9
11 Task 3 - 90% Design 58 days 5/20/2024 8/7/2024
12 Prepare 90% Design 35 days 5/20/2024 7/5/2024 10
13 Internal 90% Design QC 8 days 7/8/2024 7/17/2024 12
14 External 90% Design Submittal 0 days 7/17/2024 7/17/2024 13
15 City Review of 90% Design 15 days 7/18/2024 8/7/2024 14
16 Task 4 - 100% Design 48 days 8/8/2024 10/14/2024
17 Prepare 100% Design 25 days 8/8/2024 9/11/2024 15
18 Internal 100% Design QC 8 days 9/12/2024 9/23/2024 17
19 External 100% Design Submittal 0 days 9/23/2024 9/23/2024 18
20 City Review of 100% Design 15 days 9/24/2024 10/14/2024 19
21 Task 5 - Bid Phase Services 85 days 10/15/2024 2/10/2025
22 Advertising and Letting (Local Let)35 days 10/15/2024 12/2/2024 20
23 Contractor Selection 10 days 12/3/2024 12/16/2024 22
24 City Council Review and Approval 30 days 12/17/2024 1/27/2025 23
25 Construction Contracting 10 days 1/28/2025 2/10/2025 24
26 Task 6 - Construction Phase Services 200 days 2/11/2025 11/17/2025
27 Construction Phase Services 200 days 2/11/2025 11/17/2025 25
28 Task 7 - Franchise Utility Coordination 176 days 2/12/2024 10/14/2024
29 Franchise Utility Coordination 176 days 2/12/2024 10/14/2024 3
30 Task 8 - TDLR/TAS Plan Review and Inspection 300 days 10/15/2024 12/8/2025
31 Plan review 15 days 10/15/2024 11/4/2024 20
32 Post Construction Inspection 15 days 11/18/2025 12/8/2025 27
Roberts Road - Phase 2
Design and Construction Phase
2/5 Notice to Proceed
Project Setup
Task 1 - Project Management
Project Review Meetings and Invoicing
Task 2 - 30% Design
Prepare 30% Design
Internal 30% Design QC
4/26 External 30% Design Submittal
City Review of 30% Design
Task 3 - 90% Design
Prepare 90% Design
Internal 90% Design QC
7/17 External 90% Design Submittal
City Review of 90% Design
Task 4 - 100% Design
Prepare 100% Design
Internal 100% Design QC
9/23 External 100% Design Submittal
City Review of 100% Design
Task 5 - Bid Phase Services
Advertising and Letting (Local Let)
Contractor Selection
City Council Review and Approval
Construction Contracting
Task 6 - Construction Phase Services
Construction Phase Services
Task 7 - Franchise Utility Coordination
Franchise Utility Coordination
Task 8 - TDLR/TAS Plan Review and Inspection
Plan review
Post Construction Inspection
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M
Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Page 1 of 1
Date: 12/18/2023
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number 4d Agenda Date 1/16/2024 Number Resolution R-24-4907
Type Resolution
Department Engineering
Title
Approval of an amendment to the Professional Services Agreement with Freese and
Nichols, Inc., amending the design parameters for the Roberts Road Project in an
amount not to exceed $8,400, and authorizing the City Manager to execute the
amendment
Explanation
Reading and Public Hearing
This item is for the consideration and approval of an amendment to increase the
existing Professional Services Agreement with Freese and Nichols, Inc., by $8,400, for
the purpose of conducting a signal warrant analysis for the Roberts Road Project.
Freese and Nichols will perform a traffic signal warrant analysis for the intersection of
Roberts and Glade Road. The analysis will include turning movement counts for the
intersection; intersection traffic count data to determine if the intersection warrant
traffic signalization based on volumes as set for in the latest edition of the Manual on
Uniform Traffic Control Devices; and preparation of a technical memorandum detailing
the results and analysis. The warrant analysis will be based on existing traffic and
proposed Phase 1 lane geometry conditions at the intersection.
Financial Impact
The TIF is the designated funding source for this project. Prior to this amendment, the
cost for the design of the Roberts Road Project was $518,299.09. If approved, this
would increase the design contract by $8,400.00, for a total not to exceed design cost
of $526,699.99.
Recommendation
Approve
Attachments
1.Contract Amendment 5
Fifth Amendment to Professional Services Agreement 1
FIFTH AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
This Fifth Amendment to Professional Services Agreement (“Fifth Amendment”) is
entered by and between the City of Colleyville, Texas (“City”) and Freese and Nichols Inc.,
(“Professional”) as of the Effective Date.
WHEREAS, the parties desire to further amend that certain Professional Services
Agreement for improvements to Roberts Road, effective February 5, 2019 (“the Agreement”), as
amended on September 9, 2019, (“First Amendment”), and April 29, 2020, (“Second
Amendment”), and October 31, 2023 (“Third Amendment”), and January 16, 2024 (“Fourth
Amendment”); and
WHEREAS, City and Professional now desire to amend the terms of the Agreement in the
manner provided herein.
NOW THEREFORE, for and in consideration of the mutual covenants made herein and
other good and valuable consideration, the receipt and sufficiency of which is hereby
acknowledged, City and Professional agree as follows:
1.Exhibit A of the Agreement (Scope of Services) is hereby amended to incorporate the
revisions to the Project scope contained in Contract Amendment #5 attached hereto and
incorporated herein as Exhibit A to this Fifth Amendment.
2.The total compensation amount stated in Section 4(C) of the Agreement (entitled
“Payment”) is hereby amended to provide for a total not to exceed amount of
$526,699.09.
3.Except as provided in Paragraphs 1 and 2 above, the provisions of the Agreement, as
previously amended, remain in full force and effect.
4.This Fifth Amendment shall be deemed effective on the date it has been signed by the
authorized representatives of City and Professional (“the Effective Date”).
[REMAINDER OF PAGE INTENTIONALLY LEFT BLANK –
SIGNATURE PAGE FOLLOWS]
Fifth Amendment to Professional Services Agreement 2
The parties have executed and delivered this Fifth Amendment as of the Effective Date.
For City:
CITY OF COLLEYVILLE, TEXAS
r1|Signature]
By:
Jerry Ducay
City Manager
Date:
For Professional:
FREESE AND NICHOLS, INC.
[sig|req|signer2|Signature]
By:
Name:
Title:
[date|req|signer2|Date of Signing]
Date:
Fifth Amendment to Professional Services Agreement 3
EXHIBIT A
Contract Amendment #5
Revised Scope of Services
(attached)
Page 1 of 2
EXHIBIT A
Scope of Services for
Roberts Road from Glade Road to Birch Avenue
Contract Amendment #5
Project Understanding:
The City of Colleyville intends to conduct a traffic signal warrant at the intersection of Roberts Road and
Glade Road. This amendment covers obtaining traffic counts, effort required to conduct the signal warrant
analysis, and effort to summarize and provide the results to the City.
Special Services
A.Obtain and Review Traffic Counts (Task 1)
The Traffic Count Data shall be submitted to the OWNER per the approved Project Schedule.
a.FNI will obtain and review traffic counts as follows.
i.FNI will contract with a professional traffic counting firm to obtain turning
movement counts at the intersection of Roberts Road at W Glade Road. The
traffic counts will include 24-hr weekday turning movement counts scheduled
on a Tuesday, Wednesday, or Thursday while schools are in session.
ii.FNI will review and summarize the traffic count data for input into the Traffic
Signal Warrant Analysis.
b.ASSUMPTIONS
i.All traffic counts will be summarized in 15-minute intervals and include basic
vehicle classification.
c.DELIVERABLES
i.Detailed intersection turning movement count data
B.Perform Traffic Signal Warrant Analysis (Task 2)
The traffic signal warrant analysis results shall be submitted to the OWNER per the approved
Project Schedule.
FNI will perform traffic signal warrant analysis as follows:
a.FNI will analyze the intersection traffic count data to determine if the intersection meets
traffic signal warrants based on volumes (Warrant 1, 2 & 3) as set forth in the latest
edition of the Manual on Uniform Traffic Control Devices (MUTCD). Warrant analysis
would be based on existing traffic and proposed Phase 1 lane geometry conditions at
the intersection.
b.FNI will prepare a technical memorandum detailing the results of the traffic signal
warrant analyses and provide supporting information.
c.FNI will conduct a maximum of one (1) review meeting with OWNER staff to discuss the
results of the analysis.
d.ASSUMPTIONS
Page 2 of 2
i.The review meeting with OWNER staff will be conducted virtually using
Microsoft Teams.
ii.All deliverables will be provided in an electronic format via email.
iii.No traffic analysis will be performed except that required to determine if the
intersection meets a traffic signal warrant
e.DELIVERABLES
i.Technical memorandum detailing the results of the traffic signal warrant
analyses including traffic count data.
COMPENSATION
FNI agrees to provide the professional services described above for a price not to exceed amount of
eight thousand six hundred dollars and zero cents ($8,400.00).
Basic Services (Not-to-Exceed)Original Authorization Amendment #1 Amendment #2 Amendment #3 Amendment #4 Amendment #5
Project Administration 11,199.00$ -$ -$ 5,870.00$ 10,721.00$ -$
Roadway Design - Colleyville 116,625.00$ -$ 15,182.00$ 32,718.00$ 67,638.00$ 8,400.00$
Roadway Design - Grapevine -$ 10,595.00$ -$ -$ -$ -$
Water and Sewer Design - Colleyville -$ -$ 109,153.00$ -$ -$ -$
Bid Phase 5,934.00$ -$ -$ -$ 6,429.00$ -$
Construction Phase 13,702.00$ -$ -$ -$ 11,710.00$ -$
Basic Services (Not-to-Exceed) Subtotal 147,460.00$ 10,595.00$ 124,335.00$ 38,588.00$ 96,498.00$ 8,400.00$
Special Services (Not-to-Exceed)Original Authorization Amendment #1 Amendment #2 Amendment #3 Amendment #4 Amendment #5
Public Meeting 4,440.00$ (4,440.00)$ -$ -$ -$ -$
Environmental 7,604.00$ -$ -$ (4,064.91)$ -$ -$
Topographic Survey - Colleyville 17,969.00$ -$ -$ -$ -$ -$
Topographic Survey - Grapevine -$ 3,393.00$ -$ -$ -$ -$
ROW Documents 2,760.00$ -$ -$ -$ -$ -$
TDLR Registration, Review, and Inspection 1,035.00$ -$ -$ -$ 1,226.00$ -$
Water Design - Grapevine (50%)-$ 32,693.50$ -$ -$ -$ -$
Water Design - Colleyville (50%)-32,693.50$ -$ -$ -$ -$
Franchise Utility Coordination -$ -$ -$ -$ 2,006.00$ -$
Glade Road - Right Turn Lane -$ 3,508.00$ -$ -$ -$ -$
Special Services (Not-to-Exceed) Subtotal 33,808.00$ 67,848.00$ -$ (4,064.91)$ 3,232.00$ -$
Authorization Total 181,268.00$ 78,443.00$ 124,335.00$ 34,523.09$ 99,730.00$ 8,400.00$
Project Total Fee 181,268.00$ 259,711.00$ 384,046.00$ 418,569.09$ 518,299.09$ 526,699.09$
City of Colleyville - Roberts Road
Amendment No. 5 - Fee Summary
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number 4e Agenda Date 1/16/2024 Number Resolution R-23-4907
Type Resolution
Department Engineering
Title
Approval to purchase a replacement Vactor 2100i Sewer Cleaner truck from Kinlock
Equipment & Supply, Inc., through the HGAC Purchasing Program in an amount not to
exceed $514,214.00, and authorizing the City Manager to execute the contract
Explanation
Reading and Public Hearing
This item seeks approval to purchase a replacement Vactor 2100i Sewer Cleaner truck
for the Public Works Wastewater Division from Kinlock Equipment & Supply, Inc.,
through the HGAC Purchasing Program in an amount not to exceed $514,214.00.
The City uses a combination vacuum and hydro-jetting vehicle to perform required
maintenance on the City’s 179 miles of sewer line. This equipment cleans and removes
debris such as roots, rags, sludge, fats, oils, and grease from the sewer collection
system to prevent sanitary sewer overflows. In addition, the Vactor truck is utilized to
locate underground utilities (water and sewer lines) prior to excavation repairs. Unlike
backhoes or other excavating equipment, the Vactor truck uses high pressure water
that reduces potential damage to fragile underground utility infrastructure.
In order to maintain the City's fleet in an effective and efficient manner, the vehicles are
replaced at established milestones. Criteria considered when determining the end of a
vehicle's useful life includes, but is not limited to mileage, age, motor hours, past
maintenance, and overall condition.
The existing Vactor truck will be retained as a back-up unit, and could be utilized by the
Drainage Division as preventative maintenance of main line cleaning in the storm water
sewer system.
The State mandates only a franchise motor vehicle dealer can legally pass title on a new
motor vehicle. The proposed Vactor unit is mounted on an International HV607 chassis
and the cooperative purchasing contract being utilized through HGAC is with Santex
Truck Centers, dba Kyrish Truck Center. If approved, the purchase order generated will
be issued to Santex Truck Centers, dba Kyrish Truck Center. Kinlock Equipment &
Supply, Inc., will coordinate the installation and delivery of the Vactor equipment, and
provide training to City staff.
City of Colleyville Page 2
City Council Agenda Briefing 4e
Financial Impact
Funding for this replacement equipment is available in the Utility Capital Projects Fund.
Recommendation
Approve
Attachments
1.Vactor 2100i HGAC Proposal
2.HGAC Cost Breakdown
Dan Federico
Tel: 813.713.1455
Quote Number: 2023-70307
Presents a Proposal Summary
of the
2100i
Combination Single Engine Sewer Cleaner with Positive Displacement Vacuum System Mounted on a
Heavy-Duty International HV607 Truck Chassis
For
Quote Number: 2023-70307
PRODUCT DESCRIPTION
ꞏ 2100i with Roots 824-16" Hg. Blower, 10 Yard Debris body, 1000 Gallons of Fresh Water
STANDARD FEATURES
ꞏ 48" x 22" x 24" Curb Side Aluminum Toolbox
ꞏ Aluminum Fenders
ꞏ Mud Flaps
ꞏ Electric/Hydraulic Four Way Boom
ꞏ Color Coded Sealed Electrical System
ꞏ Intuitouch Electronic Package
ꞏ Double Acting Dump Hoist Cylinder
ꞏ 3" Y-Strainer at Water Pump Inlet
ꞏ Ex-Ten Steel Cylindrical Debris Tank
ꞏ Flexible Hose Guide
ꞏ (3) Nozzles with Carbide Inserts w/Rack
ꞏ Vacuum Tube Storage: Rear Door (2) Pipe
ꞏ 1" Nozzle Pipe
ꞏ 10' Leader Hose
ꞏ Flat Rear Door w/Hydraulic Locks
ꞏ Dual Stainless Steel Float Shut Off
ꞏ Debris Body Vacuum Relief System
ꞏ Debris Deflector Plate
ꞏ 48" Dump Height
ꞏ Additional Water Tank Sight Guage
ꞏ Liquid Float Level Indicator
ꞏ Boom Transport Post Storage
ꞏ 3" Y-Strainer @ Water Pump
ꞏ 1" Water Relief Valve
ꞏ Microstrainer Prior to Blower
ꞏ Midship Handgun Coupling
ꞏ Side Mounted Water Pump
ꞏ Hose Wind Guide (Dual Roller)
ꞏ Hose Reel Manual Hyd. Extend/Retract
ꞏ Hose Reel Chain Cover (Full)
ꞏ Hydraulic Extending 15", Rotating Hose Reel, 1" x 800' Capacity
ꞏ Tachometer & Hourmeter/Blower
ꞏ Circuit Breakers
ꞏ LED Lights. Clearance, Back-Up, Stop, Tail & Turn
ꞏ Tow Hooks, Front and Rear
ꞏ Electronic Back-Up Alarm
ꞏ Module Paint, Dupont Imron Elite - Sanded Primer Base
ꞏ 7" Vacuum Pipe Package
ꞏ Emergency Flare Kit
ꞏ Fire Extinguisher 5 Lbs.
ꞏ Fixed Rear Door Pipe Rack, 7" Pipe
ꞏ Low Water Alarm with Water Pump Flow Indicator
ꞏ Joystick Boom Control
ꞏ Rodder System Accumulator- Jack Hammer on/off control w/ manual valve
ꞏ Digital Hose Footage Counter
ꞏ Water Pump Hour Meter
ꞏ PTO Hour Meter
ꞏ Hydraulic Oil Temp Alarm
ꞏ Digital Water Pressure Gauge
ADDITIONAL FEATURES
Quote Number: 2023-70307
ꞏ Roots 824-16" Hg. Blower
ꞏ 180 Degree Rotation, 10’ x 15’ Rapid Deployment Boom
ꞏ Rotatable Boom Inlet Hose
ꞏ 80 GPM Variable Flow Water System
ꞏ 2500 PSI Water Pressure
ꞏ Hydraulic Cooling Package
ꞏ 1" x 800' Piranha Sewer Hose, 2500 PSI
ꞏ Debris Body Washout
ꞏ 6" Rear Door Knife Valve w/ Camloc w/Port, 6:00 position
ꞏ Centrifugal Separators (Cyclones)
ꞏ Folding Pipe Rack, Curbside, Hydraulic 7" Pipe
ꞏ Folding Pipe Rack, Streetside, Hydraulic 7" Pipe
ꞏ Rear Door Splash Shield
ꞏ Lube Manifold
ꞏ Plastic Lube Chart
ꞏ Digital Debris Body Level Indicator Tied to Vacuum Relief
ꞏ Bellypack Wireless Controls w/ Hose Reel Controls- 2 Way Communications & LED Display
ꞏ Hot Shift Blower Drive (automatic transmission)
ꞏ Cold Weather Recirculator, PTO Driven, 25 GPM
ꞏ Handgun Couplers, Front and Rear
ꞏ Hydro Excavation Kit - Includes Lances w/ Shield, Nozzles, Storage Tray, and Vacuum Tube
ꞏ Hose Wind Guide (Dual Roller), Auto, Non-Indexing
ꞏ Rodder Hose Pinch Roller
ꞏ High Pressure Hose Reel (Mid-Ship, Passenger Side)
ꞏ High Pressure Hose Reel (Front Bumper Mounted, Drivers Side)
ꞏ Digital Water Level Indicator
ꞏ Rodder Pump Drain Valves
ꞏ Rear Directional Control, LED Arrowstick
ꞏ Wireless, Waterproof, Rechargeable, Handheld, LED Spot Light w/12V Charger
ꞏ Worklights (2), LED, Boom
ꞏ Worklights (2), LED, Rear Door
ꞏ Work Light, LED, Operators Station
ꞏ Work Light, LED, Hose Reel Manhole
ꞏ Work Light, LED, Curb Side
ꞏ Work Light, LED, Street Side
ꞏ 14 Light Package – 14 Federal Signal Strobe Lights - LED
ꞏ Toolbox, Behind Cab
ꞏ Camera System, Front and Rear
ꞏ Safety Cone Storage Rack - Post Style
ꞏ Water Cooler Storage Rack
ꞏ (1) 7" Adjustable Air Adapter
ꞏ 1" x 25' Leader Hose Assembly
ꞏ (1) Offset Manhole Roller
ꞏ Chassis, Single Axle, 2025 International HV607 SBA, 370 HP, Auto, 46,000 GVWR, GHG
Product Model: 2100i
Module Paint Match Cab - Yes
Module Paint Color - Gray
Cab Color – Gray
Door Stripe Color - None
Chassis Axle - Single
Certified Unit Weight Required - No
Total HGAC Cooperative Purchasing Contract Price F.O.B. Colleyville, TX: $514,214.00
Quote Number: 2023-70307
Proposal Date: 1/11/2024
Quote Number: 2023-70307
Price List Date: 11/17/2023
Payment Terms: Net Due Upon Delivery
Proposal Notes:
1.Price valid until 2.11.24.
2.Prices quoted herein are in accordance with HGAC Contract # SC01-21.
3.Under Texas Motor Vehicle laws, this vehicle must be sold via a Texas franchise motor vehicle dealer. Therefore, any Purchase
Order issued in conjunction with this quote must be in the name of Kyrish Truck Center of Houston, HGAC Contract # HT06-
20.
SIGNED BY:
_____________________________________________________ Date: ________________________
Quote Number:2023-70307
LIMITED WARRANTY
Limited Warranty. Each machine manufactured by VACTOR MANUFACTURING (or, "the Company") is warranted against defects in
material and workmanship for a period of 12 months, provided the machine is used in a normal and reasonable manner and in accordance
with all operating, maintenance and safety instructions. In addition, certain machines and components of certain machines have extended
warranties as set forth below. If sold to an end user, the applicable warranty period commences from the date of delivery to the end user. If
used for rental purposes, the applicable warranty period commences from the date the machine is first made available for rental by the
Company or its representative. This limited warranty may be enforced by any subsequent transferee during the warranty period. This
limited warranty is the sole and exclusive warranty given by the Company.
STANDARD EXTENDED WARRANTIES (Total Warranty Duration)
2100 Series, HXX Series and Jetters 10 years against water tank leakage due to corrosion. Nonmetallic water tanks
are covered for 5 yrs. against any factory defect in material or workmanship.
2100 Series, HXX Series and Guzzler only 5 years against leakage of debris tank, centrifugal compressor or housing due to
rust-through.
2100 Series and Jetters 2 years - Vactor Rodder Pump
Exclusive Remedy. Should any warranted product fail during the warranty period, the Company will cause to be repaired or replaced, as
the Company may elect, any part or parts of such machine that the Company's examination discloses to be defective in material or factory
workmanship. Repairs or replacements are to be made at the selling Company's authorized dealer's or distributor's location or at other
locations approved by the Company. In lieu of repair or replacement, the Company may elect, at its sole discretion, to refund the purchase
price of any product deemed defective. The foregoing remedies shall be the sole and exclusive remedies of any party making a valid
warranty claim.
This Limited Warranty shall not apply to (and the Company shall not be responsible for):
1.Major components or trade accessories that have a separate warranty from their original manufacturer, such as, but not limited to, trucks
and truck chassis, engines, hydraulic pumps and motors, tires and batteries.
2.Normal adjustments and maintenance services.
3. Normal wear parts such as, but not limited to, oils, fluids, vacuum hose, light bulbs, fuses and gaskets.
4. Failures resulting from the machine being operated in a manner or for a purpose not recommended or not in accordance with operating,
maintenance or safety instructions provided by the Company.
5.Repairs, modifications or alterations without the express written consent of the Company, which in the Company's sole judgment, have
adversely affected the machine's stability, operation or reliability as originally designed and manufactured.
6. Items subject to misuse, negligence, accident or improper maintenance.
*NOTE* The use in the product of any part other than parts approved by the Company may invalidate this warranty. The Company
reserves the right to determine, in its sole discretion, if the use of non-approved parts operates to invalidate the warranty. Nothing
contained in this warranty shall make the Company liable for loss, injury, or damage of any kind to any person or entity resulting from any
defect or failure in the machine.
THIS WARRANTY SHALL BE IN LIEU OF ALL OTHER WARRANTIES, EXPRESS OR IMPLIED, AND TO THE EXTENT
PERMITTED, CONFERRED BY STATUTE, INCLUDING WITHOUT LIMITATION, ANY IMPLIED WARRANTIES OF
MERCHANTABILITY, OR FITNESS FOR A PARTICULAR PURPOSE, OR ANY WARRANTY AGAINST FAILURE OF ITS
ESSTENTIAL PURPOSE, ALL OF WHICH ARE DISCLAIMED.
This warranty is in lieu of all other obligations or liabilities, contractual and otherwise, on the part of the Company. For the avoidance of
doubt, the Company shall not be liable for any indirect, special, incidental or consequential damages, including, but not limited to, loss of
use or lost profits. The Company makes no representation that the machine has the capacity to perform any functions other than as
contained in the Company's written literature, catalogs or specifications accompanying delivery of the machine. No person or affiliated
company representative is authorized to alter the terms of this warranty, to give any other warranties or to assume any other liability on
behalf of the Company in connection with the sale, servicing or repair of any machine manufactured by the Company. Any legal action
based hereon must be commenced within eighteen (18) months of the event or facts giving rise to such action.
The Company reserves the right to make design changes or improvements in its products without imposing any obligation upon itself to
change or improve previously manufactured products.
VACTOR MANUFACTURING
1621 S. Illinois Street
Streator, IL 61364
Contract
No.:HT06-20 Date
Prepared:1/5/2024
Buying
Agency:Contractor:
Contact
Person:
Prepared
By:
Phone:Phone:
Fax:Fax:
Email:Email:
Product
Code:F10 Description:
74420
Cost Cost
2060 6476
2526 3473
791
497
432
1159 404830
2128
483
12848
586
Subtotal B: 438289
Cost Cost
5
Subtotal C: 5
0%
1 512714 =Subtotal D: 512714
Subtotal E: 1500
Cost Cost
Subtotal F: 0
514214
Check: Total cost of Unpublished Options (C) cannot exceed 25% of the total of the Base Unit
Price plus Published Options (A+B).
Description Description
F.Trade-Ins / Special Discounts / Other Allowances / Freight / Installation / Miscellaneous Charges
X Subtotal of A + B + C:
jescamilla@colleyville.com
SANTEX TRUCK CENTERS, LTD
CARLOS WEEBER
713-674-3444
G. Total Purchase Price (D+E+F):Delivery Date:
Subtotal From Additional Sheet(s):
Quantity Ordered:
Subtotal From Additional Sheet(s):
CONTRACT PRICING WORKSHEET
For MOTOR VEHICLES Only
2025 HV607 4x2 WITH VACTOR 2100i BODY
A.Product Item Base Unit Price Per Contractor's H-GAC Contract:
This Worksheet is prepared by Contractor and given to End User. If a PO is issued, both documents
MUST be faxed to H-GAC @ 713-993-4548. Therefore please type or print legibly.
CITY OF COLLEYVILLE
JON ESCAMILLA
817-503-1360
Description
01GBP FRAME REINFORCEMENT OUTER C 120K PSI 13BCS TRANS ALLISON AUTO 3000 RDS
05PTB STEERING GEAR (2) {Sheppard M100/M80 KINLOCH VACTOR 2100i QUOTE
02ARY AXLE FRONT MERITOR 20K WIDE TRACK
B.Published Options - Itemize below - Attach additional sheet(s) if necessary - Include Option Code in description if applicable.
(Note: Published Options are options which were submitted and priced in Contractor's bid.)
cweeber@kyrishtrucks.com
E.H-GAC Order Processing Charge (Amount Per Current Policy)
D.Total Cost Before Any Applicable Trade-In / Other Allowances / Discounts (A+B+C)
Description
For this transaction the percentage is:
08RPS RADIO AM/FM/WB/ BLUETOOTH
Description Description
C.Unpublished Options - Itemize below / attach additional sheet(s) if necessary.
(Note: Unpublished options are items which were not submitted and priced in Contractor's bid.)
12WUN ENGINE WATER COOLER AUX
012EZA ENGINE, CUMMINS L9 370 HP
03AGA SUSPENSION FRONT SPRING 20K W/SHOCKS
14AHL AXLE, REAR SGLE 26K LOCKING DIFFERENTIAL
04VGN AIR TANK PAINTED ALUM
04EBD AIR DRYER WABCO HEATED
07BLW EXH SYST HORIZ WITH VERTICAL TAIL PIPE
UNPUBLISHED OPTIONS
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number 4f Agenda Date 1/16/2024 Number Resolution R-24-4907
Type Resolution
Department City Manager
Title
Approval of the Second Amended Regional Municipal Court Judge Agreement
Explanation
Reading and Public Hearing
On December 1, 2021, the cities of Colleyville and Keller executed a Regional Municipal
Court Judge Agreement appointing Judge Carol Montgomery to serve as the presiding
judge for the Regional Municipal Court. On December 21, 2021, a First Amended
Regional Municipal Court Judge Agreement was approved by both cities, to provide for
restating the original agreement to provide for Judge Montgomery's status as a part-
time employee of the City of Colleyville and authorizing the Judge's participation in the
Texas Municipal Retirement System.
The cities of Keller and Colleyville met to review the performance of Judge Carol
Montgomery. Both cities agreed they wish to continue with Judge Montgomery, and
reviewed the attached Second Amended Regional Municipal Court Judge Agreement
which provides for Judge Montgomery to continue to serve the cities, provides for a
salary increase, an annual performance review, and a three-year term.
It is anticipated the City of Keller will approve the Second Amended Regional Municipal
Court Judge Agreement at their January 16, 2024, City Council Meeting.
Financial Impact
Funding for the Second Amended Regional Municipal Court Judge Agreement is provided
for in the FY24 budget.
Recommendation
Approve
Attachments
1.Second Amended Regional Municipal Court Judge Agreement
PAGE 1 CITY OF COLLEYVILLE/CITY OF KELLER
SECOND AMENDED REGIONAL MUNICIPAL COURT JUDGE AGREEMENT
SECOND AMENDED
REGIONAL MUNICIPAL COURT JUDGE AGREEMENT
This second amended Regional Municipal Court Judge Agreement (“Agreement”) is made by
and between the City of Colleyville (“Colleyville”), the City of Keller (“Keller”), and Carol
Montgomery (“Judge”), (each a “Party” and collectively the “Parties”), acting by and through their
authorized representatives.
RECITALS:
WHEREAS, Colleyville and Keller (each a “City” and collectively the “Cities”) jointly
administer and operate a regional municipal court; and
WHEREAS, on December 1, 2021 the Cities executed a Regional Municipal Court Judge
Agreement appointing Judge Carol Montgomery to serve as the presiding judge for the regional
municipal court; and
WHEREAS, the Parties desire to enter into this Agreement amending and restating the original
agreement to provide for Judge’s status as a part-time employee of the City of Colleyville and to
authorize Judge’s participation in the Texas Municipal Retirement System (TMRS) program.
NOW, THEREFORE, in consideration of the mutual covenants and terms and conditions
herein contained, and of the execution hereof, the Parties agree and bind themselves to the
obligations, and performance of the tasks as follows:
Article I
Purpose
The purpose of this Agreement is for the City to contract for municipal court judge services to
be performed in accordance with the terms and conditions of this Agreement.
Article II Term
This Agreement shall be effective as of January 1, 2024 (the “Effective Date”) and shall expire
December 31, 2026. Notwithstanding the foregoing, the term of this Agreement may be extended by
mutual written agreement of the Parties.
Article III
Regional Municipal Court Judge
3.1 Authority; Services. Judge shall have all authority vested under law and shall
undertake Judge’s duties fairly, impartially and independently. Judge shall, in a timely and
responsive manner, perform all services set forth herein and as required of municipal court judges in
accordance with Cities’ respective Charters, the Cities’ interlocal agreement for combined
municipal court services, the adopted policies and procedures of the regional municipal court, and the
laws applicable to municipal judges of courts in the State of Texas, as the foregoing may be amended
(“Services”). The Services shall include, without limitation, the following:
(a)Preside over all municipal court proceedings;
PAGE 2 CITY OF COLLEYVILLE/CITY OF KELLER
SECOND AMENDED REGIONAL MUNICIPAL COURT JUDGE AGREEMENT
(b)Promptly handle all adult and juvenile arraignments (see Section 3.2 below);
(c)Execute all arrest warrants;
(d)Execute all court warrants;
(e)Coordinate court activities with the municipal court administrator, prosecutor(s), city
attorney(s), and other departments of the Cities as necessary;
(f)Perform such other duties as assigned by the respective City Councils and/or the City
Managers that may be commensurate with the position of Regional Municipal Court
Judge; and
(g)Perform all other administrative duties of a municipal court judge as may be provided by
ordinance, resolution of the City Council, or applicable state law.
3.2 Arraignments; Magistrate Duties. Judge shall be responsible for all duties customarily
performed by magistrates of municipal courts of record in Texas. In particular, Judge shall be
responsible for all arraignments and magistrate duties for the regional holding facility (jointly
administered by Keller, Colleyville and Southlake), subject to the terms and conditions of all existing
MOUs and other agreements of the cities related to the same. Judge (or duly assigned associate
judge(s)) shall, at all times during the term of this Agreement, be available on a 24/7 basis to handle
all warrants, bonds, emergency orders, prisoner transfers requests, and similar matters.
Compensation for these duties flow through the stipend received from Southlake in the amount of
$12,000 per year and Roanoke in the amount of $7,300 per year, to be paid to the Judge quarterly.
3.3 Scheduling of Dockets. Judge shall be responsible for scheduling all court dockets and
proceedings in coordination with the municipal court administrator to facilitate optimal court efficiency
in support of the Cities’ customer service goals and values.
3.4 Review and Selection Committee. The Cities have established a Municipal Judge
Review and Selection Committee (the “Committee”) to assist in administering the position of the
regional municipal court judge. The Committee may meet from time to time to discuss, review and/or
modify the administration of the regional municipal judge position, including the periodic review the
Judge’s performance under this Agreement. On an annual basis, a performance evaluation of judge
shall be undertaken by the Cities (through their respective City Managers, or designee(s)) and
presented to the Committee. Upon request by the Committee and/or Cities, Judge agrees to collaborate
with the Committee to ensure the municipal court’s operations, policies and orders are being
effectively administered consistent with the operational goals and values of the Cities. The members
of the Committee shall be made known to Judge Montgomery along with a copy of any performance
evaluation.
3.5 Associate Judge(s). Judge shall, upon prior written approval of the Cities, engage the
services of one or more associate judges during the term hereof, subject to all terms and conditions
established by the Cities, in the Cities’ sole discretion. Judge shall exercise direct supervision over
all associate judges and be responsible for assigning such associate judges to act in Judge’s absence
in accordance with Section 30.00007(a)(4) of the Texas Government Code. Judge shall be responsible
for all compensation due to all associate judges under this Agreement and shall ensure that the
position of associate judge does not go vacant for more than 60 consecutive days during the term
of this Agreement.
3.6 Qualifications; Trainings. Judge must be an attorney licensed by the Texas Supreme
Court and must remain in good standing with the State Bar of Texas at all times during the term of
PAGE 3 CITY OF COLLEYVILLE/CITY OF KELLER
SECOND AMENDED REGIONAL MUNICIPAL COURT JUDGE AGREEMENT
this Agreement. Judge shall further adhere to the Texas Code of Judicial Conduct and all other
constitutional and statutory requirements of Judge’s appointed office. The Cities acknowledge that
Judge may be required to participate in training programs during the term of this Agreement and
agree that the City of Southlake, as Judge’s current employer, may seek equitable contribution in the
form of reimbursement from the Cities for the proportionate costs of such trainings attributable to the
Judge’s Services under this Agreement. If at any time the Judge no longer is employed by the City of
Southlake, all expenses for judicial education shall be paid by Colleyville.
Article IV
Compensation
4.1 Compensation. Judge shall be compensated for the Services based upon a flat annual rate
of $150,000, payable in installments at the same time as other employees of the City are paid and subject
to the same applicable deductions during the term of this Agreement. Should this Agreement terminate
prior to the last day of the month, the Judge’s compensation will be prorated on a daily basis for any
partial month. Additionally, the Cities will provide Judge, during the term of this Agreement, (i) use of
2 iPads (to be purchased and owned by Colleyville) at least one device will be a cellular streaming
device, (ii) a one-time reimbursement up to $250.00 for judicial robe(s), (iii) a mobile
telecommunications device stipend in the amount of $100.00 per month, and (iv) beginning on January
1, 2022, the Cities shall contribute to the Judge’s participation in Texas Municipal Retirement System
(TMRS), which shall be administered by the Cities in such manner as may be agreed by the Parties.
Judge shall not be entitled to any other compensation of the Cities under this Agreement unless otherwise
agreed by the Parties in writing.
4.2 Part-Time Employee Status. The Parties intend and agree that Judge shall be a part-time
employee of the City of Colleyville during the term of this Agreement. Notwithstanding Judge’s status as
a part-time employee, the provisions of this Agreement shall govern the employee benefits available to
Judge from the Cities and said benefits shall be limited to those expressly stated in this Agreement, unless
otherwise agreed in writing by the applicable Parties.
Article V
Termination
5.1 Termination for Convenience. Any Party may terminate this Agreement, in whole or in
part, at any time by providing sixty (60) days written notice. Judge shall be compensated for all Services
up to the time of termination. If Judge has any property or documents in its possession belonging to the
Cities, Judge will account for and dispose of the same in the manner requested.
5.2 Termination for Default [Breach or Cause]. If Judge fails to perform in the manner called
for in this Agreement, or if Judge fails to comply with any other provisions of this Agreement,
the Cities may terminate this Agreement for default. Termination shall be given by serving a notice
of termination on Judge setting forth the default and stating the date of termination. Upon termination
under this Section 5.2, Judge shall be compensated only for Services performed in accordance with this
Agreement through the date of termination.
5.3 Removal of Judge. Notwithstanding any other provisions of this Agreement, the
Parties acknowledge that Judge may be removed from office only as provided by law. The removal
of Judge by either City, regardless of reason, shall be mutually effective to terminate this Agreement.
PAGE 4 CITY OF COLLEYVILLE/CITY OF KELLER
SECOND AMENDED REGIONAL MUNICIPAL COURT JUDGE AGREEMENT
5.4 Waiver of Remedies for Any Breach. In the event that City elects to waive its
remedies for any breach or default by Judge of any covenant, term or condition of this Agreement, such
waiver by City shall not limit City's remedies for any succeeding breach or default of this Agreement.
Article VI
Miscellaneous
6.1 [Intentionally Deleted]
6.2 Assignment of Agreement. Judge may not assign this Agreement, or assign or
delegate any right or duty under this Agreement, without prior written approval from the Cities.
6.3 Notice. Any notice required or permitted to be given under this Agreement by one Party
to the other Party shall be in writing and shall be given and deemed to have been given immediately
if delivered in person to the recipient's address set forth in this section, or on the date shown on the
certificate of receipt if placed in the United States mail, postage prepaid, by registered or certified mail
with return receipt requested, addressed to the receiving Party at the address hereinafter specified:
For Colleyville:
City of Colleyville
Attn: Jerry Ducay, City Manager
100 Main Street, 3rd Floor
Colleyville, Texas 76034
E: jducay@colleyville.com
For Keller:
City of Keller
Attn: Mark Hafner, City Manager
P.O. Box 770
Keller, Texas 76244
E: mhafner@cityofkeller.com
For Judge:
Carol Montgomery
6.4 Conflict of Interest. Judge covenants that it presently has no interest and shall not
acquire any interest, direct or indirect, which would conflict in any manner or degree with the
performance of Services required to be performed under this Agreement. If any such conflict of
interest shall arise during the Agreement Term, Judge shall immediately and fully disclose the nature
and extent of the conflict to the respective party and resolve the conflict to party’s satisfaction.
6.5 Signatories. Having agreed to the terms herein, the undersigned signatories hereby
represent and warrant that they have authority to enter into this Agreement.
6.6 Applicable Law and Venue. The laws of the State of Texas shall govern this
Agreement; and venue for any action concerning this Agreement shall be in the state district court of
Tarrant County, Texas. The Parties agree to submit to the personal and subject matter jurisdiction
of said court.
PAGE 5 CITY OF COLLEYVILLE/CITY OF KELLER
SECOND AMENDED REGIONAL MUNICIPAL COURT JUDGE AGREEMENT
6.7 Amendments. This Agreement may be amended only upon written Agreement signed
by the Parties.
6.8 Severability/Interpretation. In the event any one or more of the provisions contained in
this Agreement shall for any reason be held to be invalid, illegal, or unenforceable in any respect, such
invalidity, illegality or unenforceability shall not affect any other provisions, and the Agreement shall
be construed as if such invalid, illegal, or unenforceable provision had never been contained in it.
6.9 Compliance with Laws. Judge shall fully comply with all federal, state, and local laws,
rules, regulations, and ordinances applicable to the services covered hereunder as they may now read
or may hereafter be amended.
[REMAINDER OF PAGE INTENTIONALLY LEFT BLANK -
SIGNATURE PAGE FOLLOWS]
PAGE 6 CITY OF COLLEYVILLE/CITY OF KELLER
SECOND AMENDED REGIONAL MUNICIPAL COURT JUDGE AGREEMENT
IN WITNESS WHEREOF, the parties have executed and delivered this Agreement as of the Effective
Date.
CITY OF COLLEYVILLE REGIONAL MUNICIPAL COURT JUDGE
By: By:
Mayor Bobby Lindamood Carol Montgomery
Date signed: Date signed: __________________________
CITY OF KELLER
By:
Mayor Armin Mizani
Date signed:
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number Agenda Date 1/16/2024
Type Report
Department Finance
Title
Monthly Financial Report - December 2023
Explanation
Staff will present the December 2023 financial report.
Attachments
1.December 2023 Presentation
2.December 2023 Monthly Financial Report
Monthly Financial Report
December 2023
City Council Meeting
December 16, 2024
Agenda Item -Items not for council action
General Fund
% of year Completed 25%
% of Budget Spent 26%
FY24 Budget FY24 YTD % of
Budget FY23 YTD
FY23% of
Budget
Revenues $ 28,554,942 $ 8,536,793 30%$ 8,978,530 34%
Expenditures $ 27,263,762 $ 7,115,509 26%$ 6,087,715 24%
$ 1,291,180 $ 1,421,284 $ 2,890,815
Utility Fund
% of year Completed 25%
% of Budget Spent 14%
FY24 Budget FY24 YTD % of
Budget FY23 YTD
FY23% of
Budget
Revenues $ 24,552,616 $ 5,264,552 21%$ 4,784,867 25%
Expenditures $ 24,552,616 $ 3,474,747 14%$ 3,341,597 17%
$ -$ 1,789,805 $ 1,443,270
TRA Summary City Summary
FY24 Budget FY24 YTD FY24 Budget FY24 YTD
Revs $ 20,339,768 $ 4,096,601 Revs $ 4,212,848 $ 1,167,951
Exps $ 19,889,768 $ 1,929,374 Exps $ 4,212,848 $ 1,545,373
Net $ 450,000 $ 2,167,227 Net $ -$ (377,423)
Drainage Fund
% of year Completed 25%
% of Budget Spent 28%
FY24 Budget FY24 YTD % of Budget FY23 YTD
FY23% of
Budget
Revenues $ 1,482,143 $ 370,961 25%$ 261,280 25%
Expenditures $ 738,386 $ 203,564 28%$ 165,635 23%
$ 743,757 $ 167,397 $ 95,646
Hotel Fund
% of year Completed 25%
% of Budget Spent 22%
FY24 Budget FY24 YTD % of
Budget FY23 YTD FY23% of
Budget
Revenues $ 202,000 $ -0%$ 891 0%
Expenditures*$ 188,532 $ 42,239 22%$ 73,948 27%
$ 13,468 $ (42,239)$ (73,057)
Debt Service Fund
% of year Completed 25%
% of Budget Spent 14%
FY24 Budget FY24 YTD % of
Budget FY23 YTD FY23% of
Budget
Revenues $ 1,238,871 $ 248,606 20%$ 292,278 48%
Expenditures*$ 1,235,460 $ 169,235 14%$ 168,485 22%
$ 3,411 $ 79,372 $ 123,793
25%
26%
FY24 Budget FY24 YTD
% of
Budget FY23 YTD
FY23% of
Budget
Revenues 28,554,942$ 8,536,793$ 30% 8,978,530$ 34%
Expenditures 27,263,762$ 7,115,509$ 26% 6,087,715$ 24%
1,291,180$ 1,421,284$ 2,890,815$
Revenue Highlight: Property Tax
Colleyville anticipates receiving $17.1M in General Fund property tax revenue in FY24. This represents
an approximately 7% increase from FY23. All of the increase in property tax was added on the M&O
side; however, the new debt for the Recreation Center will be paid for out of M&O property taxes
through a transfer to the Debt Service Fund. The City receives the majority of this revenue December
through February.
Monthly Financial Report - December 2023
% of year Completed
% of Budget SpentGeneral Fund
Through December, the General Fund has collected 30% of budget revenues and spent 26% of
budgeted expenditures. Both revenues and expenditures are in line with where we would expect to be
three months into the fiscal year. The largest General Fund revenue source is property taxes, which
comprises 60% of revenues, and the City receives the majority of this revenue December through
February. Thus, the revenue side of the General Fund will jump in the next several months.
Expenditures are up compared to last fiscal year, which is expected with normal cost of service
increases.
$6,515,659 $7,580,971
$10,606,975 $8,032,170
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
FY24 FY23
Collected to Date Collected Later
1
Revenue Highlight: Sales Tax
Sales tax is collected two months in arrears. The December 2023 report includes sales tax for the
first month of FY24 (purchases in October 2023). Total collections were down 4.95% from the
same month last year. The collection did include an audit adjustment of $27,630. When accounting
for the audit, the percentage improves to down 1.3%. It is important to note that sales tax for
purchases made in October jumped 19.52% from 2021 to 2022, followed by another increase of
1.3% last year. This could be an indicator of sales tax reaching a leveling point going forward. We
will continue to monitor.
Monthly Financial Report - December 2023
$‐
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
Sales Tax Month‐over‐Month
2020 2021 2022 2023 2024
$7,584,354
$8,248,648
$9,445,150
$10,286,767 $10,494,933
$‐
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
2019 2020 2021 2022 2023
Total Sales Tax
2
25%
14%
FY24 Budget FY24 YTD
% of
Budget FY23 YTD
FY23% of
Budget
Revenues 24,552,616$ 5,264,552$ 21% 4,784,867$ 25%
Expenditures 24,552,616$ 3,474,747$ 14% 3,341,597$ 17%
-$ 1,789,805$ 1,443,270$
Breakout of City's revenues/expenses from those related to the Trinity River Authority:
FY24 Budget FY24 YTD FY24 Budget FY24 YTD
Revs 20,339,768$ 4,096,601$ Revs 4,212,848$ 1,167,951$
Exps 19,889,768$ 1,929,374$ Exps 4,212,848$ 1,545,373$
Net 450,000$ 2,167,227$ Net -$(377,423)$
Through the second month of the fiscal year, the Utility Fund has collected 21% of its budgeted revenue
and spent 14% of its budgeted expenses. As the summary above shows, the majority of our surplus is
coming from our relationship with the Trinity River Authority. Just like in previous years, the City has
reached its revenue requirement for the Trinity River Authority as of September and is therefore being
under billed during the months of October and November. The Authority's fiscal year resets in December,
so we can expect invoices that reflect the full cost of water usage for the remainder of our fiscal year. The
City’s portion of the Utility Fund is right in line with the break-even nature of the utility.
*TRA Revenue/Expense Summary City Revenue/Expense Summary
Monthly Financial Report - December 2023
Water/Sewer Utility Fund % of Budget Spent
% of year Completed
3
25%
28%
FY24 Budget FY24 YTD % of Budget FY23 YTD
FY23% of
Budget
Revenues 1,482,143$ 370,961$ 25% 261,280$ 25%
Expenditures 738,386$ 203,564$ 28% 165,635$ 23%
743,757$ 167,397$ 95,646$
The Drainage Utility Fund has received 25% of its revenue and spent 28% of its expenditures. The fund
will collect more revenue than last year due to an increase in monthly drainage fee from $7 to $10. The
purpose of the drainage fee increase is to build funding to undertake capital projects from the new
Drainage Master Plan. That plan identifies $44M in needed improvements throughout the City.
Drainage Utility Fund
% of year Completed
Monthly Financial Report - December 2023
% of Budget Spent
4
25%
22%
FY24 Budget FY24 YTD
% of
Budget FY23 YTD FY23% of
Budget
Revenues 202,000$ -$ 0% 891$ 0%
Expenditures* 188,532$ 42,239$ 22% 73,948$ 27%
13,468$ (42,239)$ (73,057)$
The Hotel Tax Fund has not booked revenue yet for FY24. This fund collects revenue on a quarterly
basis, and the first revenue will be received in January. The City’s revenue from its one hotel has
been lower than expected for the previous two fiscal years, and so we moved some expenses from
this fund to other funds to account for lower revenue.
Monthly Financial Report - December 2023
% of year Completed
% of Budget SpentHotel Tax Fund
5
25%
14%
FY24 Budget FY24 YTD
% of
Budget FY23 YTD FY23% of
Budget
Revenues 1,238,871$ 248,606$ 20% 292,278$ 48%
Expenditures* 1,235,460$ 169,235$ 14% 168,485$ 22%
3,411$ 79,372$ 123,793$
For any questions or comments regarding this report, please contact:
Mark Wood
Assistance City Manager
City of Colleyville, TX
mwood@colleyville.com
817-503-1117
Being predominately funded through property taxes, the Debt Service fund has yet to receive a
substantial portion of its revenue this year. Cash-flow for this fund is very predictable, as most
revenues are recognized in December/January and debt service payments occur twice annually,
with lease payments also occurring throughout the year. This chart reflects property tax revenue
that will be transferred from the General Fund to pay the debt on the Recreation Center.
Monthly Financial Report - December 2023
% of year Completed
% of Budget SpentDebt Service Fund
6
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number 6a Agenda Date 1/16/2024 Number Resolution R-24-4908
Type Resolution
Department City Secretary
Title
Approval of a resolution calling a General Election for the purpose of electing City
Councilmembers to Place 5 and Place 6, and adding a Referendum Question to the
ballot to determine whether voters desire to place a proposition on a future election
ballot asking the City's voters to authorize issuance of ad valorem tax bonds for
expansion of the Colleyville Recreation Center, and authorizing a joint election
agreement and contract for election services for the General Election and the
Referendum Question with Tarrant County Elections Administration
Explanation
Reading and Public Hearing
This item provides for the election order calling a General Election for May 4, 2024, for
the purpose of electing City Councilmembers to Place 5 and Place 6 and a Referendum
Question to determine whether the voters desire to place a proposition on a future
election ballot asking the voters to authorize issuance of ad valorem tax bonds for
expansion of the Colleyville Recreation Center.
At the City Council Worksession on December 19, 2023, staff was directed to move
forward to place the Referendum Question, "Should the City of Colleyville place a
proposition on a future election ballot asking the City’s voters to authorize the issuance
of ad valorem tax bonds for expansion of the Colleyville Recreation Center, which may
include a fitness center, locker room, indoor track, and multi-use field?" on the May 4,
2024, ballot.
The City contracts with Tarrant County Elections Administration for election services,
which provides for citizens to vote at any early voting and election day location in
Tarrant County. The City and Tarrant County will begin utilizing the Colleyville
Recreation Center, Annex A, 5008 Roberts Road, for the conduct of all early voting and
election day voting, beginning with early voting in February for the March primaries.
The contract for the General Election and Referendum Question will not be received until
late March or early April.
The attached proposed resolution provides the dates, times, and locations for voting in
the General Election and Referendum Question and authorizes the joint election
agreement with Tarrant County Elections Administration.
City of Colleyville Page 2
City Council Agenda Briefing 6a
Financial ImpactFunds for the 2024 General Election and Referendum Question are allocated in the FY24
City Secretary's Office budget.
Recommendation
Approve
Attachments
1. Resolution R-24-4908
RESOLUTION R-24-4908
CALLING A GENERAL ELECTION FOR MAY 4, 2024, FOR THE
PURPOSE OF ELECTING CITY COUNCILMEMBERS
TO PLACE 5 AND PLACE 6 AND ADDING A REFERENDUM QUESTION
TO THE BALLOT TO DETERMINE WHETHER VOTERS DESIRE TO
PLACE A PROPOSITION ON A FUTURE ELECTION BALLOT ASKING
THE CITY’S VOTERS TO AUTHORIZE ISSUANCE OF AD VALOREM
TAX BONDS FOR EXPANSION OF THE COLLEYVILLE RECREATION
CENTER, WHICH MAY INCLUDE A FITNESS CENTER, LOCKER ROOM,
INDOOR TRACK, AND MULTI-USE FIELD; AUTHORIZING A JOINT
ELECTION AGREEMENT AND CONTRACT FOR ELECTION SERVICES
WITH TARRANT COUNTY ELECTIONS ADMINISTRATION; AND
PROVIDING AN EFFECTIVE DATE
WHEREAS, the City of Colleyville, Texas, desires to conduct a General
Election as set forth by the City of Colleyville Charter and
Texas Election Code, Section 41.001, to be held on Saturday,
May 4, 2024, at which time the voters will elect
Councilmembers to Place 5 and Place 6, and answer a
Referendum Question, including the conduct of early voting.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF COLLEYVILLE, TEXAS:
Sec. 1. THAT a General Election, including any necessary run-off
election(s), is hereby called to be held on May 4, 2024, to elect
City Councilmembers to Place 5 and Place 6, to serve until their
successors are duly elected and qualified, and to add a
Referendum Question, as set forth in Section 2 herein.
Sec. 2. THAT a Referendum Question is hereby added to the May 4,
2024 General Election ballot. The ballot for the Referendum
Question shall read as follows:
(__) Yes
(__) No
Should the City of Colleyville place a
proposition on a future election ballot asking
the City’s voters to authorize the issuance of
ad valorem tax bonds for expansion of the
Colleyville Recreation Center, which may
include a fitness center, locker room, indoor
track, and multi-use field?
Resolution R-24-4908
Page 2 of 3
Sec. 3. THAT the General Election and Referendum Question shall be
held at Colleyville Recreation Center, Annex A, 5008 Roberts
Road, Colleyville, Texas, on Saturday, May 4, 2024, from 7:00
a.m. to 7:00 p.m.
Sec. 4. THAT the Mayor, or his designee, is authorized to negotiate
and execute an agreement with the Tarrant County Elections
Administration to administer the elections (the “Election
Agreement”) in conformance with the Texas Elections Code
and City Charter.
Sec. 5. THAT qualified persons for City Council may file as candidates
by filing applications in the Office of the City Secretary, 100
Main Street, Colleyville, Texas, Wednesday, January 17, 2024
through Friday, February 16, 2024, Monday through Friday,
from 9:00 a.m. to 4:00 p.m.
Sec. 6. THAT Clint Ludwig, Elections Administrator, or his successor,
2700 Premier Street, Fort Worth, Texas 76111, is hereby
appointed as Early Voting Clerk and may appoint additional
deputy early voting clerks, as necessary, to properly conduct
the election. Applications for ballot by mail must be received
by mail no later than the close of business on Tuesday, April
23, 2024 (Mailing address: Tarrant County Elections, Early
Voting Clerk, or his successor, P.O. Box 961011, Fort Worth,
Texas, 76161-0011).
Sec. 7. THAT Early Voting shall be conducted at Tarrant County’s Main
Early Voting location at Tarrant County Elections Center, 2700
Premier Street, Fort Worth, Texas 76111, Colleyville
Recreation Center, Annex A, 5008 Roberts Road, Colleyville,
Texas 76034, and locations established and to be published by
the Tarrant County Elections Administration, and in
conformance with the Election Agreement.
Sec. 8. THAT this resolution shall take effect immediately upon
passage.
AND IT IS SO RESOLVED.
Resolution R-24-4908
Page 3 of 3
APPROVED BY A VOTE OF _ AYES, _ NAYS, ON THIS THE 16TH DAY OF
JANUARY 2024.
Mayor Bobby Lindamood Aye Mayor Pro Tem Callie Rigney Aye
Brandi Elder, Place 1 Aye George Bond, Place 2 Aye
Scotty Richardson, Place 3 Aye Ben Graves, Place 4 Aye
Chuck Kelley, Place 5 Aye
ATTEST: CITY OF COLLEYVILLE
Christine Loven, TRMC Bobby Lindamood
City Secretary Mayor
City of Colleyville Page 1
CITY OF COLLEYVILLE
CITY COUNCIL BRIEFING
Agenda Number 7a Agenda Date 1/16/2024 Number Resolution R-23-4883
Type Resolution
Department Community Development
Title
Consideration of a variance to lot size, lot coverage, and side yard setbacks for lot 27,
Community Home Addition, located at 1611 Cherry Lane, Case VC23-004 THE
APPLICANT HAS WITHDRAWN THE REQUEST
Explanation
Reading and Public Hearing
UPDATE: THE APPLICANT HAS WITHDRAWN THE REQUEST. This item was removed
from the table at the December 5, 2023 City Council meeting. The item was then tabled
to a date certain of January 16, 2023. However, the applicant has withdrawn the
request at this time due to outstanding issues with the drainage plan for the property.
Once those issues have been worked out, the applicant intends to resubmit.
This item was tabled from the October 17, 2023, November 8, 2023, November 21,
2023, and at the December 5, 2023, meetings. Per the Council's request, the applicant
ordered a drainage plan from a local engineering firm but what was provided is a
grading plan. A fully detailed drainage plan is still outstanding. Comments have been
provided to the engineering firm and staff is awaiting the revised plan. .
The applicant was present and answered questions from the City Council at the October
4, 2023, meeting. The Council discussed the need for a drainage study to understand
how the increased run-off will be handled with the existing drainage. The applicant
indicated they will have a drainage study for the next meeting. No one came forward to
speak during the public hearing.
Colin and Janice Travis, the applicants, have submitted a request for variances to the
provisions of Section 3.24.G, Schedule of District Regulations of the Land Development
Code, specifically for the lot size (area and width), lot coverage, and side yard setbacks
in the R-40 Single Family Residential district. The request is to allow for the lot area of
27,355 sq. ft., lot width of 105 ft., lot coverage of 29.1%, and 10 ft. side yards.
Existing Conditions/Background: The subject property, 1611 Cherry Lane, resides at
the end of Cherry Lane near the intersection with Rose Street and has R-40 zoning. The
existing lot area is 27,355 sq. ft., not the required 40,000 sq. ft. The lot width is 105 ft.,
not the required 150 ft. This is an existing platted lot, which is not developed.
Requested Variance: The applicant is requesting a variance to the lot size (area and
City of Colleyville Page 2
City Council Agenda Briefing 7a
width), lot coverage, and side yard setbacks to allow for a single-family home to be
constructed. The existing R-40 zoning requires a minimum of 40,000 sq. ft. for the lot
area, 150 ft. for lot width, 20% maximum lot coverage, and 15 ft. side yard setbacks
when developed with a single-family residential use. The variance would allow for the
existing lot area of 27,355 sq. ft. and lot width of 105 ft. along with a 29.1% lot
coverage and 10 ft. side yard setbacks.
Ordinance – Chapter 3 – Land Use – Section 3.24.G Schedule of District Regulations
The minimum standards for the R-40 zoning district are as follows:
Minimum Lot Size 40,000 square feet 27,355 s.f.
Minimum Lot Width 150 feet 105 ft.
Minimum Lot Depth 150 feet
Front Building Line 40 feet
Side Building Line 15 feet 10 ft.
Rear Building Line 25 feet
Max. Lot Coverage 20% 29.1%
Max. Impervious Coverage 50%
Plat Status: The property is currently platted as Lot 27, County Home Addition.
DRC Review: The Development Review Committee (DRC) reviewed the request at their
August 21, 2023 meeting, did not offer any comments, and scheduled the request for
the City Council meeting on October 4, 2023.
Drainage: There is approximately 21.2 offsite drainage from the north and west
currently being conveyed through this property. This development will be required to
convey this offsite drainage under fully developed conditions through this development
and into the existing wye inlet located south of this property.
Analysis: The subject property is requesting to have a variance to the lot size (area
and width), lot coverage and side yard setbacks. The property is zoned R-40 and the lot
size is not in compliance. When developed with a single-family residential use, the lot
shall comply with the R-40 zoning district standards. A variance to the lot size (area and
width), lot coverage and side yard setbacks would allow the ability to apply for and
receive the necessary building permit to build a new single-family home.
Surrounding Development: The properties to the north, south, and west are zoned R-
40 Single Family Residential district and are improved with single-family residential
homes. The properties to the east are zoned R-20 Single Family Residential district and
are improved with single-family residential homes.
Public Notification: Staff mailed notices to all property owners within 500 feet as well
as any Homeowners Associations within 1,000 feet of the subject property regarding
this request. Grapevine-Colleyville ISD, where the subject property is located, was
City of Colleyville Page 3
City Council Agenda Briefing 7a
notified per State law. Notice was published in the Fort Worth Star-Telegram as required
by State law and the Land Development Code.
Staff Recommendation: Staff is neutral on the requested variances.
Financial Impact
There is no financial impact to the City.
Recommendation
None
Attachments
1.Request to Withdraw
2.Aerial
3.Zoning
4.Future Land Use
5.Statement of Planning Objectives
6.Original Plat
7.Plat
8.Site Plan
9.Grading Plan Exhibit
10.Lot Size Exhibit
11.Elevation Exhibit
12.Proposed Pool Exhibit
13.Land Development Code Information
14.Notification Map
15.Notification List
16.Notification Letter
17.Letters Received
18.Resolution R-23-4883
1
Ben Bryner
Subject:RE: Conceptual Plans 1609 Cherry
From: Janice Travis < >
Sent: Tuesday, January 9, 2024 10:15 AM
To: Ben Bryner <BBryner@colleyville.com>
Subject: RE: Conceptual Plans 1609 Cherry
Hi Ben,
Yes, please withdraw unƟl the Engineer has Ɵme to complete a drainage plan that will saƟsfy the city.
Best Regards,
Janice Travis
G L A D E R D
AVONDALE DRJANETLN
BEHRENS RDBEHRENS CTCOVENTRYPLCHELSEA DRCHERRY LN
ARTHUR DR
A V A L O N DRCOVENTRY CTROSE STBLUEBONNET DRSubject Property
DISCLAIMER:
This map and information contained in it were
developed exclusively for use by the City of Colleyville.
Any use or reliance on this map by anyone else is
at that party's risk and without liability to the
City of Colleyville, its officials or employees for any
discrepancies, errors, or variances which may exist.
VC23-004
1611 Cherry Ln
Aerial Map
G L A D E R D
AVONDALE DRJANETLN
BEHRENS RDBEHRENS CTCOVENTRYPLCHELSEA DRCHERRY LN
ARTHUR DR
A V A L O N DRCOVENTRY CTROSE STBLUEBONNET DRAG
R-40
PUD-R
R-30
R-20
R-20
AG
R-40
R-20
Subject Property
DISCLAIMER:
This map and information contained in it were
developed exclusively for use by the City of Colleyville.
Any use or reliance on this map by anyone else is
at that party's risk and without liability to the
City of Colleyville, its officials or employees for any
discrepancies, errors, or variances which may exist.
VC23-004
1611 Cherry Ln
Zoning Map
G L A D E R D
AVONDALE DRJANETLN
BEHRENS RDBEHRENS CTCOVENTRYPLCHELSEA DRCHERRY LN
ARTHUR DR
A V A L O N DRCOVENTRY CTROSE STBLUEBONNET DRResidential
Institutional
Open Space; Parks
Subject Property
DISCLAIMER:
This map and information contained in it were
developed exclusively for use by the City of Colleyville.
Any use or reliance on this map by anyone else is
at that party's risk and without liability to the
City of Colleyville, its officials or employees for any
discrepancies, errors, or variances which may exist.
VC23-004
1611 Cherry Ln
Future Land Use Map
August 9, 2023
Re: 1611 Cherry Lane, Colleyville 76034
Lot 27 - Communiuty Home AddiƟon
We would like to request a variance for 1611 Cherry Lane, Colleyville.
The City of Colleyville has advised us that a re-zoning applicaƟon would not be approved, despite the
fact that this lot should be zoned R20 due to the size.
In 1952 this lot was plaƩed as it stands today. The size of the lot is approximately 27,355 sq Ō. In the
1970’s, Colleyville zoned the lot as R40, which requires a minimum lot size of 40,000 sq. Ō. For this
reason, we are requesƟng the following variances:
(1) the east side setback of 10 Ō, instead of the required 15 Ō.
(2) the west side setback of 10 Ō, instead of the required 15 Ō
(3) lot coverage of 29 % from 20% required for R40 size lot.
This property differs from other properƟes in the area due to the limited size of the lot.
Special condiƟons and circumstances exist which differ from other structures in the area and the same
district. This is a hardship as we are not allowed to build the house that we want, the lot coverage and
set backs are calculated on a lot that is 30 % larger than the lot in quesƟon, 1611 Cherry Lane.
Example:
R20 side yard setback 10 Ō.
R40 side yard setback 15 Ō.
R20 Maximum Lot coverage of 30% of 27,355 sq Ō = 8206 sq Ō of under roof which includes all garages,
paƟos, porch, outdoor kitchen.
R40 Maximum Lot coverage of 20% of 27,355 sq Ō= 5471 sq Ō of under roof which includes all garages,
paƟos, porch, outdoor kitchen.
We ask that you consider approving the variances.
Sincerely,
Colin and Janice Travis
BM#1
CP>>>>>>>>>>>>>>>>>>>>>
>
>
>>>>>>
WE NO.
DATE
007677-11075
11-20-2023
DRWN
CAS
SHEET NO.
REVISIONS
DATE#1609 CHERRY LANENEW RESIDENTIAL HOMECITY OF COLLEYVILLETARRANT COUNTY, TEXASTHIS DOCUMENT IS RELEASED FOR THE
PURPOSE OF REGULATORY REVIEW
AND PERMITTING. IT IS NOT TO BE USED
FOR BIDDING OR CONSTRUCTION
PURPOSES. THIS DOCUMENT WAS
PREPARED UNDER THE DIRECT
SUPERVISION OF:
NAME LICENSE NO.
CAMERON EHN, PE
11/20/2023
DATE
129176
PRELIMINARYJANICE TRAVIS1609 CHERRY LANECOLLEYVILLE, TX 76034214-204-6000jtravis@pci.worldWHITWORTHENGINEERINGDIAMOND JW INC5700 LIONFISH WAY - FORT WORTH, TX - 76131817-236-6106 - PLANS@RJWE.COM - F-3973CTE CTE
DSGN CHKDGRADING &DRAINAGEPLANDESCRIPTION
C1.00
PAGE 1 OF 1
0 20 40
N
FLOOD PLAIN NOTE:
GRADING NOTES:
TEXAS ONE CALL SYSTEM
BEFORE YOU DIG CALL:
1-800-245-4545
TEXAS 811
NOTE:
LEGEND:
GRADING ADJACENT TO STRUCTURE DETAILSWALE SECTION
Lot Size for surrounding area in R40 district
1. Lot 1 40,616
2. Lot 2 41,566
3. Lot 3 42,706
4. Lot 4 42,634
5. Lot 5 42,814
6. Lot 6 42,109
7. Lot 7 41,889
8. Lot 8 40,795
9. Lot 9 41,843
10. Lot 10 33,871
11. Lot 11 35,063
12. Lot 12 33,146
13. Lot 13 35,089
14. Lot 14 32,798
15. Lot 15 33,776
16. Lot 16 34,048
17. Lot 17 33,392
18. Lot 18 32,557
19. Lot 19 27,428
20. Lot 20 26,436
21. Lot 21 47,794
22. Lot 22 & 23 combined 57,978
23. Lot 24 42,000
24. Lot 25 33,032
25. Lot 26 27,566
26. Lot 27 27,355
Of 27 Lots in “Community Home AddiƟon” plaƩed in 1952, only 11 have the R-40 District Minimum
requirement of 40,000 sq. Ō. the other 16 are less than the minimum requirement.
1504
5019
1708
1416
5005
5012
5013
1704
1608
1709
4900
5117
5204
1604
5105
5305
5012
53055304
4905
5402
1717
1801
5004
4900
4904
1500
4901
1708
5208
5305
5201
1612
5101
4901
5105
1717
1504
5000
5212
1712
1721
5209
17165111
1500
5121
5009
5319
1709
1800
1600
5209
5113
5013
4901
5405
5401
5013
5213
1317
1508
1705 1713
5400
5100
5101
5009
1716
49101600
5108
1708
1708
1717
1716
5301
5317
5209
5016
5004
5017
4905
1405
1712
1512
4916
5009
5005
5301
5021
1701
5001
5109
5300
5209
5005
5104
5216
5025
5300
5117
5100
5208
1801
5304
1712
1717
5403
5011
5017
5016
5305
5301
1604
5125
1412
1800
5205
1716
5008
5213
1800
1713
1608
1609
1700
1612
1501
52055200
1704
1805
5201
15091505
1709
1800
1713
4900
1705
5008
5108
1801
1705
1704
5104
5200 5121
1704
5204
5205
5404
1611
G L A D E R D
AVONDALE DRJANETLN
BEHRENS RDBEHRENS CTCOVENTRYPLCHELSEA DRCHERRY LN
ARTHUR DR
A V A L O N DRCOVENTRY CTROSE STBLUEBONNET DRParcels to be notified
Buffer
Subject Property
DISCLAIMER:
This map and information contained in it were
developed exclusively for use by the City of Colleyville.
Any use or reliance on this map by anyone else is
at that party's risk and without liability to the
City of Colleyville, its officials or employees for any
discrepancies, errors, or variances which may exist.
VC23-004
1611 Cherry Ln
Notification Map
1
Notify_List
OBJECTID Owner Name Owner Address Owner City Owner Zip Situs Address
55 MONTCLAIR PARC ADDITION 1108 W. Pioneer Parkway ARLINGTON ,TX 76013 COURTESY NOTICE
33 STEWART, LARRY 1509 CHERRY LN COLLEYVILLE, TX 76034 5016 ROSE ST
27 WOODCOCK, DAVID 1512 CHERRY LN COLLEYVILLE, TX 76034 1512 CHERRY LN
17 DAMERON, RAY 1600 CHERRY LN COLLEYVILLE, TX 76034 1600 CHERRY LN
36 TRAVIS, COLIN 1609 CHERRY LN COLLEYVILLE, TX 76034 1609 CHERRY LN
4 ROGERS, NANCY 1612 CHERRY LN COLLEYVILLE, TX 76034 1608 CHERRY LN
37 DUCIC, YADRANKO 1700 GLADE RD COLLEYVILLE, TX 76034 1700 GLADE RD
49 PARKER, TIMOTHY 1704 ARTHUR DR COLLEYVILLE, TX 76034 1704 ARTHUR DR
3 DAVIS, RICHARD J 1704 AVALON DR COLLEYVILLE, TX 76034 1704 AVALON DR
39 DUNN, MARC P 1704 AVONDALE DR COLLEYVILLE, TX 76034 1704 AVONDALE DR
46 STANLEY, REBECCA S 1704 GLADE RD COLLEYVILLE, TX 76034 1704 GLADE RD
18 MILNER, WALTER J 1705 ARTHUR DR COLLEYVILLE, TX 76034 1705 ARTHUR DR
45 CASILIO JOELLEN TR 1705 AVALON DR COLLEYVILLE, TX 76034 1705 AVALON DR
42 LEPORI, WILLIS R 1705 AVONDALE DR COLLEYVILLE, TX 76034 1705 AVONDALE DR
23 SPENCER, DANIEL 1708 ARTHUR DR COLLEYVILLE, TX 76034 1708 ARTHUR DR
22 GILSTRAP, JEFF 1708 AVALON DR COLLEYVILLE, TX 76034 1708 AVALON DR
10 KLINE, ALAN 1708 AVONDALE DR COLLEYVILLE, TX 76034 1708 AVONDALE DR
5 BROWN, KATHARINE M 1709 ARTHUR DR COLLEYVILLE, TX 76034 1709 ARTHUR DR
16 CARR, DONNA M 1709 AVALON DR COLLEYVILLE, TX 76034 1709 AVALON DR
40 MARSHALL, M A 1709 AVONDALE DR COLLEYVILLE, TX 76034 1709 AVONDALE DR
26 WALKER, BRYAN 1712 AVALON DR COLLEYVILLE, TX 76034 1712 AVALON DR
41 STOWE, STEPHEN 1713 AVALON DR COLLEYVILLE, TX 76034 1713 AVALON DR
34 MARCH, JAMES H 1713 AVONDALE DR COLLEYVILLE, TX 76034 1713 AVONDALE DR
52 CHELSEA PARK ADDITION 1816 Avondale Drive COLLEYVILLE ,TX 76034 COURTESY NOTICE
11 FATCAT II LLC 2140 E SOUTHLAKE BLVD STE L-675 SOUTHLAKE, TX 76092 5208 COVENTRY CT
56 GRAPEVINE COLLEYVILLE ISD 3051 IRA E WOODS AVE GRAPEVINE, TX 76051 STATE REQUIRED
32 ABBOTT, LARRY 4700 JIM MITCHELL TR E COLLEYVILLE, TX 76034 1712 ARTHUR DR
13 OLENGUE, INNOCENT 5000 CHELSEA DR COLLEYVILLE, TX 76034 5000 CHELSEA DR
25 HOOKS, DURAN 5004 CHELSEA DR COLLEYVILLE, TX 76034 5004 CHELSEA DR
29 BACA, CHAD 5005 ROSE ST COLLEYVILLE, TX 76034 5005 ROSE ST
43 MANGHAM, WEBSTER M 5008 CHELSEA DR COLLEYVILLE, TX 76034 5008 CHELSEA DR
1 HARRINGTON, D NEAL 5012 CHELSEA DR COLLEYVILLE, TX 76034 5012 CHELSEA DR
9 WILLIAMS, LACI 5012 ROSE ST COLLEYVILLE, TX 76034 5012 ROSE ST
2 WINTERS, DAN L 5013 ROSE ST COLLEYVILLE, TX 76034 5013 ROSE ST
24 KING, MARY 5016 CHELSEA DR COLLEYVILLE, TX 76034 5016 CHELSEA DR
31 HICKEY, BRIAN DOUGLAS 5100 CHELSEA DR COLLEYVILLE, TX 76034 5100 CHELSEA DR
19 STEWART, CONNIE 5100 ROSE ST COLLEYVILLE, TX 76034 5100 ROSE ST
20 FORDYCE, MARK 5101 ROSE ST COLLEYVILLE, TX 76034 5101 ROSE ST
30 BURAL, EARL 5104 CHELSEA DR COLLEYVILLE, TX 76034 5104 CHELSEA DR
47 CLARK, HARRY P 5104 ROSE ST COLLEYVILLE, TX 76034 5104 ROSE ST
8 HERRON, DAVID 5105 ROSE ST COLLEYVILLE, TX 76034 5105 ROSE ST
21 MILLER, TRACY S 5108 CHELSEA DR COLLEYVILLE, TX 76034 5108 CHELSEA DR
44 COURON, SUSAN 5108 ROSE ST COLLEYVILLE, TX 76034 5108 ROSE ST
14 PERRY, STAN 5111 ROSE ST COLLEYVILLE, TX 76034 5111 ROSE ST
6 TEW, TERESA A 5117 COVENTRY PL COLLEYVILLE, TX 76034 5117 COVENTRY PL
28 DOSSANI, ANWAR A 520 E NORTHWEST HWY STE 100 GRAPEVINE, TX 76051 5209 BLUEBONNET DR
48 HARGROVE, BELINDA 5200 COVENTRY CT COLLEYVILLE, TX 76034 5200 COVENTRY CT
50 APTE, SHIREESH 5204 COVENTRY CT COLLEYVILLE, TX 76034 5204 COVENTRY CT
53 CRANBROOK ESTATES P.O. Box 372 COLLEYVILLE ,TX 76034 COURTESY NOTICE
54 KINGSWOOD ESTATES-COLLEYVILLE P.O. Box 978 COLLEYVILLE ,TX 76034 COURTESY NOTICE
15 STEWART, LARRY R PO BOX 1497 COLLEYVILLE, TX 76034 5009 ROSE ST
7 PHILLIPS, DEAN F PO BOX 210445 BEDFORD, TX 76095 1604 CHERRY LN
NOTICE OF PUBLIC HEARING
«Owner_Name»
«Owner_Address»
«Owner_City» «Owner_Zip»
The City of Colleyville has scheduled public hearings concerning the below referenced request on the
following dates and location:
City Council Meeting: Tuesday, September 19, at 7:00 p.m.
3rd floor of City Hall, 100 Main Street, Colleyville, Texas
Request: Consideration of a variance for the required lot size, lot coverage, and side
yard setbacks. The area and width of the lot do not comply with the
minimums standards for the R-40 district. The request will allow for the
construction of a new single family home.
Zoning Case: VC23-004 Applicant: Colin and Janice Travis Owner: Colin and Janice Travis Location: 1611 Cherry Lane Property Description: Lot 27, Community Home Addition Present Zoning: R-40, Single Family Residential This notice has been sent to all owners of real property within 500 feet of the request as such ownership appears on the last approved tax roll and all homeowners associations within 1000 feet. Approval by the Planning and Zoning Commission serves as a recommendation to the City Council and is not a final action on the request. Denial of the proposal by the Commission is final, unless the applicant submits a written notice of appeal within 10 days from the date of action by the Commission. If appealed, the request will be placed on the next available City Council agenda as listed above. Rezoning requests, zoning amendments and conditions recommended by the Commission for approval by the City Council may be more restrictive than those described in this notice.
All interested persons are encouraged to attend the public hearing and express their opinions on the zoning
change request. If you are unable to attend, but wish to have your opinions made a part of the public record,
please submit written comments prior to the public hearing, to the address below:
Community Development Department
City of Colleyville
100 Main Street
Colleyville, TX 76034
If the property owners of 20% or more of the land within the 200 foot notification area file a written protest
prior to the public hearing, State law provides that the approval of the zoning change request shall require
the approval of a super majority vote by City Council.
NOTICE OF PUBLIC HEARING
The application is on file for public examination in the Community Development Department at 100 Main
Street, Colleyville, Texas 76034. A brief project description can be found online on the Agenda Packet and
Active Development Case map (please use your phone’s camera to scan QR code below):
For additional information, please contact the Community Development Department at 817.503.1056.
Please reference the zoning case number when requesting information.
Jacquelyn Reyff
Principal Planner
jreyff@colleyville.com
From:Brian Hickey
To:Jackie Reyff
Subject:VC23-004
Date:Tuesday, September 26, 2023 1:32:29 PM
Ms. Reyff,
I am writing regarding the zoning case noted above.
I live directly east of and next to the subject lot. I have lived here over 18 years.
The Travis’s requested and received the same variance for their current lot, and the results were
fantastic.
The property they built is beautiful, and the setback deltas are not noticeable at all.
Based on the proposed renderings of the home to be built, I am sure it will be just as nice.
As such, I have no issue with their request for a variance and support their request.
Should you have any questions, please contact me at your convenience.
Regards,
Brian Hickey
5100 Chelsea Drive, Colleyville
RESOLUTION R-23-4883
A RESOLUTION APPROVING A REQUEST FOR A VARIANCE TO
SECTION 3.24.G, SCHEDULE OF DISTRICT REGULATIONS OF THE
LAND DEVELOPMENT CODE, SPECIFICALLY FOR LOT AREA, LOT
WIDTH, LOT COVERAGE, AND SIDE YARD SETBACKS, IN THE R-40
SINGLE FAMILY RESIDENTIAL DISTRICT, FOR LOT 27, COMMUNITY
HOME ADDITION, LOCATED AT 1611 CHERRY LANE
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF COLLEYVILLE, TEXAS:
Sec. 1. THAT the variance to allow for the lot area to be approximately
27,355 square feet, lot width to be 105 feet, lot coverage to
be 29.1%, and side yard setbacks of 10 feet with the R-40
Single Family Residential zoning district located at 1611 Cherry
Lane (the “Property”), as depicted in Exhibit “A” hereto, is
approved.
Sec. 2. THAT this Resolution shall become effective immediately upon
passage; provided that, the variance for the Property shall
become effective immediately upon the conditions stated
herein being fully satisfied.
AND IT IS SO RESOLVED.
PASSED BY A VOTE OF ___ AYES, ___ NAYS, ON THIS THE 5TH DAY OF
DECEMBER 2023.
Mayor Bobby Lindamood Aye Mayor Pro Tem Callie Rigney Aye
Brandi Elder, Place 1 Aye George Bond, Place 2 Aye
Scotty Richardson, Place 3 Aye Ben Graves, Place 4 Aye
Chuck Kelley, Place 5 Aye
ATTEST: CITY OF COLLEYVILLE
Christine Loven, TRMC Bobby Lindamood
City Secretary Mayor
Attachment “A”
Attachment “B”
City of Colleyville Page 1
CITY OF COLLEYVILLE
PLANNING AND ZONING
COMMISSION MINUTES
100 Main Street, Colleyville, Texas, 76034
MONDAY, DECEMBER 11, 2023
CALL MEETING TO ORDER
EXECUTIVE CONFERENCE ROOM
The City of Colleyville Planning and Zoning Commission Worksession Meeting was
called to order by Chair Bevill on December 11, 2023 at 6:15 p.m.
Roll Call
Present: David Groves, Tim Raine, Mark Alphonso, Sayeda Syed, Jerry Savoie,
Claudia Bevill, and Jerome Obinabo
Staff Present: Ben Bryner, Jacquelyn Reyff, Kris Potts and Chris Pham
Also Present: Attorney, Nicole Corr, Fire Marshall, Rob Mckeown, City Engineer,
Larry Wright
There was discussion amongst staff and the Commission regarding updated items
to be presented this evening at the regular meeting.
Chair Bevill adjourned the Planning and Zoning Commission Wor ksession Meeting
at 6:50 p.m.
CALL MEETING TO ORDER
CITY COUNCIL CHAMBERS
The City of Colleyville Planning and Zoning Commission Meeting was called to
order by Chair Bevill on December 11, 2023, at 7:08 p.m.
Roll Call
Present: David Groves, Tim Raine, Mark Alphonso, Sayeda Syed, Jerry Savoie,
Claudia Bevill, and Jerome Obinabo
Staff Present: Ben Bryner, Jacquelyn Reyff, Kris Potts and Chris Pham
Planning and Zoning Commission Minutes December 11, 2023
City of Colleyville Page 2
Also Present: Attorney, Nicole Corr, Fire Marshall, Rob Mckeown, City Engineer,
Larry Wright
1.ELECTION OF OFFICERS
1a Election of Officers, Chair and Vice-Chair
Commissioner Syed made a motion to elect Claudia Bevill as Commission
Chair. Commissioner Alphonso seconded the motion.
The motion was carried by the following vote:
Aye: 7 – Groves, Syed, Raine, Alphonso, Savoie, Bevill, and Obinabo
Nay: 0
Commissioner Syed made a motion to elect David Groves as Commission
Vice Chair. Commissioner Raine seconded the motion.
The motion was carried by the following vote:
Aye: 7 – Groves, Syed, Raine, Alphonso, Savoie, Bevill, and Obinabo
Nay: 0
2.APPROVAL OF MINUTES
2a Planning and Zoning Commission Meeting Minutes – November 13,
2023
Planning and Zoning Commission Worksession Minutes – November 27,
2023
Commissioner Groves made a motion to approve the November 13, 2023
Planning and Zoning Commission Meeting Minutes and the November 27,
2023 Planning and Zoning Commission Worksession Minutes.
Commissioner Alphonso seconded the motion.
The motion was carried by the following vote:
Aye: 7 – Groves, Syed, Raine, Alphonso, Savoie, Bevill, and Obinabo
Nay: 0
Planning and Zoning Commission Minutes December 11, 2023
City of Colleyville Page 3
3. PUBLIC HEARING AGENDA ITEMS
3a Tabled from the November 13th, 2023 Planning and Zoning
Commission Meeting - Consideration of a rezoning from AG Agricultural
to R-30 Single Family Residential and R-40 Single Family
Residential for Lots 1 and 2R1, Block 1, Davis Place Addition,
located at 6400 and 6316 Pleasant Run Road, Case ZC23-025
Commissioner Raine made a motion to remove Case ZC23-024 from the
table. Commissioner Groves seconded the motion.
The motion was carried by the following vote:
Aye: 7 – Groves, Alphonso, Syed, Raine, Savoie, Bevill, Obinabo
Nay: 0
Jacquelyn Reyff presented the case and briefed the commission.
Matthew Lee, 2901 Dallas Pkwy, Plano, TX presented his case for the proposed
subdivision. He addressed changes made from the previous design, including a
reduction of the number of lots from 8 to 7 lots, the addition of a detention pond,
the restructuring of the lots to have all lots be R-40 zoning, and answered
questions from the Commission regarding the proposed street frontage of the lots.
The public hearing was opened at 7:21 p.m.
The following citizens did not wish to speak but did wish to record their opposition:
Lisa Bain Grossman, 6014 Pleasant Run Rd
The following citizens spoke at the public hearing:
Todd and Lisa Pipes, 6117 Hunter Ln, spoke in opposition of the case, specifically
regarding drainage concerns.
Tom Panno, 6114 Hunter Ln, spoke in opposition of the case, specifically regarding
drainage concerns.
The applicant, Matthew Lee, came forward to address the drainage concerns and
the measures taken to improve the drainage to the South.
With no one else wishing to speak, the public hearing was closed at 7:26 p.m.
Planning and Zoning Commission Minutes December 11, 2023
City of Colleyville Page 4
The Commissioners discussed with the applicant whether drainage would improve
with the proposed development, concerns regarding lot frontage and traffic, the
ability to extend the cul-de-sac further into the development, and whether
neighbor discussions had been done.
Commissioner Groves made a motion to deny Case ZC23-025.
Commissioner Syed seconded the motion.
The motion was carried by the following vote:
Aye: 7 – Groves, Alphonso, Syed, Raine, Savoie, Bevill, and Obinabo
Nay: 0
3b Tabled from the November 13th, 2023 Planning and Zoning
Commission meeting - Consideration of a Special Use Permit for a
contractor office with storage yard on Tract 2K, Abstract 963,
Absalom J Lott Survey, located at 6516 Colleyville Boulevard, Case
ZC23-029
Case ZC23-029 was withdrawn by the applicant prior to the December
11th Planning and Zoning Commission Meeting.
3c Tabled from the November 13th Planning and Zoning Commission
meeting - Consideration of a Special Use Permit to allow a Heliport
on Lot AR, Block 7, of the Windview Addition, located at 2325
Oak Knoll Drive, Case ZC23-031
Case ZC23-031 was withdrawn by the applicant prior to the December
11th Planning and Zoning Commission Meeting.
3d Consideration of a Replat for Lot 3A and 3B, Block 4, Western Trails
Addition, being located at 512 Bandit Trail, Case PC23-011
Jacquelyn Reyff presented the case and briefed the Commission. Larry Wright
addressed the additional drainage requirements needed to approve the replat.
Jennifer Starr, 4311 Oak Lawn Ave Unit 550, Dallas, TX 75219, came forward and
requested to table to the January 8th Planning and Zoning Commission Meeting to
provide the required drainage documentation.
Planning and Zoning Commission Minutes December 11, 2023
City of Colleyville Page 5
The public hearing was opened at 7:41 p.m.
The following citizens did not wish to speak but did wish to record their opposition:
Wendy Kelso, 504 Bandit Tr
Jason Terando, 509 Sagebrush St
The following citizens spoke at the public hearing:
Tim Kelso, 504 Bandit Tr, spoke in opposition regarding drainage and lot coverage
concerns.
Mike Brown, 508 Bandit Tr, spoke in opposition, specifically regarding the
characteristic of the neighborhood, lot coverage, privacy, and misalignment with
the long-term comprehensive plan.
William Juroska, 517 Tumbleweed Tr, spoke in opposition, specifically regarding
the characteristic of the neighborhood, lot coverage, and tree preservation.
With no one wishing to speak, the public hearing was closed at 7:52 p.m.
The applicant, Jennifer Starr, came forward to address the neighborhood concerns
regarding the preservation of the neighborhood characteristics, and stated that the
house constructed would match the existing neighborhood.
Commissioner Alphonso made a motion to table Case PC23-011.
Commissioner Groves seconded the motion.
The motion was carried by the following vote:
Aye: 7 – Groves, Alphonso, Syed, Raine, Savoie, Bevill, and Obinabo
Nay: 0
3e Consideration of a Special Use Permit to allow a Heliport on Lot 1,
Block 1, of the Ben and Elizabeth Addition and Lot 1, 2, and 3,
Block 4, Stafford Heights Subdivision, located at 1407 through 1505
Oak Knoll Drive, Case ZC23-034
Case ZC23-034 was withdrawn by the applicant prior to the December
11th Planning and Zoning Commission Meeting.
Planning and Zoning Commission Minutes December 11, 2023
City of Colleyville Page 6
3f Consideration of a Special Use Permit to allow for a fence on Lot 1R-A,
Block 4, Fairway Addition, located at 1020 McDonwell School Road
West, Case ZC23-035
Jacquelyn Reyff presented the case and briefed the Commission.
Osama Nashed, 5000 Thompson Terr, presented his case for the proposed fence.
Commissioner Groves spoke regarding the hardship requirement of the fence,
stating that similar homes adjacent to schools lack fences along the perimeter.
Commissioner Syed spoke regarding fence, stating that the proximity to the school
is not a valid reason to approve a fence that encroaches in the front and side yard
setback for an R-20 lot.
The public hearing was opened at 8:07 p.m.
Lenonna Nichols, 1017 W Murphy Rd, spoke in support, specifically regarding child
safety concerns, prevalence of cars parking along Herbert Rd, and definition of lot
boundaries.
Mark Nuttall, 6606 Herbert Rd, spoke in opposition, specifically regarding the
fence’s aesthetic appeal, visibility concerns, and sidewalk & street crossing
concerns.
David Mashushire, 6604 Herbert Rd, spoke in support, specifically regarding the
security of the property, privacy, and aesthetic appeal.
Emmanuel Ikharebha, 6602 Herbert Rd, spoke in support, specifically regarding
the ability of the applicant to fix concerns raised by the Commission with staff.
Jill Powell, 6905 DaVinci, spoke in opposition, specifically regarding visibility
concerns along McDonwell School Rd from Herbert Rd.
The applicant, Osama Nashed, came forward and requested to table the case to
make changes raised by the Commission.
With no one wishing to speak, the public hearing was closed at 8:21 p.m.
Larry Wright discussed the city’s sidewalk connectivity plan, drainage concerns
related to the opacity of the fence, & required driveway widths on roads.
Planning and Zoning Commission Minutes December 11, 2023
City of Colleyville Page 7
The Commissioners discussed with the applicant whether the applicant could meet
a 30 ft. setback for the fence, rather than the requested perimeter fence.
Commissioner Savoie made a motion to table Case ZC23-035 to the
January 8th, 2024 Planning & Zoning Commission Meeting. Commissioner
Alphonso seconded the motion.
The motion was carried by the following vote:
Aye: 3 – Alphonso, Savoie, and Obinabo
Nay: 4 – Groves, Syed, Raine, and Bevill
Commissioner Groves made a motion to deny Case ZC23-035.
Commissioner Syed seconded the motion.
The motion was carried by the following vote:
Aye: 6 – Groves, Alphonso, Syed, Raine, Bevill, and Obinabo
Nay: 1 – Savoie
4.CITIZEN COMMENTS
The public forum opened at 8:34 p.m.
With no one else wishing to speak, the public forum closed at 8:34 p.m.
5.ADJOURNMENT
The meeting adjourned at 8:34 p.m.
The minutes were written and prepared by:
Christopher Pham
Christopher Pham
Planner
The meeting minutes were approved on January 8, 2024 by a vote of 6-0.
RESOLUTION R-24-4909
A RESOLUTION APPROVING CITY COUNCIL ACTION UNDER
BUSINESS AT THE REGULAR CITY COUNCIL MEETING OF
JANUARY 16, 2024
WHEREAS, City Council has taken action on certain items on the agenda
under Business.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF COLLEYVILLE, TEXAS:
Sec. 1. THAT
AND IT IS SO RESOLVED.
APPROVED BY A VOTE OF _ AYES, _ NAYS, ON THIS THE 16TH DAY OF
JANUARY 2024.
Mayor Bobby Lindamood Aye Mayor Pro Tem Callie Rigney Aye
Brandi Elder, Place 1 Aye George Bond, Place 2 Aye
Scotty Richardson, Place 3 Aye Ben Graves, Place 4 Aye
Chuck Kelley, Place 5 Aye
ATTEST: CITY OF COLLEYVILLE
Christine Loven, TRMC Bobby Lindamood
City Secretary Mayor