HomeMy WebLinkAboutCity Council Resolutions (Resolution R-21-4598)-03/23/2021RESOLUTION R-21-4598
A RESOLUTION OF THE CITY OF COLLEYVILLE, TEXAS
RECOMMENDING CERTAIN TRANSPORTATION PROJECTS FOR
CONSIDERATION AND INCLUSION IN THE TARRANT COUNTY 2021
BOND PACKAGE
WHEREAS, the City of Colleyville is a City in Tarrant County; and
WHEREAS, Tarrant County has initiated plans to propose a bond package
to voters in November 2021; and
WHEREAS, the cities within Tarrant County have been asked to submit
recommendations for transportation improvement projects
with cross -jurisdictional benefit, for potential inclusion in the
bond package; and
WHEREAS, the City of Colleyville has reviewed potential capital projects
and identified those projects listed in "Exhibit A" as worthy of
consideration.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF COLLEYVILLE, TEXAS:
Sec. 1. THAT the City Manager is authorized to submit this resolution
and list of recommended capital projects to Tarrant County.
AND IT IS SO RESOLVED.
APPROVED BY A VOTE OF 7 AYES, 0 NAYS, ON THIS THE 23RD DAY OF
MARCH 2O21.
Mayor Richard Newton Aye Mayor Pro Tern Bobby Lindamood Aye
Place 1, Tammy Nakamura Aye Place 3, Kathy Wheat Aye
Place 4, George Dodson Aye Place 5, Chuck Kelley Aye
Place 6, Callie Rigney Aye
ATTEST:
Christine Loven, TRMC
City Secretary
CI OF COLLEYVILLE
/�
l
Richard Newton
Mayor
Exhibit "A"
Tarrant County - November 2021 Bond Issue
City of Colleyville Project Recommendations
Project
Description
Preliminary Work
Funding
Cheek-Sparger Road
Design & Construction —
ROW acquired
Est. $26,000,000
& Trail
Arterial road reconstruction and
(Heritage Avenue to
enhancement (36 ft.; 2 lane
Colleyville: $6,500,000
Bedford Road)
design); Turn lanes added at key
Bedford: $6,500,000
intersections; Pedestrian trail
County: $13,000,000
reconstruction and
enhancement
City source: TIF
*Partner with Bedford
County source: A, B. or C
Roundabout at
Construction —
Design
Est. $1,400,000
Cheek- Spargerand
Intersection improvement via
engineering
Bedford Rd.
new roundabout
complete.
Colleyville: $700,000
No additional
Bedford: $0 (Support Only)
ROW required.
County: $700,000
City source: TIF
County Source: A or B
West Glade Road
Design & Construction —
Est. $10,000,000
(SH26 to Precinct Line
Arterial road reconstruction and
Rd)
enhancement (36 ft.; 2 lane
Colleyville:$2,500,000
design); Turn lanes at key
Hurst: $2,500,000
intersections
County: $5,000,000
*Partner with Hurst
City source: TIF
County source: A, B, or C
Tinker Road
Construction —
Design
Est. $2,000,000
(Pleasant Run to
Collector road reconstruction
engineering
SH26)
and enhancement; drainage
initiated.
Colleyville: $1,000,000
improvements
County: $1,000,000
City source: TIF, General and
Utility Capital Project Funds
County source: A
Roberts Road
Construction —
Design
Est. $2,700,000
(Glade Rd to Northern
Collector road reconstruction
engineering
City Limits)
and enhancement; Utility
complete.
Colleyville: $1,700,000
replacements
County: $1,000,000
City source: Capital Project
Funds; Utility Capital Funds
County source: A
Bedford Rd Low
Design Engineering —
Est. $400,000
Water Crossing
To raise road profile to eliminate
(at Little Bear Creek)
low water crossing
Colleyville: $100,000
County: $300,000
City source: Capital Proj. Fund
County source: A or B
Heritage Avenue
Design & Construction —
Est. $750,000
Right Turn Lane / Trail
Right turn extension; bridge
/ Bridge Extension
deck expanded; extension of
Colleyville: $125,000
(North side of
pedestrian trail
Euless: $125,000
intersection with
*Partner with Euless, Bedford,
Bedford: $0 (Support Only)
Cheek-Sparger)
Tarrant County
County: $500,000
City source: Capital Proj. Fund
County source: A, B or C
Heritage Avenue
Design & Construction —
Est. $1,932,503
(Cheek-Sparger to
Replace asphalt roadway with
Guadalupe)
concrete; replacement of 1
Colleyville: $251,225
bridge; curb, gutter, and
Euless: $135,275
drainage systems
County: $1,546,002
*Partner with Euless
City Source: Capital Proj. Fund
County source: A, B, or C
Cheek-Sparger
Construction —
Est. $1,200,000
Pedestrian Trail
Replacement of existing trail
Reconstruction
with concrete trail (10 ft. width);
Colleyville: $200,000
(Heritage Avenue to
Existing trail is degraded asphalt
Bedford: $200,000
Bedford Rd)
*Partner with Bedford
County: $800,000
City source: TIF
County source: A, B, or C
Bransford Trail
Construction —
No additional
Est. $800,000
(Field St to Cotton Belt
New pedestrian trail along
ROW needed.
Trail)
Bransford Road; includes
Colleyville: $600,000
drainage culverts where
Design complete.
County: $200,000
necessary to construct the trail
City Source: Capital Proj. Fund
County Source: A or B
Bedford Road Trail
Construction —
Design complete.
Est. $1,000,000
(Glade Rd to Cheek-
New pedestrian trail along
Sparger)
Bedford Rd; includes drainage
Colleyville: $700,000
improvements where necessary
County: $300,000
City Source: Capital Proj. Fund
County Source: A or B
Glade Road Trail
Design & Construction —
Est. $800,000
(Pool Rd. to Eastern
New pedestrian trail on the
City Limits)
north side of Glade Road,
Colleyville: $200,000
connecting the new trail west of
County: $600,000
Pool to the eastern City limits
*Provides connectivity to 121
City Source: TIF
and regional trail systems
County Source: A, B, or C
Trail from the Nature
Construction —
60% Design
Est. $1,200,000
Center to SH26
New East/West pedestrian trail
Complete
connecting major trail systems
Colleyville: $1,000,000
at the Nature Center and on
County: $200,000
SH26
*Provides connectivity from
City Source: Capital Proj. Fund
Hurst to SH26 I
I County Source: A or B