3a Discussion of Master Plan Update
4.CITIZEN COMMENTS/PRESENTATIONS REGARDING ITEMS NOT ON
THE AGENDA
5.ADJOURNMENT
I hereby certify this agenda was posted on City Hall bulletin boards May 4,2018 by
5:00 p.m.
Joyceinne Williams
Administrative Support Specialist
A quorum of the Colleyville City Council and/or any other Colleyville Board,
Commission, or Committee may be in attendance at this meeting.
Any matter on this agenda may, at the discretion of the governing body, be
opened for public comment and discussion.
If you plan to attend this public meeting and have a disability that requires special
accommodations, please advise the Administrative Assistant at least 48 hours in
advance at 817.503.1180, and reasonable accommodations will be made to assist
you.
City of Colleyville Page 1
City of Colleyville
Parks and Recreation
Advisory Board
AGENDA DRAFT
City Hall
100 Main Street
Colleyville, Texas
76034
817.503.1000
www.colleyville.com
Monday, March 5,
2018
6:00 p.m.
Colleyville Public Library
110 Main Street - 2nd Floor Meeting Room
1. CALL TO ORDER
Vice Chair Mitali Mandelkar called the meeting of the Parks and Recreation
Advisory board to order on March 5, at 6:02 p.m.
Present: Vice Chair Mitali Mandlekar, Board Members: Rich Hendler, Cliff
LeBlanc, Jim Hasenpflug, Natalie Genco, and Ajit Purandare.
Colleyville Baseball Association Representative, Scott Hickson. City staff: Parks
Manager, Heather Dowell, Senior Center/Recreation Manager, Lisa Escobedo,
Administrative Secretary, Joyceinne Williams.
Absent: Chair, Hillary Schwanbeck and Board Member, John Hillebrand.
Heather Dowell introduced Joyceinne Williams to the group as the new
Administrative Secretary for Parks/Recreation/Senior Center. Everyone introduced
themselves welcomed Joyceinne to the group.
2. APPROVAL OF MINUTES – January 8, 2018
2a Corrections to January 8 Minutes
Jim Hasenpflug made note that there was no recording of motion of
approval of January 8, 2018 minutes. The correction will be added to
the final minute notes.
Rich Hendler wanted to clarify that he was excited at the meeting on
January 8, 2018 his comments intent was more for dialogue but never
questioned the Board’s focus. He stated that the Board is highly
appreciated.
Board member Jim Hasenpflug moved to approve the January 8, 2018
meeting minutes (with corrections) and Board Member Rich Hendler
seconded the motion. The motion carried unanimously.
Parks and Recreation Advisory
Board MINUTES March 5, 2018
City of Colleyville Page 2
3. REGULAR AGENDA ITEMS
3a Colleyville Baseball Association discussion and report
Scott Hickson, currently the President of the Colleyville Baseball
Association, thanked the group for the invitation and proceeded to
update the Board on the status of the Association. Presently, there
are approx. 680 registered participants in the 2018 Spring Program
(capacity is 700). Spring is the biggest season. Usually about 70% of
capacity in the Fall season. The population of participants was down
three years ago, but now we are getting back the kids, but they are
much younger. The players today are 8 years old and under and make
up approx. 65% of the overall capacity.
Scott Hickson indicated that there are some struggles of the
association; a lot of the kids are from out of the city and they come
because they have played together since they were 3, 4, and 5 years
old. They are used to playing together. When they turn 7 years old
they go into a draft and they are appointed new coaches and start to
play with other kids. Most of the coaches are volunteer coaches (a
little bit of daddy ball). The level of coaching experience varies, as a
result of this. That is why 4 to 5 players are retained on each team,
the rest are drafted. If they don’t get drafted, they go to a blind draw.
If they are not selected on the blind draw, they will end up on a new
team. We lose whole teams to Tri-Cities, Grapevine, Keller, etc. where
they can keep playing together. (They take their team over to the rec
team which then become part of a select team.) They play 12 games
and get beat. A lot of times they come back and realize “the grass is
not always greener on the other side”. The older age players are
divisional one athletes and they are a part of that pool of players. As a
result, they go to Grapevine (who has formed a new Raiders Program)
and other select teams or club ball teams and pay $2000 a season
(that is where the best talent is). For this reason, we are seeing that
we have younger players.
Rich Hendler - How many kids that are playing rec are actually having
fun?
Scott Hickson stated that most of the kids that are playing rec are
actually having fun but 80% of the kids playing “select” actually feel
like it is a job. They are playing 5 days a week and they feel a lot of
pressure because they are always playing in tournaments.
Rich Hen dler - Is that the way the tournaments go, a bunch of games
played on Saturday and if they win, they play on Sunday?
Parks and Recreation Advisory
Board MINUTES March 5, 2018
City of Colleyville Page 3
Scott Hickson – You play two games on Saturday and get seeded into
brackets for Sunday – personal observations. One of the hidden gems
is that we have a “premier league” which allows our teams to play
against other cities. This provides a higher level of recreational play.
When season is over they can play the All Stars together.
Cliff LeBlanc - How can we help?
Scott Hickson indicated that a lot of the teams are leaving to play on
turf. A lot of negative criticism because the teams could not play
because of the wet grass.
Discussion on the pros and cons of turf (synthetic) versus grass:
Heather Dowell – The disadvantage of grass is because it gets muddy
and teams can’t play. We receive many comments that the synthetic
turf gets really hot and they do not like it. The City of Grapevine had
synthetic turf installed on all of their fields. They did not pay for the
synthetic turf. An outside firm came in and paid for it.
Scott Hickson – When the fields are wet, games can’t be played. There
is available cash to use on additional practice facilities. It is great to
be profitable but not for a nonprofit organization. The money needs to
be reinvested. Some considerations are:
• installing WiFi so the games can be followed on game changer and
face time for the parents to watch all over the country.
• contacting other locations, including the Colleyville Senior Center
open area to see if something could be done for additional practice
locations.
• Colleyville Baseball Association would like to partner with the city
to come up with ideas of enhancing our fields.
• Consideration of a giant pl ay area for young kids
Heather Dowell – WiFi is being heavily discussed in the Master Plan.
Cliff LeBlanc – Is there a priority list?
Mitali Mandlekar – Is practice space considerations in the Master Plan
discussion?
Parks and Recreation Advisory
Board MINUTES March 5, 2018
City of Colleyville Page 4
Heather Dowell – Yes, practice space was brought up multiple times.
There continues to be a lighting issues at some of the parks (Reagan
Park). The Senior Center is our only prime piece of available space left
that can be opened up. We are tight on space and purchasing
affordable land in Colleyville is a problem.
Scott- People are comparing all of the Grapevine and Southlake
updates.
Rich – Are we doing enough to work with GCISD for availability?
Lisa Escobedo - We utilize GCISD space availability as much as
possible. We have to consider that they have many sports and
activities going on at their facilities, so availability is limited. GCISD
gets priority. It is very difficult to keep it on a regular basis.
Heather Dowell – Some of GCISD fields also have lighting problems.
Some of their fields need improvements, which is costly.
Jim Hasenpflug – In preparation for the final stages of the master plan
that are earmarked for softball, recreation, etc. maybe we can come to
the table with the Association to see what improvement we can work
out together.
Heather Dowell – We have previously worked with the baseball and
softball association to come up with priority list. Last year we put up
new scoreboards for softball, baseball did not want it, but later they
wanted it. Things like that we can do outside the Master Plan.
The Master plan is for big ticket items and we can work together to
come up with everybody’s feedback to establish a priority list for next
season, not just organized space but how the “open space” is best
used. We can definitely set up a smaller meeting to discuss putting
ideas together.
Rich Hendler – Do coaches have specific training required?
Scott Hickson – The Association has established an academy for coach
training for our Select group that was established for older kids. We
have partnered with the Profession Development Center (PDC) and we
house the Colleyville Club Team at the facility which is located in
Bedford. This is to try to give some of the Colleyville kids an outlet
without leaving and to stay with our league. We are trying to work
Parks and Recreation Advisory
Board MINUTES March 5, 2018
City of Colleyville Page 5
with some of the high school coaches to team up with us to help train
some of our Dad’s that are less experienced.
Rich Hendler – Do we still have some of the Rangers that live in
Colleyville?
Scott Hickson – Yes, some of them are starting up their own clubs for
rising stars in the baseball world.
Rich Hendler – Again, how can we help?
Heather Dowell – We need to work together on our top priority list to
bring back to our group to see how we can combine the funds from the
Association, Volunteer Park Funds, etc. It depends on what it all looks
like and how we can accomplish it together. Some of the things will
fall out in the Master Plan.
Our main objective is to keep our Colleyville kids playing here. We are
approximately 50% residents involved.
Cliff LeBlanc– Are our facilities full?
Scott Hickson – Yes, as far as practice, the facilities are full. Now that
the games have started we have had to shift the practices elsewhere.
Check with Council about signage for sponsors to put money into
paying for scoreboards etc. City ordinance does not allow sponsor
logos. Maybe that can be changed.
Also, no grand opening celebration is allowed for opening day.
4. REPORTS
4a Parks Update
Heather Dowell reported:
In full gear for Spring sports after all the rain.
Finishing up grass cutbacks, weed bed cleanout mulching for this
month. Clean out of the tree wells completed and uniform
improvements should be finished before Farmers Market.
Working on installing the artwork project to the roundabout on Main
Street. Three little dancing children will be added and we plan to have
Parks and Recreation Advisory
Board MINUTES March 5, 2018
City of Colleyville Page 6
it finished before the Farmer’s Market on March 24. This is the first of
the program.
The design for the Village Plaza at city hall will be discussed at City
Council tomorrow, March 6, and there will be a public meeting on
March 14 in the breezeway by the Library to look at some of the
design options proposed by the consultant, Freese & Nichols, Inc., for
public feedback.
Movies in the Park on March 16, at 7:45 p.m. Movie feature is
“Ferdinand”.
Farmers Market is on March 24, from 9 a.m.-2 p.m. and will proceed
every Saturday. Vendors may change weekly.
We are working on the sealed bids for the Ki mzey Pond Project. Bids
expected to go out this month. Hopefully, work will begin at the end
of April into May. We will try to do the “best value bid”. The bids are
being sent out without full explanation to try to get a variety of
different ideas on how the job can be accomplished, time frames, etc.
A basic conversation was held with one of the bidders to get more
familiar with the project. There has been siltation study done and a
settlement testing and we are prepared to put that on the document.
Cliff LeBlanc – Will it help with the drainage in that area?
Heather Dowell – Not necessarily, but it will have more capacity. Now
that everything is built out, this should help the situation. We also
would like to stock the pond, once this is completed.
Mitali Mandlekar – Are there special permits needed for this project?
Heather Dowell – No, they think we will do the National permit.
Heather Dowell – The Hall Johnson Median has been completed with
new landscape. Looking forward to a lot more median work to be done
in the city.
Public Works cleaned out the LD Lockett Park channel. They are still
working on details and then will revegetate it.
We have been clearing out fallen trees from the creek in the Nature
Center. They were creating some major trash collection points and it
Parks and Recreation Advisory
Board MINUTES March 5, 2018
City of Colleyville Page 7
was not only looking bad but was not good for our aquatic life and
other wildlife. We are looking into some options to collect trash
upstream as it enters Colleyville to help keep our creeks cleaner in the
future.
The Parks and Recreation Master Plan Council Worksession is set for
March 20th at 5:30 p.m. This meeting will be directed at Council, but
we would like you to be in the room to hear Council thoughts/feedback
and the Mayor may ask you questions, if he needs to. We will send
out Chapter 4 and Chapter 6 for you to review what the consultants
have put together as visual from discussion from you and Council.
From there they will bring a draft back to finish it out. Will then send
out final draft for review.
Mitali Mandelkar – Do we have a schedule as to when the Master Plan
will be completed?
Heather Dowell – It depends on once we get feedback. They are
working on everything right now. They want to get Chapter 6
reviewed before they can determine the implementation. Everything
else in the Master Plan is in the process. In a couple weeks the final
draft should be prepared.
4b Recreation Update
Lisa Escobedo reported:
The Bunny Brunch is scheduled for Saturday, March 24. The event is
sold out with 250 participants. Market Street will be catering the
brunch.
Girls Spring Volleyball League began February 26 with 38 teams
participating. There are 17 Division 2 teams (13 years & under) and
21 Division 1 teams (10 years & under). A total of 372 girls
participating.
Spring Tennis Leagues began in late February into early March, with
13 teams playing at City Park.
Senior Valentine’s Dance was held on Wednesday, February 14. Sixty
seniors participated and enjoyed an ice cream bar, refreshments and
music by Doc Gibbs.
Parks and Recreation Advisory
Board MINUTES March 5, 2018
City of Colleyville Page 8
Colleyville Clean Sweep will be held on April 7 from 9 a.m.-11:00 a.m.
at the Colleyville Heritage High School (annual Hazardous Household
Waste Collection Event).
The Texas Junior Anglers is scheduled for Saturday, April 21 from 9
a.m. – noon at the Colleyville Nature Center. This is a great
opportunity for children 16 years and under to enjoy a day of free
fishing. Prizes will be awarded. Poles and bait are available. No pre-
registration is required.
5 CITIZEN COMMENTS/PRESENTATIONS REGARDING ITEMS NOT
ON THE AGENDA
Rich Hendler – Are we outside of the by-laws by meeting quarterly.
Heather Dowell – We spoke with the City Secretary and we are OK.
We can call special meetings when necessary, as long as we do not
meet less than what is in the by-laws. We must have items entered 2
weeks before the next meeting for approval of everything that is going
to be on the Agenda so it can be entered into the laserfiche system.
The Agenda must be posted 72 hours before the meeting.
Rich Hendler – I would like to add Colleyville Tree discussion on next
Agenda. Would like to discuss the following:
The tree ordinance
More knowledge about the Tree board. (i.e. when they worked
last , how are they enforcing, etc.)
Report on parks fund
General education to our staff and what we need to do when we
have an oversight by P&Z.
Natalie Genco – Can we send the minutes from the last tree board
meeting? There was valuable information discussed.
Rich Hendler - Is the tree inventory discussed in the Master Plan? Can
we invite the Urban Forester to our next meeting?
Heather Dowell – Yes, he will be invited to the next meeting.
Natalie Genco– Is there a way to send out minutes sooner?
Parks and Recreation Advisory
Board MINUTES March 5, 2018
City of Colleyville Page 9
Heather Dowell – We will do better.
Ajit Purandare– When will the Nature Center signs go up?
Heather Dowell – The guys are making the signs now. It was delayed
because of the weather. Should be up this Spring. Hope to have
them up by Texas Junior Angler on April 21.
Natalie Genco – When Hwy 26 is finished will Colleyville be
responsible for the medians that run along Hwy 26 with landscaping.
Heather – Yes, we are responsible for the middle medians. That is
the City’s responsibility not the State’s. It will be revisited in their
original contract.
Jim Hasenpflug – Further north median landscaping, proactive about
trying to get stuff to grow. Is that part of the contract that the City
will take care of?
Heather Dowell - It depends on what the contract reads. Each City is
different. We will be responsible for the middle median and our
landscaping should be better.
6. ADJOURNMENT
Board member Natalie Genco moved to adjourn the meeting, and board
member Cliff LeBlanc seconded. Motion c arried unanimously. Vice Chair,
Mitali Mandlekar adjourned the meeting at 7:25 p.m.
APPROVED BY A VOTE OF __ AYES, __NAYS, AND __ ABSTENTIONS ON THIS THE
___________.
Minutes taken and prepared by:
Joyceinne Williams
Administrative Secretary
Capital Projects Priority Ranking
Colleyville Parks, Recreation & Open Space Master Plan Name_____________________________________________________
Capital Improvements Ranking Draft 5/2/2018
Priority
Level Capital Improvement
Capital Projects Rank - High (3), Medium (2), Low (1), or Not Needed (0).
1 Athletic Fields - Upgrade turf
2 City Park - Both Restroom/Concession Buildings - Repair building exterior grout and wainscot, update interiors, improve concession areas
3 City Park - Small playground near ballfields
4 City Park - Install shaded outdoor fitness stations
5 City Park - Replace and enlarge shade shelters over spectator areas
6 City Park - Additional netting at ball diamonds for spectator safety
7 City-wide - Consistent park signage system (including entrance signs, directional signs, park rules signs, and interpretive signs)
8 City-wide - Provide accessible walkways to all playgrounds, picnic shelters, athletic fields and spectator areas to meet ADA guidelines
9 City-wide - Install Wi-Fi in the larger parks
10 City-Wide - All parks - Tree planting program to provide shade and improve tree canopy
11 CNC - Expand paved trail system and safer stream crossing
12 CNC - Restroom Building
13 CNC - Signage and wayfinding system
14 CNC - Establish as an arboretum with labelled trees and horticultural display areas.
15 CNC - Develop bird blinds
16 CNC - Install benches along trails
17 Dog Park - Identify a location and develop a dog park
18 Kimzey Park - Add a restroom building
19 Kimzey Park - Dredge pond
20 Kimzey Park - Replace playground and improve drainage
21 Kimzey - Install shaded outdoor fitness stations
22 L.D. Lockett - Playground and exercise stations
23 L.D. Lockett - Clear out vegetation from drainage channel
24 McPherson - Rock House interior renovation, upgrade lighting
25 McPherson - Pavilion/Restrooms renovations - painting and ventilation, additional electrical outlets
26 McPherson - Upgrade Dairy Barn displays
27 McPherson - Rehabilitate the two historic mud house barns
Please indicate a High Priority (3), Medium Priority (2), Low Priority (1), or Not Needed (0) for each item on the list. Please place a number in the far left column that
indicates your priority for the proposed improvement. Rank each improvement. The priority ranking is for the level of importance of the improvements and not necessarily
the order in which they will be developed. When completed, please scan and email it to phoagland@bciaep.com or send to Lisa Escobedo. Thank you very much.
Capital Projects Priority Ranking
Colleyville Parks, Recreation & Open Space Master Plan Name_____________________________________________________
Capital Improvements Ranking Draft 5/2/2018
Priority
Level Capital Improvement
Please indicate a High Priority (3), Medium Priority (2), Low Priority (1), or Not Needed (0) for each item on the list. Please place a number in the far left column that
indicates your priority for the proposed improvement. Rank each improvement. The priority ranking is for the level of importance of the improvements and not necessarily
the order in which they will be developed. When completed, please scan and email it to phoagland@bciaep.com or send to Lisa Escobedo. Thank you very much.
28 Pleasant Glade Tract (behind Senior Center) - Develop as a Neighborhood Park with playground, splash pad, picnic shelters, Pickleball courts, shaded
fitness stations, tree planting for shade, parking, etc.
29 Pleasant Run - Shade, restrooms and drinking fountain on practice field side
30 Pleasant Run - Develop trail system within park on north (practice fields) side to complete the loop
31 Pleasant Run - Upgrade landscaping in parking lot islands
32 Pleasant Run - Install accessible walk from overflow parking to park
33 Reagan Park - New restroom building
34 Reagan Park - Upgrade irrigation system
35 Reagan Park - Shade and dugouts at fields for players and spectators. Walkways to spectator areas.
36 Recreation Center - Develop a Recreation Center at the Senior Center site with kitchen, program space, gym, walking track, aerobics/dance rooms.
37 Recreation Center - Develop an indoor pool as part of the proposed Recreation Center
38 Senior Center - Develop a new Senior Center Wing on the Recreation Center with meeting and program space, kitchen, computer lab, game room, craft
room
39 Trails - Develop a trail between Sparger Park and the Colleyville Nature Center
40 Trails - Implement the Trails Plan
41 Woodbriar Park - Replace playground and shelter, improve trail system
42
ACTION PLAN - COLLEYVILLE PARKS, RECREATION & OPEN SPACE MASTER PLAN
0-2 3-5 6-10 10+
Goal 1: Maintain Exemplary Facilities, Programs, and Services
Strategy 1.1.1:Initial focus should be directed toward improvements to existing, key facilities such as needed
improvements at the existing parks, trails, playgrounds, game courts, picnic shelters, restrooms, and athletic
fields.P P Capital Parks OP, CIP
Strategy 1.1.2:Restrooms are needed at Kimzey Park, Reagan Park, Colleyville Nature Center, and the McPherson
Practice Felds. P Capital Parks CIP
Strategy 1.1.3:The addition of needed support facilities, including trails, restrooms, signage, and drinking fountains should
be part of any park improvement. P P P P Capital Parks CIP
Strategy 1.1.4:Completely redesign and redevelop Woodbriar Park to current standards (new playground, picnic shelter,
landscaping, signage, etc.)P Capital Parks CIP
Strategy 1.1.5:Install the originally planned playground and adult fitness stations at L.D. Lockett Park to complete this park
development P Capital Parks CIP
Strategy 1.1.6:Opportunities for additional picnic shelters should be considered at existing parks
P P P P Capital Parks CIP
Strategy 1.1.7:Electricity should be provided at all rentable picnic shelters
P P P Capital Parks CIP
Strategy 1.1.8:Establish an implementation committee to monitor timelines, measure progress, update priorities, and
ensure continued enthusiasm for Master Plan goals and recommendations P Policy Parks, City OP
Strategy 1.1.9:Additional benches and shade are needed along the trail behind the Senior Center in the Pleasant Glade
Tract, especially as one gets further from the Senior Center P Capital Parks CIP
Strategy 1.1.10:Consider unmet facility needs as part of any new park development
P P P P
Policy,
Planning,
Capital
Parks OP, CIP
5/2/2018
Legend of Abbreviations/Organizations
Parks =City of Colleyville Parks and Recreation
City = City Council, Other City Divisions
Dev = Developers
Objective 1.1 – Excellence - Proactively maintain high quality facilities constructed with durable materials and innovative design to reduce long-term maintenance costs and inspire community confidence in the quality
of the park system.
Goals, Objectives, and Strategies
OP = Parks Operating Budget
CIP = Capital Improvement Budget
Agency
Partners = Other organizations (foundations/friends groups, businesses, civic associations, state/federal grants, etc.)
Funding
SourceCategory Planning LinkTimeframe (Years)
NH/HOA = Neighborhood or Homeowners Associations Revenue = Items that Generate Additional Revenue
Targeted Outcome: Strive for excellence in all aspects of parks and recreation with an emphasis on safety and security to meet and encourage high standards for facilities, programs, and services.
1 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Strategy 1.1.11:Renovate and improve both restroom facilities at City Park and at Pleasant Run Soccer Complex - repair
building exterior, update interiors, improve concessions. Restrooms at City Park should be renovated to
include improved air circulation and repair of the grout and wainscoting. All water closets should have
toilet seats installed. The exterior surfaces of several restroom and concession building need to be
improved.
P Capital Parks CIP
Strategy 1.1.12:Add a small playground near the ball diamonds at City Park
P P Capital Parks CIP
Strategy 1.1.13:Improvements should be made to upgrade the Colleyville Nature Center with restrooms as a top priority,
followed by drinking fountains, shade, bird blind, benches along trails, and improved signage. These
improvements would accommodate school groups use and self-led use of the facility. The Center also
needs volunteer efforts to eradicate invasive species and poison ivy
P Capital Parks CIP
Strategy 1.1.14:Replace the playground and improve drainage at Kimzey Park
P Capital Parks CIP
Strategy 1.1.15:Improve McPherson Rock House with interior renovation and upgraded lighting
P Capital Parks CIP
Strategy 1.1.16:McPherson Pavilion/Restroom renovations - painting and ventilation, additional electrical outlets
P P Capital Parks CIP
Strategy 1.1.17:McPherson - Upgrade Dairy Barn interpretive displays
P Capital Parks CIP
Strategy 1.1.18:McPherson - Rehabilitate the two historic mud house barns
P Capital Parks CIP
Strategy 1.1.19:Program satisfaction levels, attendance, and trends should be continuously monitored to ensure program
offerings match the needs of the community Operations Parks OP
Strategy 1.1.20:Colleyville should continuously solicit feedback from park and program users to ensure new and changing
needs are met Operations Parks OP
Strategy 1.1.21:Upgrade the Pleasant Run Soccer Complex practice fields. Develop restrooms on the practice field side of
the complex. Provide additional shade. P Capital Parks CIP
Strategy 1.2.1:Shade was a common and strong suggestion in all forms of public engagement. Shade can be provided
through structures and trees. All parks should be evaluated to determine where shade could be provided
and the best method to accomplish the shade. Locations that were mentioned in the engagement the
most are the sports facilities, such as between fields at City Park and Pleasant Run Soccer Complex.
Shade should be provided at playgrounds, splash pads, and along trails.
P P Capital Parks CIP
Strategy 1.1.2:Assure that all playgrounds meet current guidelines, especially as they pertain to safety issues such as fall
zones and surfacing. Older playgrounds in the city should be replaced, such as at Woodbriar Park. Operations Parks OP, CIP
Ongoing
Ongoing
Ongoing
Objective 1.2 - Safety and Security - Provide a safe environment by ensuring regulatory compliance, sufficient supervision, and adequate shade at parks and facilities.
2 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Strategy 1.2.3:Install security cameras (and additional lighting as needed) to all Community and Neighborhood parks to
encourage a safe atmosphere and to prevent damage to park property P P Capital Parks, City CIP
Strategy 1.2.4:Improvements should be made as needed to athletic field surfaces to provide for optimal playing
experiences and to maintain safety for users P P Capital Parks CIP
Strategy 1.2.5:Prioritize short-term maintenance of existing parks and facilities over long term capital improvements
P Policy Parks, City CIP
Strategy 1.2.6:Replace and enlarge spectator and dugout fabric shade structures
P P Capital Parks CIP
Strategy 1.2.7:Provide additional netting at City Park Ball Diamonds for spectator safety
P Capital Parks CIP
Strategy 1.2.8:Collaborate with law enforcement to increase presence in the parks and an improved perception of safety
for park users Operations Parks, City OP
Strategy 1.3.1:The maintenance staff should be expanded as additional parks and facilities are developed to maximize
the parks’ longevity, safety, and appearance P P Operations Parks OP
Strategy 1.3.2:Provide training to ensure highly proficient and passionate staff, coaches, and volunteers
Operations Parks OP
Strategy 1.4.1:Establish a program to recruit and organize volunteers to adopt sections of trails in Colleyville (and new
trails as they are developed), including paved trails and unpaved trails, to keep the trails free of litter Operations Parks OP
Strategy 1.4.2:Establish a position of Volunteer and Sponsor Coordinator and promote the use of volunteers, especially as
the nature-oriented facilities and trails are developed P Operations Parks OP
Strategy 1.5.1:Cooperate with other agencies and organizations toward the creation and promotion of a common
calendar for activities and events in Colleyville, including opportunities for recreation, education, and
tourism. Cross promotion of events should also be part of such an agreement P P Operations Parks,
Partners OP, Partners
Strategy 1.5.2:Investigate new and inventive funding sources for parks and recreation improvements. Some communities
in the Metro have utilized a dedicated sales tax for major improvements Operations Parks CIP, OP
Strategy 1.5.3:Encourage the creation of a Friends of Colleyville Parks foundation to recruit and organize volunteers, to
raise funds and apply for grants, and to work toward the implementation of improvements outlined in this
Master Plan. The Friends of Colleyville Nature Center (CNC) already have an established organization
which can be utilized for these purposes at the CNC.
P P Operations,
Policy Parks OP
Strategy 1.5.4:Pursue grants for development and operation of parks and recreation facilities and programs Operations,
Policy Parks, City OP, City
Ongoing
Ongoing
Ongoing
Objective 1.3 - Model for Service - Employ a highly trained, proficient, and passionate staff to set a standard of excellence for programming and maintenance of land and facilities as expected by Colleyville residents.
Objective 1.4 - Volunteerism - Encourage volunteerism to help build community interest and to ensure the continuation of quality parks and programs.
Ongoing
Ongoing
Objective 1.5 - Financial Sustainability - Promote financial sustainability through cost-effective development decisions that consider revenue opportunities.
3 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Strategy 1.5.5:Programs offered should include a level of cost recovery as most classes and programs will require fees for
registration Policy Parks OP
Strategy 1.5.6:Consider selling naming rights to facilities to help mitigate capital and operating costs. Rights could be
sold to whole facilities (community center, fields, splash pad, playground) or to areas within a facility
(meeting rooms, fields, courts). P P P P Policy Parks OP
Strategy 1.6.1:Partner with Grapevine-Colleyville ISD to develop park facilities adjacent to any new schools they may
develop Operations City,
Partners CIP, Partners
Strategy 1.6.2:Partner with existing and potential private recreation providers to expand the availability of opportunities in
the City Operations Partners Partners
Strategy 1.6.3:The City should seek partnerships to provide programs that require facilities not offered by the City of
Colleyville Operations Partners Partners
Strategy 1.6.4:Continue to coordinate with adjacent communities on program offerings, events, and coordination of
dates Operations Partners,
Parks OP, Partners
Strategy 1.6.5:Seek opportunities for collaboration with other organizations to improve the number and variety of
program offerings and to help fill program deficiencies. Work with these other agencies and organizations
to improve awareness of programming opportunities and to coordinate offerings to avoid duplication of
services. A partnership with the GCISD and possibly local colleges as part of the development of nature
programs
Policy,
Operations Partners OP, Partners
Strategy 1.6.6:Establish partnerships for both the securement of funding for capital improvements and for the operation of
new facilities, particularly for high cost projects. Partnerships should require detailed documentation of
funding sources and operating strategies (pro-forma)
Policy,
Operations Partners CIP, Partners
Strategy 1.6.7:Maintain existing relationships with organizations that manage the youth sports leagues and seek new
partners for the management of new sports leagues as interests grow Operations Partners Partners
Strategy 1.6.8:Maintain and expand existing relationships with private recreation providers and develop relationships with
any future providers Operations Partners Partners, OP
Strategy 1.7.1:Utilize branding in the development of common design standards to maintain a consistent appearance of
parks, signage, and amenities and to enhance the Colleyville brand P P Planning,
Operations Parks, City OP, CIP
Strategy 1.7.2:A strong and consistent branding and signage program will elevate the public’s awareness of parks and
facilities and recognize them as City of Colleyville facilities. Apply branding standards to visual elements of
Colleyville parks and recreation, including signage, printed materials, web page, social media, and other
methods
P P
Planning,
Operations,
Capital
Parks, City CIP, OP
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Ongoing
Objective 1.6 - Partnerships - Pursue partnerships with other public agencies and private organizations to maximize the availability of parks and recreation services and facilities for residents and visitors.
Objective 1.7 - Branding - Establish uniform appearance and design standards to enhance the identity of Colleyville Parks and Recreation.
4 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Goal 2: Promote Fun, Excitement, Health and Community Enrichment through Parks and Programs
Targeted Outcome: Strategically plan short- and long-term investments in parks, facilities, and programs that promote the enrichment of the community.
Strategy 2.1.1:Develop disc golf courses where appropriate to attract youth and young adults to utilize parks
P Capital Parks CIP
Strategy 2.1.2:Establish more adult oriented sports activities
P P P Operations Parks OP
Strategy 2.1.3:Establish some multi-purpose fields that may be used for open play and adult use to encourage fun fitness
activities P P P
Planning,
Operations,
Capital
Parks CIP
Strategy 2.1.4:Develop a new Splash Pad on the southeast portion of the City for more equitable distribution. It could
potentially be developed to complement a new community/recreation center P Capital Parks OP
Strategy 2.1.5:Continuously monitor trends in recreation, particularly among growing population groups, to ensure facility
and program offerings remain on the cutting edge while meeting the needs of a diverse community Operations Parks OP
Strategy 2.1.6:Increase the number and types of active adult programs (ages 40-60)
P P P Operations Parks OP
Strategy 2.2.1:The agriculture buildings at McPherson Park are underused and offer an opportunity for additional program
and interpretive function P P Planning,
Capital
Parks,
Partners
OP, CIP,
Partners
Strategy 2.2.2:Include playgrounds and rentable picnic shelters whenever possible as part of new park development
P P Capital Parks CIP
Strategy 2.2.3:The Nature Center would get better use with a nature education center and naturalist staff for education
programs Operations Parks,
Partners OP
Strategy 2.2.4:The Nature Center could be developed as an arboretum with labelled trees
P P P Capital.
Planning Parks CIP, OP
Strategy 2.2.5:The City is planning nature camps for the summer of 2018. Build on the success of these programs
P P Operations Parks OP
Strategy 2.2.6:At City Park, provide a small playground near the ballfields. Also provide additional netting to protect
spectators P Capital Parks CIP
Strategy 2.2.7:Programs should be developed to maximize utilization of existing facilities and any future facilities
Policy Parks OP
Strategy 2.2.8:Provide Wi-Fi in all Neighborhood and Community Parks with initial focus on the most used parks (City Park,
McPherson Park, Colleyville Nature Center, Pleasant Run Soccer Complex, and the Senior Center). P P Capital Parks CIP
Strategy 2.2.9:Encourage youth to experience the outdoors in healthy and educational pursuits by expanding nature
education programs and recreational opportunities Operations Parks OP
Strategy 2.2.10:Keep programs fresh and relevant through continuous monitoring of satisfaction, attendance, and
effectiveness Operations Parks OP
Ongoing
Ongoing
Ongoing
Objective 2.1 - Fun - Explore a wide variety of opportunities for fun and excitement at parks.
Objective 2.2 - Exceptional Experiences - Utilize trendsetting and exceptional parks and recreational facilities to enrich the community through a variety of athletic, educational, fitness, life skills, and
cultural arts programs.
Ongoing
5 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Strategy 2.3.1:Add walking trails at parks currently lacking those facilities (particularly trail loops) and improve
connectivity within parks through added walkways and connecting paths. Walking trails should be
developed as loop trails at all major parks, including expansion of the trails at McPherson Park and
Pleasant Run Soccer Complex. For maximum accessibility, these should be concrete paved
P P Capital Parks, City CIP
Strategy 2.3.2:Include trails as part of the development of all new parks. These offerings should include both paved and
unpaved trails and should provide connections to the adjacent communities P P P P Capital,
Planning Parks, City CIP
Strategy 2.3.3:Outdoor fitness equipment with a shade cover should be installed at select parks to provide an opportunity
for improved fitness for residents, including seniors. Good opportunities exist at Kimzey, City Park,
McPherson, and Pleasant Run Parks, to install these facilities P P Capital Parks CIP
Strategy 2.3.4:Expand the availability of programs for seniors, particularly healthy seniors. A Silver Sneakers program
would offer a series of fitness programs for seniors in the City P P Operations Parks OP
Strategy 2.3.5:Increase programming and opportunities for adult fitness and wellness through additional facilities and
programs, which may include indoor fitness oriented activities, programs in parks (i.e., yoga, etc.), and
more fitness stations (with programs)Operations Parks OP
Strategy 2.4.1:Allocate space and study the feasibility of development of a full-service Recreation and Senior Center with
indoor pools, walking track, gymnasium, fitness/cardio rooms, meeting rooms, kitchen, group exercise
studios, and more. Investigate potential partnerships to share in the development and operations costs of
such a facility
P Planning,
Capital Parks, City CIP, City
Strategy 2.4.2:Pursue partnerships to develop a full-service recreation center with indoor pool. This facility should also
include a senior component to maximize space utilization and meet this growing need. The recreation
center portion should include a walking track, gym, aerobics/dance rooms, cardio and weight rooms,
meeting rooms, kitchen, as well as a pool for lap and fitness swimming. The senior component would
include a library, kitchen, meeting/program space, fitness room, computer lab, game (billiard) room, craft
room, and potentially more. The current site of the Senior Center would work well for this new facility as
there is additional land available behind the facility.
P P
Policy,
Planning,
Capital
Parks, City
CIP,
Partners,
City
Goal 3: Utilize Connectivity to Build Community
Targeted Outcome: Improve connectivity to promote community interaction, health, and awareness of opportunities for parks, trails, programs, and events.
Strategy 3.1.1:Work with homeowner associations on privately held trails to incorporate them into the overall network of
trails, specifically mentioned throughout the public engagement were the Tara trails Operations,
Policy
City,
Partners
NH/HOA,
City
Strategy 3.1.2:Develop a soft-surface trail along Little Bear Creek to connect Sparger Park to the Colleyville Nature
Center P Capital Parks, City CIP
Strategy 3.1.3:Partner with the City and GCISD to develop safe routes to schools and parks. Provide connections to parks
from the surrounding neighborhoods where possible P P
Capital,
Policy,
Planning
City,
Partners
City, CIP,
Partners
Ongoing
Ongoing
Objective 2.3 - Healthy Lifestyles - Further enrich the community by encouraging interaction between users of all ages and by providing motivation and opportunities for healthy activities.
Objective 2.4 - Indoor Facilities - Upgrade the indoor recreation opportunities residents of all ages to accommodate a growing senior population, year-round programming, and fitness/wellness opportunities.
Objective 3.1 - Connectivity - Facilitate community connectivity with parks and programs to inspire pride and community identity though shared experiences.
6 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Strategy 3.2.1:Develop a Civic Commons near City Hall to host concerts and events. (This project is currently being
designed). P Capital City City
Strategy 3.2.2:If an event space is developed at The Village at Colleyville near City Hall and the Library, the City should
utilize the facilities for a series of events, including concerts, throughout the year P P P P Operations Parks, City OP, City
Strategy 3.3.1:Implement the recommendations of the Trails Plan that is part of this Master Plan
P P P P Planning,
Capital City City
Strategy 3.3.2:Coordinate with the currently ongoing Sidewalk Plan to ensure the two efforts complement each other
P P P P Planning,
Capital City City
Strategy 3.3.3:Coordinate with neighboring communities as part of long-term trail planning
Planning City,
Partners
City,
Partners
Strategy 3.3.4:Increase the availability of bicycle parking at all parks
P Capital Parks CIP
Strategy 3.3.5:Require that trails developed by private developments and homeowner associations adhere to the same
standards of design for City developed trails Policy City City,
NH/HOA
Strategy 3.3.6:Develop an adopt-a-trail program to assist in the maintenance and funding for trail improvements and
maintenance P P
Operations,
Policy,
Operations
Parks, City OP
Strategy 3.4.1:A conveniently located community bulletin board for the promotion of events and programs would help to
improve awareness of programming opportunities Capital,
Operations
Parks,
Programs OP, Partners
Strategy 3.4.2:Actively promote park improvements and new program offerings as they become available
Operations Parks OP
Strategy 3.4.3:Develop, promote, and regularly update a mobile application (smart phone/tablet app) to communicate
program offerings and improve park experiences (event information, park/trail maps). This app could be
utilized to encourage fitness in the community and to connect park users interested in gathering for
exercise. This app could also connect to a master schedule for athletic events.
Operations Parks,
Partners OP
Strategy 3.4.4:Increase usage of social media to promote programs and events to residents and visitors
P P Operations Parks OP
Strategy 3.4.5:Increase staff time and resources for marketing efforts
P P Operations Parks, City OP, City
Ongoing
Ongoing
Ongoing
Ongoing
Objective 3.2 - Gathering - Supply venues for the community to gather and connect with each other, and with nature, through both events and daily usage.
Objective 3.3 - Trail Connections - Utilize trails to provide opportunities for health and fitness and to connect parks, schools, neighborhoods, and other gathering places.
Objective 3.4 - Awareness - Encourage community connectivity by increasing awareness of available parks, programs, and events through online publication, promotion, and registration, including those
offered by other agencies or organizations.
Ongoing
7 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Goal 4: Ensure Equitable Access to a Wide Variety of Park and Recreation Services
Targeted Outcome: Strive to ensure accessibility of park facilities and programs to provide equitable access for all present and the future users.
Strategy 4.1.1:Opportunities for new parks should be investigated in key areas outside of the service areas of key facilities,
including playgrounds, trails, and basketball courts P P P P Planning Parks, City City, CIP
Strategy 4.1.2:Monitor any potential changes to be made by Grapevine-Colleyville ISD and any voids which may result
from any school closures, especially for playgrounds and outdoor basketball courts Planning Parks, City,
Partners
City,
Partners
Strategy 4.1.3:If land is available, some rectangular fields on the east side of the community would improve access
P P P Capital Parks CIP
Strategy 4.2.1:Provide a paved, accessible route to all playgrounds, picnic shelters, athletic fields and spectator areas
P P Capital Parks CIP
Strategy 4.2.2:Develop a dog park at an existing or new site (possibly adjacent to the Public Works Service Center to
share parking)P P Capital Parks CIP
Strategy 4.2.3:Opportunities for multigenerational and intergenerational programming should be considered to provide
opportunities for all ages. Intergenerational programming could include nature-based activities outdoors
(fishing, gardening, bird watching) and arts and crafts activities indoors (music, painting, cooking). Operations Parks OP
Strategy 4.2.4:Purchase a new bus to serve the Senior Center. The current van is difficult to enter and deters some from
participating when travel is involved P Capital City, Parks CIP
Strategy 4.3.1:Perform an ADA Accessibility Assessment of all facilities, programs, and communications. This assessment
could be accomplished by trained staff or an outside consultant P Planning Parks, City City, OP
Strategy 4.3.2:Pickleball has become extremely popular, especially among seniors. Develop courts at locations
throughout the City and mainly in conjunction with a potential recreation center which would host
programs for persons over age 50 P P Capital Parks CIP
Strategy 4.3.3:The Fitzgerald Collection of Colleyville artifacts needs a permanent home. Explore the possibility of
including it in the Webb Hosue or Bedault Houae.P P P Policy,
Capital City CIP, City
Strategy 4.3.4:Expand facilities and programs to serve users with special needs and consider the needs of those users as
part of any development P P P P Operations Parks OP
Ongoing
Objective 4.1 - Equity - Provide accessibility in terms of the geographic location of parks as well as the location of individual facilities within parks.
Objective 4.2 - Inclusiveness - Ensure an inclusive environment for social activities, relaxation, and entertainment for families and individuals of all ages.
Objective 4.3 - Diversity and Accessibility - Provide facilities and programs to meet the needs of a diverse population, including users of all ages and those with disabilities.
Ongoing
8 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Strategy 4.4.1:A scholarships program for program and facility fees should be established for those that cannot afford to
pay Operations Parks OP
Strategy 4.4.2:Offer programs for residents of all ages and abilities.
Operations Parks OP
Goal 5: Respect Nature
Targeted Outcome: Emphasize the value of Colleyville’s natural resources through preservation, education, and sustainable management practices.
Strategy 5.1.1:Ponds and drainage ways must be maintained, such as dredging of ponds at Kimzey and Colleyville
Nature Center and clearing the ditch at L.D. Lockett. (Kimzey pond and the L.D. Lockett ditch clearing are
in the 2018 CIP.)P P Capital,
Operations Parks CIP
Strategy 5.1.2:Efforts should be made to maximize the utility of natural resources for recreational opportunities and
enhancement of quality of life in Colleyville Policy Parks OP
Strategy 5.1.3:Develop landscaping options that use less water, such as the use of native plants and drip irrigation, and
advertise examples of these principles for the private sector to mirror Operations,
Planning Parks OP
Strategy 5.2.1:Acquire stream and drainage corridors and flood plain lands to connect natural areas of Colleyville Policy,
Planning,
Capital
City, Parks City, OP
Strategy 5.2.2:Employ parks as models for sustainable practices. Parks should be utilized to exemplify Best Management
Practices (BMPs) for stormwater management, recycling, low-water landscaping, use of organics, etc.Operations Parks OP
Strategy 5.3.1:Facilitate tree planting and landscape enhancements within parks
P P
Capital,
Planning,
Operations
Parks OP, CIP
Strategy 5.3.2:Perform a tree inventory and assessment and prepare a long-term plan for urban forest management to
maintain a healthy tree canopy P P
Capital,
Planning,
Operations
City, Parks CIP
Ongoing
Ongoing
Ongoing
Objective 4.4 - Affordability - Offer an array of affordable programs and facilities to enrich the lives of community members.
Objective 5.1 - Sustainable Development - Ensure development is environmentally sustainable and non-disruptive to the environment through the preservation of open space, the use of green (or eco-
friendly) materials and practices, and by ensuring development is suitable for protracted use.
Ongoing
Ongoing
Ongoing
Objective 5.2 - Stewardship - Implement environmental best management practices at parks to promote environmental stewardship and education.
Objective 5.3 - Enhance the Tree Canopy – Inventory, preserve, and expand the urban forest tree canopy.
9 of 10
0-2 3-5 6-10 10+Goals, Objectives, and Strategies Agency Funding
SourceCategory Planning LinkTimeframe (Years)
Goal 6: Acquire Open Space
Targeted Outcome: Acquire land for open space and future parks.
Strategy 6.1.1:Continue to examine opportunities for the acquisition of open space, giving priority to land that is
contiguous to existing open space or parks, needed for trail connections, or in portions of the City currently
underserved by parks and open space
Planning,
Capital City City
Strategy 6.2.1:Acquire one to two park locations of 10 to 15 acres each in the eastern portion of Colleyville for the
purpose of developing Neighborhood Parks to fill the gaps and provide parks within walking distance to
most homes P P Capital,
Planning City, Parks City, CIP
Strategy 6.2.2:Develop the Pleasant Glade Tract as a new Neighborhood Park with a playground, splash pad, picnic
shelters, Pickleball courts, shaded fitness stations, tree planting for shade, parking, etc.P Capital,
Planning City, Parks City, CIP
Strategy 6.3.1:Acquire land in the eastern portion of Colleyville to maintain as open space in this more densely populated
and more established area P P P Capital,
Planning City City
Strategy 6.3.2:Encourage developers to include common Neighborhood Park elements (as identified in this master plan)
in parks constructed to serve residents of future subdivisions Policy City
City,
NH/HOA,
Dev
52 62 26 11
Ongoing
Ongoing
Objective 6.1 - Open Space - Seek opportunities to acquire and protect open spaces and corridors for wildlife management, enjoyment of nature, enhancement of the community character, and
conservation of open space for future generations.
Objective 6.2 - Walkable Access to Parks - Provide accessibility in terms of the geographic location of parks including acquisition and development of Neighborhood Parks in underserved areas.
Objective 6.3 - Future Parkland – Acquire land for future parks, especially in the eastern half of Colleyville where there is a deficit of open space and opportunities for parks within a walking distance to
residences.
Totals by Timeframe Ongoing = 38