STATE OF TEXAS X
COUNTY OF TARRANT X
CITY OF COLLEYVILLE X
RESOLUTION R-78-173
RESOLUTION ESTABLISHING PROJECT SCHEDULE FOR GRANT
WHEREAS, the City of Colleyville has made application to the Texas Water Qual ity
Board and the Environmental Protection Agency for a Federal grant
pursuant to the Federal Water Pollution Control Act Amendments of 1972,
Public Law 92-500, and the rules and regulations thereto.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Colleyville
that the application for which Federal grant assistance has been
requested pursuant to the Federal Water Pollution Control Act Amend-
ments of 1972, Public Law 92-500, will be constructed to completion
in accordance with the laws, rules, and regulations and with the
following project schedule.
Genera 1 I nformat ion
Date
Availability of applicant's
share of project costs
Step 1
Step 2
Step 3
July 1978
July 1978
January 1980
Availabil ity of site(s) for
project facilities
January 1980
Project Schedule
I tern
Calendar Days
Step
A. Infiltration/Inflow Analysis
(with Evaluation Survey Plan
of Study if required)
Report completed and submitted to State 120 days
after Step 1 grant award.
B. Infiltration/Inflow Evaluation
Survey (if required)
Report completed and submitted to State 150 days
after grant amendment for
Survey.
c.
Environmental Assessment
(Including time for draft
report, advertisement, and
Final report completed and
hearing)
su bm i tted
to State
after
150 days
Step 1 grant award.
Resolution R-78-173
Page 2
D. Faci 1 ity Plan
Report completed and submitted to State 90 days
after EPA approval of 1/1
Analysis and 1/1 Survey (if
requ ired) .
Step 2
Final Plans and Specification
completed and submitted to State
180 days
after Step 2 grant award.
Step 3
Advertise for Construction Bids
within the days indicated after
authorization to advertise for
bids has been issued
30 days
Submit Bid Opening Documents
within the days indicated ater
the bid opening date
1 5 days
Award of Construction Contract
within the days indicated after
authorization to award the
contract has been issued
15 days
Initiation of Construction
within the days indicated after
the award of the contract
30 days
Complete Construction
within the days indicated after
initiation of construction
360 days
BE IF FURTHER RESOLVED, that the above named app1 icant understands that the above
project schedule must be approved by the Texas Water Quality Board and
the Environmental Protection Agency, and that once a project schedule
has been approved, no changes will be authorized without first receiving
approval of the change from the Texas Water Qual ity Board and Environ-
ment Protection Agency.
PASSED, APPROVED, AND ADOPTED this 18th day of July, 1978.