HomeMy WebLinkAboutCity Council Resolutions (RESOLUTION R-17-4157)-7/18/2017 RESOLUTION R-17-4157
ACKNOWLEDGEMENT OF A CHANGE ORDER REQUEST FOR POWDER
COATING SIGNAL POLES FOR THE SH26 PROJECT, AND AUTHORIZE
THE CITY MANAGER TO EXECUTE THE CHANGE ORDER, IN AN
AMOUNT NOT TO EXCEED $204,000
' WHEREAS, the Colleyville City Council is committed to the best interests of
the health, safety, and welfare of the citizens of Colleyville; and
WHEREAS, the City worked with TxDOT to incorporate aesthetic
enhancements which included black powder coated traffic signal
poles, back-lit LED street name signs, and stamped and colored
concrete crosswalks into the SH26 Project; and
WHEREAS, a Memorandum of Understanding (MOU) executed between the
project's funding partners states that the City is responsible for
the cost of the aforementioned upgrades, should the project cost
exceed approved funding; and
WHEREAS, the cost of the project came in over the amount originally
approved funding, and did not include the pricing for powder
coating; and
WHEREAS, TxDOT has supplied the City with a change order request
PCO#14 in the amount of $202,637.39 for powder coating.
NOW, THEREFORE, BE IT RESOLVED BY CITY COUNCIL OF THE CITY
OF COLLEYVILLE, TEXAS:
Sec. 1. THAT all of the above findings are found to be true and correct
and are incorporated herein by reference as if copied in their
entirety.
Sec. 2. THAT the City Council hereby acknowledges the change order
PCO#14 request submitted by TxDOT, attached at Exhibit A.
Sec. 3. THAT the City Council hereby authorizes the city manager to
execute final change order documents upon receipt, to be paid
in general conformance with change order PCO#14, in an
amount not to exceed $204,000.
AND IT IS SO RESOLVED.
Resolution R-17-4157
Page 2 of 2
PASSED BY A VOTE OF AYES, a NAYS, AND A ABSTENTIONS ON THIS
THE 18TH DAY OF JULY 2017.
Mayor Richard Newton Mayor Pro Tern Bobby Lindamood .c..
Place 1, Tammy Nakamura Ave, Place 3, Kathy Wheat
Place 4, George Dodson e.1"`' Place 5, Nancy Coplen
Place 6, Mike Taylor
ATTEST: OF COLLEYVILLE
• Amy. Shel •TMRC Richard Newton
City Secretary Mayor
Exhibit A
s- — JAGOE-PUBLIC CO.AW
Nb:\l.a.Lgl th P,t xI,,..Sc A ReadC4-ezr.19[r.
...Sicce t923._
rff
�nzu Fr.\\•brlh Ur P.O.Nor.251.1 l)cnton,TX 76202 tit air,+:19411?$2-2.551 Fa•. ( ')3g2-9732
6/28/2017
Contractor: Jagoe-Public Company Work Days Needed:
CSJ : 0363-01-139 Bid Number: PCO#14
Project: STP 2014(154)TE P.O.Number:
Highway: SH 26
County: Tarrant
CHANGE ORDER REQUEST FOR ADDITIONAL WORK
ITEM I DESCRIPTION QTY I UNIT I UNIT PRICE ITOTAL
Powder Coat PR1 Rail 2064 LF $24.66 $ 50,891.27
Powder Coat PR3 Rail 474 LF $22.89 $ 10,847.77
Powder Coat C402 Rail 450 LF $22.89 $ 10,298.52
Powder Coat Signals and Pedestrian Elements 1 LS $130,599.83 $ 130,599.83
0 $0.00 $ -
Total Change in Contract $ 202,637.39
Notes: State any specific notes here regarding this change order
Submitted by:
c4C �I
Chris Roberts - Project Manager
Accepted by:
Contractor ubUoCompony
/ Jagoe-Public
0363-01'139 Item 0
Project STP 2014(154)TE Description Powder Coat PR1 Rail
Highway SH 26 Unit LF
1 County Tarrant Quantity 2.064.0
Labor
Description Hours Hourly Rate Subtotal
Supervisor 0 $35.00 . $0.00
Equip. Operator Skilled 0 $23.25 $8.00
Equip. Operator (2) 0 $18.60 $0.00
Labor'Skilled (2) 0 $21.70 $0.00
Labor-Unskilled (2) 0 $15.50 $0.00
Flaggers (2) 0 $14.73 $0.00
$0.00
'
Subtotal $0.00
25% $0.00
.
55% $0.00
.
0 Total Labor Cost $0.00
Materials
Description Unit Quantity UndPhce Subtotal
. LF 2.064.0 G - $0.00
$ - $0.00
8 - $0.00
. $0.00
Subtotal $0.00
25% $0.00
'
Total Material Cost $0.00
Equipment
Description Hours Hourly Rate Subtotal
0 $30.00 $0.00
Pickup (1)
Saw 0 G15.00 $0.00
Skid Steer 0 G15.00 $U.OV ,
Paver 0 _ $40.00 $0.00
Roller Steel Wheel 0 $40.00 $0.00
Rcd\e[_Pnaumadc 0 $20.00 $0.00
�Heu|Tnuch 0 $75.00 $0.00
Roller Sheep's Foot S16.00 $0.00
Subtotal $0.00
15% $0.00
Total Equipment Cost $0.00
Subcontractor
Name Description Unit Quantity Unit Price Subtotal
d Coat LF 2O84O $23.25 $47Q8D
CT&S P� 1Roi| Pow Powder oa . � . .00
0 $0.00 $0.00
0 $0.00 $0.00
$0.00
' Subtotal $47.888.00
5% $2.399.40
Total Subcontractor Cost $50.387.40
-6%Overhead
96Overhead $O.DO
Bond Cost 1% $503.87 1.00%
Total Cost of Item $50.891.27
Unit Cosof Item $24.66
.
Contractor Jagoe-Public Company
CSJ 0363-01-139 Item 0
Project STP 2014(154)TE Description Powder Coat PR3 Rail
Highway SH 26 Unit LF
County Tarrant Quantity 474.0
Labor
Description Hours Hourly Rate Subtotal
Supervisor 0 $35.00 $0.00
Equip. Operator Skilled 0 $23.25 $0.00
Equip.Operator(2) 0 518.60 $0.00
Labor-Skilled(2) 0 $21.70 $0.00
Labor-Unskilled (2) 0 $15.50 $0.00
Flaggers(2) 0 $14.73 $0.00
$0.00
Subtotal $0.00
25% $0.00
55% $0.00
0 Total Labor Cost $0.00
Materials
Description Unit Quantity , Unit Price Subtotal
CY 0 S - $0.00
$ - $0.00
$ - $0.00
$0.00
Subtotal $0.00
25% $0.00
Total Material Cost $0.00
Equipment
Description Hours Hourly Rate Subtotal
Pickup(1) 0 S30.00 $0.00
Saw 0 $15.00 $0.00
Skid Steer 0 $15.00 $0.00
Paver 0 $40.00 $0.00
Roller Steel Wheel 0 $40.00 $0.00
Roller_Pneumatic 0 $20.00 $0.00
Haul Truck 0 $75.00 $0.00
Roller Sheep's Foot $15.00 $0.00
Subtotal $0.00
15% $0.00
Total Equipment Cost $0.00
Subcontractor
Name Description Unit Quantity Unit Price Subtotal
Ashlar PR3 Rail Powder Coat LF 474.0 $21.58 S10.228.92
0 $0.00 $0.00
0 $0.00 $0.00
$0.00
Subtotal $10,228.92
5% $511.45
Total Subcontractor Cost $10,740.37
6%Overhead $0.00
Bond Cost 1% $107.40 1.00%
Total Cost of Item $10,847.77
Unit Cost of Item $22.89
Contractor Jagoe-Public Company
CSJ 0363-01-139 Item 0
Project STP 2014(154)TE Description Powder Coat C402 Rail
Highway SH 26 Unit LF
County Tarrant Quantity 450.0
Labor
Description Hours Hourly Rate Subtotal
Supervisor 0 $35.00 $0.00
Equip.Operator Skilled 0 $23.25 $0.00
Equip.Operator(2) 0 $18.60 $0.00.
Labor-Skilled(2) 0 $21.70 $0.00
Labor-Unskilled (2) 0 $15.50 $0.00
Flaggers(2) 0 $14.73 $0.00
$0.00
Subtotal $0.00
25% $0.00
55% $0.00
0 Total Labor Cost $0.00
Materials
Description Unit Quantity Unit Price Subtotal
CY 0 S - $0.00
$ - $0.00
$ - $0.00
$0.00
Subtotal $0.00
25% $0.00
Total Material Cost $0.00
Equipment
Description Hours Hourly Rate Subtotal
Pickup(1) 0 $30.00 $0.00
Saw 0 $15.00 $0.00
Skid Steer 0 $15.00 $0.00
Paver 0 $40.00 $0.00
Roller Steel Wheel 0 $40.00 $0.00
Roller_Pneumatic 0 $20.00 $0.00
Haul Truck 0 $75.00 $0.00
Roller Sheep's Foot $15.00 $0.00
Subtotal $0.00
15% $0.00
Total Equipment Cost $0.00
Subcontractor
Name Description Unit Quantity Unit Price Subtotal
Ashlar C402 Rail Powder Coat LF 450.0 $21.58 $9,711.00
0 $0.00 $0.00
0 $0.00 $0.00
$0.00
Subtotal $9,711.00
5% $485.55
Total Subcontractor Cost $10,196.55
6%Overhead $0.00
Bond Cost 1% $101.97 1.00%
Total Cost of Item $10,298.52
Unit Cost of Item $22.89
i
Contractor Jagoe-Public Company
CSJ 0363-01-139 Item 0
Project STP 2014(154)TE Description Powder Coat Signals and Pedestrian Eleme
Highway SH 26 Unit LS
County Tarrant Quantity 1.0
Labor
Description Hours Hourly Rate Subtotal
Supervisor 0 335.00 $0.00
Equip. Operator Skilled 0 323.25 $0.00
Equip. Operator(2) 0 $18.60 $0.00
Labor-Skilled(2) 0 _ $21.70 $0.00
Labor-Unskilled (2) 0 $15.50 $0.00
Flaggers (2) 0 $14.73 $0.00
$0.00
Subtotal $0.00
25% $0.00
55% $0.00
0 Total Labor Cost $0.00
Materials
Description Unit Quantity Unit Price Subtotal
CY 0 $ - $0.00
$ - $0.00
$ - $0.00
$0.00
Subtotal $0.00
25% $0.00
Total Material Cost $0.00
Equipment
Description Hours Hourly Rate Subtotal
Pickup(1) 0 S30.00 $0.00
Saw • 0 $15.00 $0.00
Skid Steer 0 $15.00 $0.00
Paver 0 $40.00 $0.00
Roller Steel Wheel 0 340.00 $0.00
Roller_Pneumatic 0 $20.00 $0.00
Haul Truck 0 $75.00 $0.00
Roller Sheep's Foot $15.00 $0.00
Subtotal $0.00
15% $0.00
Total Equipment Cost $0.00
Subcontractor
Name Description Unit- Quantity Unit Price Subtotal
Roadway Solutions Traffic Signal Powder Coat LS 1.0 $123,149.30 $123,149.30
0 $0.00 $0.00
0 $0.00 $0.00
$0.00
Subtotal $123,149.30
5% $6,157.47
Total Subcontractor Cost $129,306.77
6%Overhead $0.00
Bond Cost 1% $1,293.07 1.00%
Total Cost of Item $130,599.83
Unit Cost of Item $130,599.83
Ashlar Contracting Company Request for C.O.
P.O. BOX 700 Number 1
BLUE RIDGE, TX 75424
Phone: 972 752 4000 Date: 4-25-17
Fax: 972 752 4002
PROJECT: HWY 26,0363 01 114
OWNER: TXDOT
CONTRACTOR: JAGOE-PUBLIC COMPANY
P.O.BOX 250
DENTON,TX 76202
ATTN: CHRIS ROBERTS
RE: ADD POWDER COAT FINISH TO C402 AND PR3 STEEL RAILING
POWDER COAT ADDED TO C402 RAIL 450 LF X$21.58 $9,711.00
POWDER COAT ADDED TO PR3 RAIL 474 LF X$21.58 $10,228.92
Subtotal $19,939.92
Overhead INCLUDED
Profit INCLUDED
Total $19,939.92
n-. _� _�,.:_:: ...�...:w.e c-. �'J'_^3r- - - cw--33°:.l.Y. - .l"d ^i.."iff� ''s^:,>•tr:u. a zYrr,:':: aria%':;-;:., "
:.an- i'sx:=`' .:i:_a .5... -<< tM. ..-,..4-�l: rYlae•..5 :..%hS,J.. y ;• _ `.c-Mi- iX�.�i`r a._.-.n... ..3
•..._.."?;.�..�....z.._.y, :,Z'., :2-vyi'a-::... ..,.._.i 3-�1�.F....._..}-,+.- ��.-�' �r'.5., r�....' .tea> __ nn_ •
} :u`:
- - >Hi^-•.c'.�.�` :�•�r __.... _._ z.... �n_. .�..,"{_-�spv�.nkv.+-
Submitted by: Larry Kennon Date:4-25-17
Engineer's Recommendation: Date:
Owner's Action: Date:
1."18
Etp04O
Construction - Metal Technology a Steel
Quality Metal Work
D/M/WBE
www.ctands.com
Brad Berland - Sales/Est
0: 972-554-9629 F: 972-438-9828 Cell: 972-890-6928
PROPOSAL # 1691
Date: 5/24/2016
Proposal For: SH 26 powdercoating
C.T. and S. Metalwork's. Proposes to furnish all Material, Shop Drawings and
Labor for the following:
1. Powder coating for PR1 railing
All powder coating will be a special 10 year warranty coating
Coating will match spec sheet and sample provided
$23.25/foot
Any and all grounding requirements are excluded
Materials for •ro'ect will be billed u s on :.urchase and .s a. ment shall be due ,ser
normal billing cycle
This is a steel bid only, any foundation or concrete work is excluded
All flagging and lane closures by others
All anchor bolts requiring to be poured in place will be by others
LrTis.. A
14,
``AM •1513 Maryland Drive • Irving,Texas 75061 • (972)554-9629 • Fax(972)438-9828 4-vt-,‘I's
Roadway Solutions, Inc. quote No. 6142017
1425 Crescent Drive.
' Carrollton, Texas 75006
972-245-2244 fax 972-245-2299
quote
Customer
Name Jagoe Public _ Date 6/14/2017
Address - Order No.
City State ZIP Rep Chris Roberts
Phone FOB
Qty Description Unit Price ; TOTAL
1 Powder Coating All Mast Arm Poles+ Hardware $98,374.30 $98,374.30
114 Powder Coating all 3,4 and 5 Section Signal Hardware $75.00 $8,550.00
8 Powder coating electrical service poles $850.00 $6,800.00
29 I Powder Coating Ped pole Assembly $325.00 $9,425.00
If City Approves Pedesl Service Rather than Service pole
There will not be any extra compensation for powder
coating the pedestal service Enclosures.
SubTotal $123,149.30
Payment Details Shipping& Handling $0.00
O Cash Taxes
• Check
O Credit Card TOTAL ( $123,149.30
Name
CC# Office Use Only
Expires
Note:Powder Coating will not be done on Camera,Radar detection
hardware or installation straps,
•
Your Business Is Greatly Appreciated.