HomeMy WebLinkAboutCity Council-Minutes-4/17/2017 City of Colleyville Page 1
City of Colleyville
City Council
Worksession Agenda
City Hall
100 Main Street
Colleyville, Texas 76034
817.503.1000
www.colleyville.com
Monday, April 17, 2017
6:00 p.m.
Executive Conference Room
Third Floor City Hall
1.CALL TO ORDER
2.PRESENTATION AND DISCUSSION
2a Presentation and discussion of the Glade Road Project
3.ADJOURNMENT
I hereby certify this agenda was posted on City Hall bulletin boards Thursday,
April 13, 2017 by 5:00 p.m.
Amy Shelley, TRMC
City Secretary
A quorum of any Colleyville board, commission, or committee may be
present at this meeting.
Any matter on this agenda may, at the discretion of the governing body, be
opened for public comment and discussion.
If you plan to attend this public meeting and have a disability that requires
special accommodations, please advise the City Secretary at least 48 hours in
advance at 817.503.1133, and reasonable accommodations will be made to assist
you.
City of Colleyville Page 1
City of Colleyville
City Council Worksession
Minutes
City Hall
100 Main Street
Colleyville, Texas 76034
817. 503.1000
www.colleyville.com
Monday, April 17, 2017
6:00 p.m.
Executive Conference Room
Third Floor – City Hall
Mayor Richard Newton called the Colleyville City Council Worksession to order on
April 17, at 6:00 p.m.
ROLL CALL: Mayor Richard Newton, and Councilmembers Tammy Nakamura,
Bobby Lindamood, Jody Short, Nancy Coplen and Mike Taylor
Absent: Mayor Pro Tem Chris Putnam
City Manager Jennifer Fadden, Assistant City Manager/Director of Public Safety
Mike Holder, Interim Assistant City Manager/Director of Economic Development
and Communications Mark Wood, Public Works Director Jeremy Hutt, and City
Secretary Amy Shelley
2. PRESENTATION AND DISCUSSION
2a Presentation and discussion of the Glade Road Project
Public Works Director Jeremy Hutt presented this item and answered questions of
the City Council. Chad Gartner, TranSystems, was also available to answer
questions of the City Council.
Councilmember Taylor asked staff if the contract is awarded in June, will they be
able to get much work completed during the summer, prior to school starting in
August. Director Hutt replied staff plans to have timelines as special provisions in
the bid document to allow for the school traffic.
Councilmember Lindamood asked staff about the start date, he believed it was
going to start in June rather than July. Director Hutt replied he is still pushing to
make this date, but it will depend on when the items fall into place with City
Council meeting dates.
Councilmember Taylor asked staff about the process. Director Hutt replied staff is
planning to award the contract at the first City Council meeting in June.
Mayor Newton stated we can call a special meeting to deal with the contract, if
necessary, rather than waiting for a regular meeting in order to save a week or
two.
Councilmember Lindamood asked staff if the work can begin as soon as the
contract is awarded. Director Hutt replied yes.
City Council Minutes April 17, 2017
City of Colleyville Page 2
Councilmember Nakamura asked staff when school starts. Director Hutt replied
August 21.
Mayor Newton asked staff how long it takes to finish, once started. Director Hutt
replied a lot of work for 1-A is for the bridge widening, and existing curb and
gutter work within the parkway, but the driving factor is associated with the
drainage culvert. Mr. Gartner added there may be some other work to be
completed after school has started, such as sidewalks. Councilmember Taylor
stated being concerned about the intersection at Bransford Road and Glade Road,
as things never go as planned.
Councilmember Coplen asked staff about the cost of the interim maintenance for
Glade Road, $142,000 or $198,000. Director Hutt replied he would provide the
numbers. City Manager Jennifer Fadden stated $198,000 has been allocated in
capital improvements for the roadway between Stafford Drive and Jim Mitchell
Trail.
Councilmember Lindamood asked staff if the section from Stafford Drive to Pool
Road (Phase 1-B) could be skipped in order to save money. Director Hutt replied
staff can look at working backwards.
Mayor Newton asked staff how much does that section cost. Director Hutt replied
$60,000, conservatively.
Councilmember Taylor suggested looking at where the delineation lines are so that
drainage and items are not placed in the ground, only to be dug up again. Mayor
Newton stated that the interim maintenance pavement will be replaced at final
construction, but this maintenance will provide a smooth surface for residents to
drive on now. The cost of the interim maintenance is a sunk cost the entire City
Council has already voted to do.
Mayor Newton asked staff if they are looking for direction to see if the City Council
is willing to invest $60,000 for interim maintenance (temporarily pave) for Phase
1-B (from the concrete to Bluebonnet Drive). Director Hutt replied yes.
Councilmember Coplen stated she would like to wait until the right-of-way has
been determined for this section.
Mayor Newton asked staff if Phase 1-B includes geography outside of the Phase 1-
B boundary. Director Hutt replied yes.
Mayor Newton asked Mr. Gartner why the boundary is defined like that. Mr.
Gartner replied the trunk line stops at the boundary limits shown today, and it is
split between the current ditches. He stated the design was created so that Phase
2 could follow closely with Phase 1 to extend the storm drain as part of Phase 2. It
may be necessary to extend the boundary of Phase 1-B to include the drain line.
City Council Minutes April 17, 2017
City of Colleyville Page 3
Mayor Newton stated the scope of Phase 1-B would then be changed. Mr. Gartner
agreed.
Councilmember Lindamood asked staff if there is already a contractor in place.
Director Hutt replied there is a contractor to use for the asphalt, interim
maintenance. The work between Bluebonnet Drive and Jackson Road/Pool Road is
scheduled for the end of the month.
Councilmember Taylor asked staff if this decision is going to be voted on. Director
Hutt replied this project is in the capital improvements plan. Councilmember
Taylor stated being concerned about the current bar ditches holding additional
water. Mayor Newton stated we are only talking about temporary pavement, which
will not increase the amount of water. The only temporary pavement is in Phase 2.
Mr. Gartner explained the following options:
• Base Option - Curb and gutters with turn lanes, trail on the north side and
sidewalk on the south
• Alternate Option 1 – Ribbon curb with roadside ditches and no turn lanes,
sidewalk on the north side from Montclair Street to Pool Road only, and a
trail on the south
• Alternate Option 2 – Alternate Option 1 with the addition of grate inlet
along with the roadside ditches (storm drainage), sidewalk on the north side
and trail on the south
• Alternate Option 3 – Alternate Option 2 with the addition of left turn lanes,
sidewalk on the north side and trail on the south
• Alternate Option 4 – is a combination two options. The Base Option for
Rose to Montclair and Alternate Option 3 for Montclair to Pool Road
• Alternate Option 5 – Pavement reclamation with the addition of ribbon
curbs and additional grading, limited pedestrian facilities (sidewalk from
Behrens Road to Behrens Court, this creates a continuous sidewalk on the
south side
• Alternate Option 6 – Pavement reclamation only, no additional pedestrian
facilities
Councilmember Coplen asked Mr. Gartner if there is a difference in the number of
left turn lanes within the options. Mr. Gartner replied Alternate Option 3 has one;
Alternate Option 4 includes same number from the Base Option; Alternate Option
1 and 2, there are no turn lanes; Alternate Option 3, has turn lanes at Behrens
and Chelsea, with none between to try to minimize the impact. Councilmember
City Council Minutes April 17, 2017
City of Colleyville Page 4
Lindamood asked Mr. Gartner to minimize the impact of what? Mr. Gartner replied
to minimize the width of the pavement.
Councilmember Nakamura asked Mr. Gartner about the total number of turn lanes.
Mr. Gartner replied nine.
Councilmember Coplen asked Mr. Gartner if both entrances to Cranbrook will have
turn lanes. Mr. Gartner replied no, just one, and used the exhibit to show how the
turn lanes work in this area.
Councilmember Lindamood asked Mr. Gartner about the curb in the Chelsea Park
area. Mr. Gartner replied the barrier curb provides the smallest footprint.
Councilmember Lindamood asked Mr. Gartner about the necessity for the trunk
line. Mr. Gartner replied the trunk line improves the current storm drain system to
meet the City code standards.
Councilmember Coplen asked Mr. Gartner if all options have a sidewalk on the
south side. Mr. Gartner replied yes. The Base Option and Option 4 have a sidewalk
on the north side.
Councilmember Lindamood asked Mr. Gartner about the difference from the east
side of Montclair Drive with the Base Option and Option 4. Mr. Garter replied the
Base Option is a barrier curb from beginning to end with enclosed, engineered
drainage.
Councilmember Lindamood asked Mr. Gartner about the curb with Option 4. Mr.
Gartner replied Option 4 is a ribbon curb.
Mayor Newton asked Mr. Gartner if he previously recommended Option 4. Mr.
Gartner replied correct.
Councilmember Lindamood asked Mr. Gartner if the sidewalk easement can be
moved to the north a little. Mr. Gartner replied it could be considered.
Councilmember Taylor asked Mr. Gartner if the Base Option is the most efficient,
least intrusive, tightest footprint, full drainage system, reconstruction. Mr. Gartner
replied yes.
Councilmember Coplen asked Mr. Gartner if the Base Option runs through Chelsea
Park, and then it goes to Option 3 from Montclair to Pool Road with Option 4. Mr.
Gartner replied correct, but Montclair to Jim Mitchell.
Councilmember Taylor asked Mr. Gartner about the reduction in the trail width.
Mr. Gartner replied on the south side, from beginning to the end, the trail has
City Council Minutes April 17, 2017
City of Colleyville Page 5
been reduced from 10 foot to 8 foot, and that is continued to the west end of
Phase 2 to the east end.
Councilmember Taylor asked Mr. Gartner about right-of-way impacts within the
tightest part of the roadway. Mr. Gartner replied there are no right-of-way
impacts.
Councilmember Lindamood asked Mayor Newton about the difference in the pricing
between the Base Option and Option 4. Mayor Newton replied Option 4 is
$300,000 less. Mr. Gartner added the ribbon curb is cheaper than barrier curb.
Councilmember Taylor asked Mr. Gartner if this was a best guess based on market
pricing. Mr. Gartner replied yes, based on recent bids of similar items.
Councilmember Nakamura asked Mr. Garter if Phase 2 is the most expensive
phase. Mr. Gartner replied he believes so.
Councilmember Lindamood asked Mr. Gartner if the sidewalk will be over the ditch
from Camelot to Chelsea, going west. Mr. Gartner replied yes.
Councilmember Lindamood suggested doing everything necessary to save trees.
Councilmember Taylor suggested the planting of additional trees, where property
owners will let us.
Mayor Newton stated he would like the number of trees impacted to be reduced
with Option 4.
Councilmember Taylor stated being in favor of the Base Option with a modified
trail.
Councilmember Short stated being in favor of the Base Option or Option 4.
Councilmembers Nakamura, Lindamood, and Coplen stated being in favor of
Option 4.
Mayor Newton asked Mr. Gartner for clarification of expanding Phase 1-B to
Montclair. Mr. Gartner replied the expansion would include Bedford Road to Beldon
Trail, as a single package. Mayor Newton asked about the benefit. Mr. Gartner
replied building the entire trunk line will mitigate any drainage issues introduced
with the new construction.
Mr. Gartner suggested releasing the new design for Phase 2, with Option 4, and
begin the utility coordination, as this portion will not hold up Phase 1-B. He stated
the utilities in this area are unknown.
City Council Minutes April 17, 2017
City of Colleyville Page 6
Mayor Newton stated he will do some internal processing to be sure to better
understand this.
Mayor Newton summarized the meeting: Phase 1-A construction will start this
summer, with the difficult part being completed before school begins in the fall;
Phase 1-B, right-of-way acquisition is underway, but yet to be completed; Phase
2, everyone is in a general agreement with Option 4; suggested extending Phase
1-B into Phase 2; with Option 4, save as many trees as possible, and Mayor
Newton stated he wants a clear accounting of the TIF.
Director Hutt stated staff will bring forward a contract amendment for
TranSystems, given the design changes to the scope. Mayor Newton stated he
wants to see what has been spent, and where it has been spent, on the project so
far.
3. ADJOURNMENT
There being no further business before the City Council, Mayor Newton adjourned
the worksession at 8:00 p.m.
APPROVED BY A VOTE OF 7 AYES, 0 NAYS, AND 0 ABSTENTIONS ON THIS THE
2ND DAY OF MAY 2017.
Minutes taken and prepared by:
Amy Shelley, TRMC
City Secretary