HomeMy WebLinkAboutColleyville Sidewalks Committee-Minutes-9/25/2007GItY o!
COLLEYVILLE TRAILS AND SIDEWALKS COMMITTEE
® MEETING MINUTES -September 25, 2007
Y'ca..
CALL TO ORDER The meeting was called to order at 3:05 p.m.
ROLL CALL Present: Gail Manion, Deena Dendy, Odilon Alvarado,
David Klenzendorf, Jack Olsen, Judy Atwood, and
Councilmember Liaison Tony Licata; Visitors: Charles
Bethards - Kingswood HOA, Mike Matton -Kingwood
HOA, and Alan Chernoff -Tiffany Park HOA
Staff Present: Steve Chutchian, Jeremy Hutt, Matt
McCombs and Kathy Moore
APPROVAL OF MINUTES
Gail Manion requested that Nancy Jane Langford be added to the attendance; verbiage
was added to Agenda Item 4 concerning the 2008 Projects to be considered. Judy
Atwood requested that her request for information concerning a sidewalk trail along
Glade Road be added to Agenda item 2. Also, a spelling correction was made. Judy
Atwood made a motion to accept the minutes with changes, and Jack Olsen seconded
the motion.
AGENDA ITEMS
1. Update on the 2007 Sidewalk Improvements
Steve Chutchian gave an update on the 2007 Sidewalk Improvements. There are
concerns on a few of the locations, one being the sidewalk on the west side of Pleasant
Run Road at Beverly Drive down to Bogart Drive; this was not originally scheduled to be
in place by the time school started, however the contractor worked to get it completed
by the school opening date of August 27. The design plan for the crossing where the
handicap ramp is called for an L-shaped section of sidewalk at the intersection so that
the kids could come up the sidewalk to the crosswalk. We were able to expanded the
landing area and add several additional feet of sidewalk up Beverly Drive.
The second location is a crosswalk at Shelton Road and Pleasant Run Road, which was
constructed as the Committee requested. However, when we got across to the east
side of Pleasant Run Road, we had to add a couple of culverts into the ditch and
created a landing on the east side of the ditch. Another problem encountered was that
once the kids reached that point there are no sidewalks on that side of the street for
Colleyville Trails and Sidewalks Committee
Minufes -September 25, 2007
them to continue on to where the School's walk picks up; there is a trail planned in the
future, but at this time there is no funding. Staff decided to use City Street Personnel to
install a temporary sidewalk that connects the landing to the School District's walk.
The third location was a sidewalk at Waller Lane and Cooks Lane which was designed
to go all the way around the outer part of the turn at Cooks and Waller; however, we
discovered that we did not have enough right-0f-way to build it as designed. We had to
do a crosswalk at two locations, one is where the two streets come together and the
other is at the location where you end it and you cross over into the walk that goes into
the elementary school. We did talk with the Police Department on these modifications.
We still have to complete the striping, but we anticipate that to be finished within the
next few days.
The fourth recommendation by the Committee was that if we had any money left over to
use it on Tinker Road, which was an added alternate. However, this altemate was way
over any unused funds. If the Committee still wants to consider doing Tinker Road, you
may want to look at that for the future budget year. Steve Chutchian made the
recommendation that if the Committee is considering changes to the 2008 budget;
those changes need to be submitted to Council as soon as possible, so that
construction can get underway earlier in the 2008 budget year.
Gail Manion stated that the Cooks Lane Project was not what the Committee was
hoping for; their hope was to eliminate the need for the kids to have to cross the street.
She questioned if there was any prospect in the future to correct this and if the property
owner was approached about granting an easement. Steve Chutchian stated that the
property owner was not approached concerning the easement.
Steve Chutchian reminded the Committee that the City is currently under design for the
widening of Bogart Drive, and when construction begins on this project in the Spring of
2008, it will include afull-width trail on the east side of Pleasant Run Road from Bogart
Drive up to where it end at the school's property. Additionally, we will be putting a
sidewalk in from that same intersection at Pleasant Run Road and Bogart Drive along
the north side of Bogart Drive down to Hall-Johnson Road. This will help completed that
section. That project will most likely run through late Fall of 2008.
Z. Update and Discussion of Sidewalk Priority Rankings
Matt McCombs passed out box maps to all Committee members; the box map includes
current sidewalk and trail locations, along with purposed locations. Matt McCombs
stated that at the last meeting there was discussion on what projects the Committee
wanted to look at doing in the long term. Staff has prepared what would be some good
criteria for measuring the need for a sidewalk at any given location. In the agenda
packet, the Committee was given a °Sidewalk Prioritization Worksheet" which is the bulk
of the criteria that we will be looking at. Each criterion is assigned a point value and that
is totaled on the second sheet, in addition there are five tie-breakers in the event of a
tie. What this is aimed at doing is making sure that we have an active inventory of
every potential sidewalk in Colleyville. Matt wanted to bring this worksheet to the
Committee to make sure to get everyone's input, once we have a worksheet that
Colleyville Trails and Sidewalks Committee
Minutes -September 25, 2007
everyone agrees is a good standard, we will then go back to the box map and divide up
the boxes, there are 51 boxes, when divided between the Committee and Matt each
person will be responsible for approximately 6 boxes. Everyone will take a section and
go out and use the worksheet to measure each project. Judy Atwood suggested that a
trial run with some of their existing priorities be used to see how they will rank, and if the
point values actually push where they want to push. Councilman Licata suggested that
priority/public benefit of the sidewalk and the difficulty of the sidewalk should be two
different measures. He also agrees that the Committee needs to do a trial run and work
with this tool and look at some of the results to see if it will accomplish what the
Committee is aiming for. This will help to figure out where the worksheet needs some
tweaking to make it a workable tool. This will enable the Committee to use it as
justification for future decisions.
Discussion continued concerning the "Sidewalk Prioritization Worksheet" and how it will
work and possible modifications that will need to be made. It was agreed that this will
be a good process and it will bring forward the hidden needs that often get overlooked.
Gail Manion also pointed out that during the ranking process, if they find incorrect
information on the box map, it should be noted whereas that information can be updated
at the same time. The purpose is to take a new look at the entire City, which will enable
the Committee to better serve the community. Gail Manion asked if the Committee was
willing to do a trial run, taking one box each to see how well the tool works. Odilon
Alvarado made a motion that the Committee members each take one box and Matt will
update the worksheet that will be used for their trial run. They also agreed that they will
meet in one month to have a work session to review their findings and determine how
well the process works in identifying the needs of the City. Deena Dendy seconded the
motion, the vote was unanimous.
Councilman Licata gave a brief overview of some possible funding through the
Colleyville Economic Development Corporation (CEDC) budget, which is tied to a half-
cent sales tax dedication which includes things such as parks and recreation...which
includes trails. There is a long-term five year plan that comes from the trail plan. This
year there is $170,000 dedicated to the L.D. Lockett Trail connector which is supposed
to connect the L.D. Lockett Trail to the Webb House. Also projected in two years is an
amount of $500,000 for a segment of trail along Pleasant Run Road. Councilman
Licata would like the Committee to look at changing the timing of the two trails and
move the Pleasant Run Road Trail ahead of the L.D. Lockett Trail.
Gail Manion asked to entertain a motion to reiterate the priority of the Pleasant Run Trail
north of the school to Tinker Road over the section south of the school and over the
Webb Crossing; she also requested that the Engineering Department look at that
section again and give updated estimates. Jack Olsen moved to make the motion and
David Klenzendorf seconded the motion, the vote was unanimous. Noting that this will
be contingent on the Safe Route to School Grant, but it will be useful information to
know how far the money will go. Matt stated that we could possibly know something on
the grant by the scheduled work session on the October 30.
Colleyville Trails and Sidewalks Committee
Minutes -September 25, 2007
3. Update of the Sidewalk Escrow Process
Matt McCombs gave a brief update on the Sidewalk Escrow Process. Staff has
currently implemented an Engineering Practice of building sidewalk instead of
escrowing funds for future sidewalks. Staff feels that the Land Development Code
supports this process. There are a few developments that are already in the final
stages of completion, which have already been granted; but all other existing
developments will move forward with the building of sidewalks. Judy Atwood
questioned the status of the escowed funds on two Glade Road houses.
4. Consideration of a Sidewalk Proposal from Kingswood Estates
Mr. Charles Bethards who is on the Board of Directors for the Kingswood Homeowners
Association spoke on behalf of the Kingwoods HOA. Their problem is a 70' gap of
sidewalk along the south side of Kingswood Lane where it approaches Riverwalk Drive.
Their request is to have this section of sidewalk included in the FY08 sidewalk list of
projects for consideration. Mr. Bethards stated that since the development at Market
Street the traffic along Riverwalk Drive has dramatically increased, along with
pedestrian traffic, which increases the need for this section of sidewalk. They feel that
this section of sidewalk should have been put in with the construction of Riverwalk
Drive, which would have closed the missing section. The estimated cost is $1500.
Gail Manion stated that the Committee was not yet at the point of determining what their
priority projects will be for the upcoming year, but they would certainly add this to their
projects to consider. The Committee should have their priority projects determined by
January 2008.
5. Consideration of a Sidewalk Proposal from Tiffany Park
Mr. Alan Chernoff who is the Vice-President of the Tiffany Park Homeowners
Association spoke on their behalf. Their request is that the Committee considers the
construction of a missing section of sidewalk along Brown Trail, behind the Walgreens.
The property is owned by the Colleyville Assembly of God Church and they are in
support of having this sidewalk connection. The sidewalk section is approximately 100'
long and would require no additional drainage improvements. This improvement would
benefit several subdivisions and citizens within the City. The preliminary cost estimate
was $1500 to $2000, based on the footage.
Gail stated that the Committee would add this request to the list of projects to consider
in FY08.
6. Suggestions for future Agenda Items
Gail would like to add as a future agenda item, the sidewalks around the school; she
feels that since school has started they need to re-look at the school, and review their
priority list.
Colleyville Trails and Sidewalks Committee
Minutes -September 25, 2007
STAFF REPORTS
The committee set a work session for Tuesday, October 30, 2007 at 4:00 p.m. and a
regular quarterly meeting for Tuesday, December 11, 2007 at 3:00 p.m.
CITIZEN COMMENTS
There were no Citizen comments.
ADJOURNMENT
The meeting adjourned at 4:57 p.m.
Respectfully Submitted,
~•
Kathy E. oore
Administrative Assistant
Approved on: December 11, 2007
Colleyville Trails and Sidewalks Committee