COLLEYVILLE SIDEWALK COMMITTEE
MEETING MINUTES - October 5, 2006
CALL TO ORDER
The meeting was called to order at 2:06 p.m.
ROLL CALL
Present: Gail Manion, Nancy Jane Langford, Judy
Atwood, Jack Olsen and Councilmember Liaison
Tony Licata
Staff: Steve Chutchian, Barry LeBaron, Chad Bartee,
Kathy Moore, Carter Sieber and Dal Anderson from
staff were present.
APPROVAL OF MINUTES
Chairperson Gail Manion requested a deletion from the August 1, 2005 minutes
referencing a bridge donation for Jackson Road. Also, a typo of the word "the" should
have been "they". Gail Manion moved to approve the minutes as amended.
AGENDA ITEMS
1. Report of the FY06 Sidewalk Budget Expenditures
Chad Bartee, City Engineer gave a presentation I overview of the FY06 expenditures.
There were two projects identified from the five year CIP Plan for FY06. The first being
John McCain Trail and a sidewalk along Bedford Road from Plantation Drive to Scarlet
Court. Both projects were completed and expended the funds for FY06.
Gail Manion questioned the sidewalk on Scarlet Court. Chad Bartee said it was part of
the Five Year CIP Plan. There was a question as to the actual cost of the projects.
Bedford Road was budgeted at $14,000 with total expenditures at $14,800. John
McCain Trail was budgeted at $9,000 with total expenditures at $19,718. There was
$9,000 identified for the Castleton Trail from FY06 budget, but it was absorbed by the
John McCain Trail. Bids on the Castleton Trail came in low, so no funds for FY07 will
be needed for this project.
There was discussion on the Castleton Trail location and construction, and the time
frame of completion.
2. Review of the GCISD Plans for the New Colleyville Elementary
School located on Pleasant Run Road
There was discussion of the new Colleyville Elementary School's impact on traffic off of
Pleasant Run Road. Gail Manion went to the school district and visited with Scott
Monahan and reviewed their plans. She stated that the school was told about the trail
they need to build and that it was in their plans. However, they were not told about the
access that comes off of Cooks Lane, which is on the Trail Plan, she pointed this out to
them and they will try to incorporate it into their plans. She felt that they were not given
Colleyville Sidewalk Committee
Minutes - October 5, 2006
a lot of impute by the City, and were only looking at their property. The school will take
information back to their Architect to see if they can connect to the middle school and
the elementary school.
Judy Atwood wants to make sure that there is a way for the kids to walk back and forth
between the two campuses.
Carter Sieber gave a presentation of pedestrian count (school kid's walking) to the
committee. He went out to intersection of Hall Johnson and Bogart and counted the
kids walking, also talked to the crossing guard. Went in the afternoon and morning,
found that more kids walked in the afternoon then in the morning. Also, found that most
of the foot traffic was along Bogart, but many kids cut across Hall Johnson to be picked
up by parents.
Committee member were given handouts that gave a breakdown of Carter's research.
Gail Manion reminded the committee that in 2002 they did surveys with the schools
asking if sidewalks were provided would you let your child walk to school, 57% said yes
in elementary schools and 51 % said yes in the middle schools.
Gail Manion read the Sidewalk Ordinance from 1990 concerning where sidewalks are
required.
Councilman Licata recommended figuring out what's needed and prioritize. To have
focused objective to help make things happen.
Steve Chutchian spoke about possibly sending out a questionnaire or having another
survey professionally done. Discussion continued on what questions might be asked as
part of a survey, and how it would be performed. Gail Manion was not sure that another
survey is a priority at this time. Councilman Licata feels this can only make the
Committee's case stronger.
Gail Manion brought to the Committee's attention project # 7, in the Trail Plan, called
"The School Yard Path" which connects the two schools. The school district was
unaware of the plan. Gail Manion asked to amended the Trail Plan to say the school
yard path does not need to go all the way to SH26, but it does need to connect the two
schools and we need to inform the school district about this. Steve Chutchian informed
the committee that we can only amend the Trail Plan to relocate the school yard path
around the school not through the school property. The committee could send a letter
recommending the connect through the school property; however the City cannot force
the school district to do that.
Discussion continued on where and what part of the trail the school is putting in. Also,
the City will be starting the Pleasant Run Trail Project which we will pick-up where the
school district leaves off.
Gail Manion strongly recommends that we have sidewalks on both sides of Bogart.
There was more discussion of where crossings and crossing guards will be, and where
the radar speed signs will be located.
Judy Atwood stated that there needs to be a match between what we are doing and
what the school is doing. This needs to be discussed between the two immediately.
Colleyville Sidewalk Committee
Minutes - October 5, 2006
Councilman Licata suggests that we have a joint planning session between committee
members, city staff, and school district. We need to point out what exist and what's
missing and what might be able to be adjusted.
Possible Sidewalk Priorities:
1 . The east side of Waller Lane to the north side of Cooks Lane to the school yard
short cut.
2. Pleasant Run Road going north from the school boundary to Tinker Road, east
side of trail.
3. Along Tinker Road between Emerald and Pleasant Run Road on the north side.
4. Both side of Beverly and Shelton Road-due to traffic pattern changes.
5. North side of Bogart-check school plans.
6. Colleyville Terrace to Central on the west side, connecting the existing sidewalks.
Steve Chutchian suggests that once a priority list is established, staff can attach cost to
priorities.
3. Purposed FY07 Sidewalk Budget
Steve Chutchian informed committee that $35,000 was approved for the FY07 budget.
4. Discussion of the Long Term Plans for the New Colleyville
Senior Center
Steve Chutchian informed committee that the Senior Center modifications were
complete and'the center would be opening soon. The Trail/Bridge Project went out for
bids, but all bids far exceed the engineering estimates, therefore all bids were rejected.
Staff will redesign the trail without the bridge and this project will be bid at a later date.
STAFF REPORTS
Committee did not schedule another meeting at this time.
CITIZEN/COMMITTEE MEMBER COMMENTS
There were no further comments.
ADJOURNMENT
The meeting adjourned at 3:53 p.m.
Respectfully Submitted,
~~€,7t~
Kathy E. Moore
Administrative Assistant
Approved on: November 6, 2006
Colleyville Sidewalk Committee