HomeMy WebLinkAboutE-News-City Publications-7/24/20151
GENERAL
CASH MOB AT MENCHIE'S ON JULY 28
Join the Mob at Menchie's Frozen Yogurt on
Tuesday, July 28. Fill your cup as full as you can
get it with frozen yogurt and as many toppings as
you like for only $4 from 12:30 to 1:30 p.m.
Menchie's Frozen Yogurt is located at 4709
Colleyville Blvd., in the Colleyville Downs shopping
center. Join us, bring a friend, and meet some
new friends at the Mob. Cash Mobs are open to
the general public. See you there!
GLADE ROAD PROJECT WORKSESSION - TUESDAY, JULY 28
The Colleyville City Council will hold a worksession on the Glade Road Project on
Tuesday, July 28, at 6:00 p.m., in the Executive Conference Room on the third floor
of Colleyville City Hall. At the City Council meeting on June 2, the City Council
gave staff approval to move forward on the design of the first phase. Get the
details.
2
READ TO THE RHYTHM SUMMER READING GRAND FINALE -
FRIDAY, JULY 31
Celebrate an amazing summer at the outdoor Summer Reading
Grand Finale! There will be a live deejay, children's crafts, face
painting, balloon artist, carnival games and prizes, petting zoo
and pony rides, inflatable rides, and Texas Star Express train
rides. It all happens in the green space in front of the Colleyville
Public Library at 110 Main Street on Friday, July 31, from 5:30 to
8:30 in the evening. Games and activities are free; concessions
are available. All ages are welcome and no registration is
required. For details, call 817.503.1154.
UPDATE ON ROAD CONSTRUCTION & CITY PROJECTS
TxDOT SH 26 RECONSTRUCTION PROJECT
Please send any questions, concerns, or
comments to 26@colleyville.com.
All main lane paving is complete. TxDOT's
contractor is scheduled to begin landscaping
and permanent striping the week of July 27, as
well as construction of the Cotton Belt Trail.
There will be intermittent lane closures during
the coming weeks, while this work is being
done. TxDOT reports that all remaining work,
including the medians and parkway behind the
curb, is scheduled to be completed by the end of August.
Cotton Belt Trail
(Note in the July 17 E-News, the initial section of the trail was reported as complete.
That information was not accurate. We apologize for the confusion.) The Cotton Belt
Trail linking Colleyville to Grapevine will be constructed on the north side of SH 26
(nearest to the railroad tracks). The trail will vary in width from 14 feet on the bridge to
between 8 and 10 feet on the approaches to the bridge. Once TxDOT's portion of the
Cotton Belt Trail, between the Colleyville entry sign and the Pool Road/Brumlow Avenue
intersection, is complete, the city will finish the connection to the trail west of the
railroad tracks. Work on that connection is planned for September, depending on
completion of TxDOT's portion of the trail construction.
SH 26 UTILITY RELOCATION PROJECT (City of
Colleyville/Utility Franchises)
Please send any questions, concerns, or
comments to 26@colleyville.com.
All of the city's new water and sewer infrastructure
is on track to be completed by the end of summer,
and Atmos and Time Warner should complete their
relocation work at about the same time. AT&T
expects to finish late this winter.
On the west side of SH 26, from Village Lane south to
Glade Road, the new water line is in. This will complete
the water line placement for this project. Tie-ins from
3
businesses to the new line will be done during overnight hours to minimize
disruption to businesses and drivers. No lane closures are expected.
The contractor has now moved the southern section of SH 26 to bore for a
sanitary sewer line. Once this is complete, services will be tied in and the
water/sewer relocations will be complete.
AT&T crews will be placing a new duct bank on the east side of SH 26 from
Professional Court to Thompson Terrace; they'll also be pouring new telephone
manholes. No lane closures are expected.
Atmoswill be boring a new gas main from Centerpark to Brown Trail. They'll also be
doing tie-ins from Centerpark to Church Street. No lane closures are expected.
Time Warnerwill be doing aerial work in various locations and boring on the west side
of SH 26 from John McCain Road to Tennison Parkway. Verizon will be boring in
the same area, No lane closures are expected.
SOUTH WHITE CHAPEL BOULEVARD RECONSTRUCTION
Construction continues on South White Chapel Boulevard, from the Colleyville border to
West Continental Boulevard. Construction hours are 8:00 a.m. to 4:00 p.m., Monday
through Friday. During those hours, the road will be reduced to one lane. Delays
should be expected. Construction should be complete by mid-August.
PONDEROSA LANE/KINGSTON ADDITION
IMPROVEMENTS
Ponderosa Street, Kingston Drive, and McCain Lane have
now been paved. Manholes and water pads will be placed
next week.
PLEASANT RUN ROAD PROJECT
Pleasant Run Road will be reduced to
one lane from 7:00 a.m. to 6:00 p.m.
in some areas, so expect delays. The
contractor will be backfilling curb and
gutter from Bogart Drive to Church Street,
and from Mission Lane to Church Street
and lowering manholes. Once curb and
gutter is in place on both sides of the road,
the contractor will start on driveways. All
affected residents will be notified.
Residents on Pleasant Run Road, from
Bogart Drive to Colleyville Terrace, as well
as the residents in Laurel Oaks, will still be
able to access Pleasant Run Road, but it will be limited to one lane. The same is
expected from Colleyville Terrace to Church Street.
Pleasant Run Road is closed from Mission Lane to Church Street and from Bogart Drive
to Church Street.Entry and exit for residents, as well as all service and emergency
vehicles will be from Church Street. All others should plan to use alternate routes: SH
4
26 to Hall-Johnson Road then to Bogart Drive or SH 26 to Church Street, then west to
Bransford Road or SH 26.
WATER FACILITY RENEWAL
Area 1
Permanent trench repair and curb repair is being done on
Overland Trail and Frontier Court. These roads will be
reduced to one lane in some places at various
times.
Area 2
The contractor will be performing permanent trench repair on Reagan Road, but the
road will remain open. The road will be reduced to one lane in some places at
various times.