1. CALL TO ORDER
2. PRESENTATION AND DISCUSSION
2a Update on SH26/Colleyville Boulevard Reconstruction Project
3. EXECUTIVE SESSION - In accordance with Texas Government Code
Chapter 551, Subchapter D
Section 551.087 - Economic Development - discuss or deliberate regarding
commercial or financial information that the City has received from business
prospects that the City seeks to have locate, stay, or expand in the City and with
which the City is conducting economic development negotiations; deliberate the
offer of a financial or other incentive to a business prospect
4. ADJOURNMENT
I hereby certify this agenda was posted on City Hall bulletin boards Friday, October 24,
2014 by 5:00 p.m.
Amy Shelley, TRMC
City Secretary
Any matter on this agenda may, at the discretion of the governing body, be opened for
public comment and discussion.
If you plan to attend this public meeting and have a disability that requires special
accommodations, please advise the City Secretary at least 48 hours in advance at
817.503.1133, and reasonable accommodations will be made to assist you.
City of Colleyville Page 1
City of Colleyville
Colleyville City Council
Worksession
Agenda Briefing
City Hall
100 Main Street
Colleyville, Texas 76034
www.colleyville.com
Agenda Number 2a Agenda Date 10/28/2014 Number
Type Presentation and Discussion
Department Public Works
Title
Update on SH26/Colleyville Boulevard Reconstruction Project
Explanation
The purpose of this meeting is threefold:
1.To update the City Council on the current status of Phase I of the SH26
reconstruction project from the Pool/Brumlow intersection to John McCain Road;
2.To present to the City Council the strategy and time line for completion of the
remaining section of SH26 from John McCain Road to Brown Trail; and
3.To get direction from the City Council on how to proceed with funding the section
from John McCain to Hall-Johnson, including a discussion of using the TxDOT
"Pass-Through" option as a funding mechanism.
Brian Barth, the Fort Worth District Engineer for TxDOT, will provide the update on
Phase I and the strategy for completing the remainder of the project. City staff will
provide information on current traffic counts and projections of future traffic counts, as
well as funding options for completing the project through the remainder of the
corridor from John McCain to Brown Trail.
Councilmembers Mogged and Short requested a traffic capacity analysis on SH26. Staff
requested it from the North Central Texas Council of Governments (NCTCOG).
However, NCTCOG wasn’t able to respond until late on the evening of Wednesday, Oct.
22. Once received, the information was sent to Kimley-Horn, a third-party traffic
engineering consultant, for review before the presentation to the City Council;
however, Kimley-Horn was not able to complete their analysis in time to include in the
worksession packet. The presentation will be updated with Kimley-Horn’s analysis prior
to the worksession.
Attachments
1.SH26/Colleyville Boulevard Project Update
2.TxDOT SH26 Presentation
SH26/Colleyville Boulevard
Project Update
City Council Worksession
October 28, 2014
Purpose
The purpose of this meeting is threefold:
•To update the City Council on the current status of Phase I of the SH26
reconstruction project from the Pool/Brumlow intersection to John
McCain Road
•To present to the City Council the strategy and timeline for completion
of the remaining section of SH26 from John McCain Road to Brown
Trail
•To get direction from the City Council on how to proceed with funding
the section from John McCain to Hall-Johnson, including a discussion of
using the TxDOT “pass-through" option as a funding mechanism
Overview
•History of the project
•Phase I Update (Pool/Brumlow intersection to John McCain
Road) -Presentation by Brian Barth, TxDOT
•Phase II Update (John McCain to Brown Trail) -Presentation
by Brian Barth, TxDOT
•Proposed pass through agreement
•Other options for completing the project
•Communications plan
•Questions, discussion, and City Council direction
Project History
•1994 -First discussions of improving SH26
•1999 -Colleyville selected for funding
•December 2001 –SH26 Advisory Committee established
•February 2002 –Preliminary design presented by Teague, Nall,
& Perkins, Inc.
•June 2002 –SH26 Business Alliance presentation
•November 2002 –Discussion of public information program
•March –June 2003 –Discussions on landscaping, utility
relocations, and enhancements
•January 2004 –Meeting with TxDOT to discuss project scope
and issues
•November 2004 –Joint City Council and SH26 Advisory
Committee meeting; discussion of underground power lines and
financing thereof
•2005 –TxDOT received environmental clearance for project
Project History
•August 2005 –Joint meeting of City Council, SH26 Advisory
Committee, and Traffic Safety Advisory Committee
•April 2008 –Overview of planned improvements by design
consultant
•October 2009 –Joint City Council and P&Z meeting to discuss
SH26 redevelopment study and overlay district
•2010 –Section from Pool/Brumlow to John McCain split out to be
bid first
•April 2010 –Discussion of pass-through financing with TxDOT;
agreement with Gateway Planning Group to prepare application
for pass-through financing from Hall-Johnson to Cheek-Sparger
•April 2011 –Approved an interlocal agreement between TxDOT,
NCTCOG, Tarrant County, and the City regarding funding for Phase
I from the Pool/Brumlow intersection to John McCain Road
•May 2011 –City began relocating water and sewer lines for
Phase I
Project History
•August 2011 –TxDOT opened bids for Phase I
•October 2011 -2013 Transportation Improvement Program (TIP)
Modification
–Shifted funding from John McCain to Hall-Johnson section to Hall-
Johnson to Brown Trail section
–Changed scope from six lanes to four lanes with intersections built to
six lane capacity
•July 2012 –Contractor (AUI) began work on Phase I
•April 2013 –City awarded contract to relocate water and sewer
lines from John McCain Road to Centerpark
•May 2014 –City awarded contract to complete water and sewer
line relocations from Hall-Johnson to Brown Trail
Phase I and Phase II Update
Presentation by Brian Barth,
Fort Worth District Engineer
TxDOT
Pass-Through Proposal
The scope and limits of the pass-through project
are to reconstruct 2.4 miles of SH26 between Hall-
Johnson Road and John McCain Road from an
asphalt roadway section to a four-lane divided
urban arterial roadway with concrete pavement and
the ability to widen to six-lanes in the future, if
traffic counts warrant such a widening. The work
also includes improving the intersection at Tinker
Road and Oak Point Drive.
Proposed Pass Through Terms
•The City will be responsible for any municipal utility relocations. TxDOT
will let the project and manage construction.
•TxDOT will be responsible for completing the design (plans, specifications,
estimate), the right-of-way acquisitions, and the oversight of any franchise
utility relocations. The environmental documents for the ultimate project
design have already been completed by TxDOT. Should there be required
revisions, TxDOT will resolve them.
•The estimated construction cost is $10,900,000 (+/-10%)
•+10% cost = $12.0 million
•The tentative negotiated terms are outlined below for the pass-through
agreement:
–The total reimbursement for the construction of the project will be
$8,720,000
–The per-vehicle-mile reimbursement rate will be $0.034 per vehicle-
mile
–The minimum annual reimbursement for the project, once it is opened
to traffic, will be $436,000
–The maximum annual reimbursement for the project, once it is opened
to traffic, will be $872,000
Pass-Through Costs
•Cost of Phase III (John McCain to Hall-Johnson)
–$12.0 million (estimated construction cost of $10.9
million + 10%)
•Funding
–$3.22 million TIF cash (1998 TIF Project Plan)
–$1.0 million from Tarrant County
–$9.4 million debt issuance
•Reimbursement (80%)
–$9.60 million ($8.72 million + 10%)
•Cost of Debt
–$3.26 million
•Net cost to City
–$5.66 million plus enhancement costs of $ 1.4 million
Another Funding Option
•TxDOT funds the entire reconstruction of SH26
from John McCain Road to Brown Trail
•Road is reconstructed with a divided median, per
TxDOT design criteria for urban arterials
•On completion of reconstruction, City assumes
ownership of the SH26
•In addition to the cost of amenities (cross walks,
street name signs, street lighting, and
landscaping) the City would assume road and
signal maintenance costs
Advantages and Disadvantages
of another funding option
Advantages
•Complete Control
–Speed limits
–Driveway cuts
–Signage
–Street lighting
–Location of new traffic
signals
Disadvantages
•Cost of Ownership
–Traffic signals
–Pavement markings
–Pavement maintenance
and repair
•Any future reconstruction
would be the responsibility
of the City
Estimated Costs of Ownership
•Signal maintenance
–9 Signals @ $9,831/year = $88,479
•Pavement markings
–$120,000 every 5-7 years based on wear
•Pavement maintenance and repairs
–Increases over time; difficult to estimate
•Possible addition of two more lanes at a
future date
Communications Plan
Inform and educate business and citizen stakeholders about the SH26 Reconstruction
Project, including construction updates and alerts, by using all communication channels
to push information out to citizens on a regular basis
Communications, Community Relations, and E-Marketing:
•Website
•Publicize 26@colleyville.com
•Colleyville E-News –regular placement in weekly e-blasts, plus special editions as
warranted
•Social Media: Facebook, Twitter
•Utilize new mobile app for alerts
•Media releases
•Public Meetings -attend existing community meetings as possible to provide project
updates and obtain feedback (HOAs, civic groups, etc.)
•Electronic message boards for construction updates
Marketing:
•Create marketing manual for businesses to assist them during construction
•Advertising/Advertorials as deemed beneficial to supplement communications
and marketing efforts
Discussion, Questions
and City Council
Direction
Footer Text Date
SH 26/Colleyville Boulevard
Brian R. Barth, P.E.
District Engineer
Tuesday, Oct. 28, 2014
FORT WORTH
DISTRICT
Date
Phase I Project Update (Brumlow/Pool to John McCain)
2
Let for bid August 2011
Construction began July 2012
The contractor is now allowed to work around the
clock (24/7).
TxDOT has incentivized the project with the goal of being
substantially complete by March 31
-Incentives will be reduced daily through June 10
-Starting June 11, the contractor will be penalized daily until the
project reaches substantial completion
Council Briefing –Sept. 16, 2013
3
Phase II Update (John McCain to Brown Trail)
4
Staff has developed both sections accordingly
2013 Transportation Improvement Program (TIP) Modification
–Shifted funding from John McCain to Hall Johnson section to
Hall Johnson to Brown Trail
–Changed scope from six lanes to four lanes with intersections
built to full six lane capacity
Plans are complete
–Plans have been reviewed by City and TxDOT staff
SH 26 Typical Section –John McCain to Brown Trail
5
Phase II Update (John McCain to Brown Trail)
6
Bid letting tentatively scheduled for this Winter
Mobility Coordinator will be assigned to both
SH 26 projects
Monthly executive meetings will be held with District
Engineer and City Manager
THANK YOU
Fort Worth District
INFORMATION RECEIVED
AFTER PACKETS COMPLETED:
SH26 emails
From: Jerry Boone
Sent: Saturday, October 25,
To: 26 Construction
Sub
2014 10:50 AM
We appreciate the updates and the enhanced work schedule as it has greatly helped our
daily trips.
Thanks,Jerry Boone
7019 Rosebrook
-----Original Message-----
From: Richard and Laura Ryan
Sent: Saturday, October 25, 2014 3:19 PM
To: 26 Construction
Subject: Construction Plans for Bedford Road between Glade and Cheek-Sparger
What are the pending plans for Bedford Road between Glade and Cheek-Sparger? Will
Bedford Road become a detour route during the Hwy 26 construction? If so, what is the
time frame for the change? What is the current traffic flow on Bedford Road?
Thank you,
The Ryan's
From:
Sent: Monday, October 27, 2014 7:07 AM
To: 26 Construction
Subject: HWY 26 Project
The residents of Pecan Estates need a turn lane added to HWY 26 between Hall Johnson to
Tinker. Increased traffic to the strip center and other commercial offices along this area as
well as the residential entrance at Hardage has made left and right hand turns increasingly
dangerous.Your attention to this matter is imperative.
Thank you
Comments received from people in the Caldwell Creek neighborhood (with a
request for anonymity):
I turn right onto 26 from John McCain every morning in the horrible line up of traffic. But,
this issue that I'm about to share has been occurring for years - not just connected to the
construction. Here's the issue: it seriously irritates me when someone turning left onto
26 gets in the right lane...especially if there is nobody in the left lane. I can't understand
why people feel the need to get in the right lane to turn left.
My dad is the President of the American Society of Civil Engineers (no joke) so he knows a
thing or two about this topic. He says that this intersection should have a left/straight lane
and a ricaht turn onlv lane. It should not have a left only and a left/straight/right. The cars
sit idling too long waiting to turn right.
On a happier note, it does seem like the man standing out there working the traffic signal
has greatly helped with the wait time. At one point a few weeks ago I called the city to tell
them that it took me 17 minutes to get from our neighborhood onto 26. That's
ridiculous. The city agreed and then a police officer called me back and told me that he'd
file a complaint. Apparently I wasn't the only one who complained, but that situation seems
to be fixed...for now.
Thanks for asking!
I am hoping when this project is finished that there will be a dedicated right turn lane on
John McCain for ppl that need to go south on 26. Nothing drives me crazier than the people
that are turning left and they sit in that right lane while the light is red, thus impeding the
traffic flow for those that want to turn right on the red.
Also, they need to keep that light green for longer in the AM to get the flow of cars off of
John McCain. Most mornings it is backed up all the way to our neighborhood and can take
10 minutes just to get onto 26.
Also, they need to keep the light green for longer on 26 at ]ohn McCain in the PM for the
southbound traffic. It has been backing up to the CVS. That is unacceptable.
Also, the light at Longwood Dr. when headed north on 26 changes to red for no apparent
reason sometimes. It should only change if someone going south wants to turn
left. Sometimes I've seen it turn red and no cars triggered it. Fix that!
It just doesn't seem like they understand commuting patterns. Traffic needs to flow
better. ]ust adjust the lights.
Here are concerns that should be asked/addressed, as I have talked to City personnel;
TXDOT personnel, and AUI (contractor) representatives over the past month after watching
the circus that has gone on:
1. Why is the project 9 months behind schedule (they will say it is due to the bird nest by
the bridge but thaYs an excuse as no one wants to take responsibility). And, who is putting
pressure on TXDOT to accelerate it? On most projects the contractor accelerates work to
catch up.
2. The penalty clause in the TXDOT/AUI agreement calls for a$1,500 daily penalty for each
day the project is late. (Which is terribly low for this scale of project) Who will be enforcing
that provision? And is AUI doing Phase 2 of the project too?
3. How much $$ is the city of colleyville putting into the project (note: it is over $SM, so
they should have some clout on the timing of when it can get done), but the question
should be asked in a public forum?
4. Who suggested four lanes and if only four, why was the project done at all?
5. What is timing and completion for phase 2, which will be by Market Street and cause
more disruption?
6. Seems very unorganized in terms of traffic control, timing of work etc. one day there is
police traffic control. Next day there are 6 txdot employees standing at the corner.
Added note. I just completed oversight of a$400M project in Austin. As part of it, WE built a
three lane, one mile long road privately (then sold to the county in an agreement done
before we started it). It took FIVE weeks with a private contractor to do. And it had a small
bridge.
I realize this is a state road but...... Three years.....Hope this helps.